FORM REP-I
Part - A
https://haryanarera.gov.in/view_project/project_preview_open/2602 1/43
3/20/24, 3:07 PM
3. Managing
Director/HOD/CEO:
Name : VARUN GUPTA
Residential Address : N52 PANSHIL PARK DELHI
4. Director 1:
Name : NARAYAN ANAND
Residential Address : D-03 Palacio No.216408 TTK Road
Alwarpet Chennai 600018
5. Director 2:
Name : PIYUL MUKHARJEE
Residential Address : 2702 Glen Heights Hiranandani
Gardens Powai Mumbai- 400076
https://haryanarera.gov.in/view_project/project_preview_open/2602 2/43
3/20/24, 3:07 PM
6. Director 3:
Name : ANKUR GUPTA
Residential Address : 3rdFloor C-8 Maharani Bagh New
Delhi-110065
7. Director 4:
Name : SONAL MATTOO
Residential Address : 1487 Block- K Palam Vihar
Gurgaon-122001 Haryana
8. Director 5:
Name : ABHISHEK DALMIA
Residential Address : Radha Vihar 35-B Prithviraj Road
New Delhi-110011
9. Director 6:
https://haryanarera.gov.in/view_project/project_preview_open/2602 3/43
3/20/24, 3:07 PM
10. Authorised
reprsentative for
correspondance with
Authority:
Name : ABHIJIT JOSHI
Residential Address : PMC062 DLF PRIMUS SECTOR 82
GURUGRAM
I hereby declare that the above information and particulars ase based on record and
are true to the best of my knowledge and belief and nothing has been concealed.
https://haryanarera.gov.in/view_project/project_preview_open/2602 4/43
3/20/24, 3:07 PM
FORM REP-I
Part - A
I hereby declare that the above information and particulars are based on record and
are true to the best of my knowledge and belief and nothing has been concealed.
https://haryanarera.gov.in/view_project/project_preview_open/2602 5/43
3/20/24, 3:07 PM
https://haryanarera.gov.in/view_project/project_preview_open/2602 6/43
3/20/24, 3:07 PM
FORM REP-I
Part - A
Fee Details
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development)
Rules,2017, the fee for registration of the project as has been calculated as follows:
--------------------------------------------------------------------------------------------------------------------
---
--------------------------------------------------------------------------------------------------------------------
---
--------------------------------------------------------------------------------------------------------------------
---
--------------------------------------------------------------------------------------------------------------------
---
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
19-
HRERA
2 526665 02- 3200000 ICICI BANK
Gurugram
2024
I hereby declare that the above information and particulars are based on record and
are true to the best of my knowledge and belief and nothing has been concealed.
https://haryanarera.gov.in/view_project/project_preview_open/2602 7/43
3/20/24, 3:07 PM
FORM REP-I
Part - B
I hereby declare that the above information and particulars are based on record and
are true to the best of my knowledge and belief and nothing has been concealed.
Signature of
the Applicant /
Authorised
Representative
Stamp
_____________
Date
_____________
https://haryanarera.gov.in/view_project/project_preview_open/2602 8/43
3/20/24, 3:07 PM
FORM REP-I
Part - C
Project Details:
1. Estimated cost of the project:
(Annex a copy of the project in 22851.36 Lakhs
Folder C)
i. Cost of the land (if included
1439 Lakhs
in the estimated cost)
ii. Estimated cost of
6951.86 Lakhs
construction of apartments
iii. Estimated cost of
infrastructure and other 2454 Lakhs
structures
iv. Other Costs including EDC,
12006.50 Lakhs
Taxes, Levies etc.
2. The total land of the project measuring 18268.72 Square Meters will be utilised in
the following manner:
1 PLOTS TO BE SOLD 0
4 PAVEMENTS 0
6 GREEN BELTS 0
https://haryanarera.gov.in/view_project/project_preview_open/2602 9/43
3/20/24, 3:07 PM
8 ELECTRICITY SUB-STATION 0
9 CLUB HOUSE 0
12 ANY OTHER 0
13 STREETLIGHTING 3.51
14 STROMWATERDRAINAGE 135.30
Total 18268.728
https://haryanarera.gov.in/view_project/project_preview_open/2602 10/43
3/20/24, 3:07 PM
External/
Whether Approval
connecting
taken from the
service to be
Facility agency concerned.
provided by
Yes/No (Annex
(Name the
details in folder C)
agency)
https://haryanarera.gov.in/view_project/project_preview_open/2602 11/43
3/20/24, 3:07 PM
4.Details of services and facilities which will be provided inside the project area
as per service plan estimates and/or the project report:
Remarks: Yet to be
prepared / Submitted
Estimated
to HUDA, Town &
cost (In
Country Planning
Lakhs)
Sr. Department/ as per
Name of the facility (Within
No. project report etc.
the
(Annex relevant
project
documents showing
area only)
costing details etc. in
folder C)
YET TO BE
1 INTERNAL ROADS AND PAVEMENTS 507
PREPARED
YET TO BE
2 WATER SUPPLY SYSTEM 164
PREPARED
YET TO BE
3 STORM WATER DRAINAGE 112
PREPARED
YET TO BE
4 ELECTRICITY SUPPLY SYSTEM 211
PREPARED
YET TO BE
6 STREET LIGHTING 31
PREPARED
YET TO BE
7 SECURITY AND FIRE FIGHTING 104
PREPARED
YET TO BE
8 PLAYGROUNDS AND PARKS 8
PREPARED
YET TO BE
9 CLUB HOUSE/COMMUNITY CENTRE 0
PREPARED
YET TO BE
10 SHOPPING AREA 0
PREPARED
YET TO BE
11 RENEWABLE ENERGY SYSTEM 11
PREPARED
YET TO BE
12 SCHOOL 0
PREPARED
YET TO BE
13 HOSPITAL/DISPENSARY 0
PREPARED
https://haryanarera.gov.in/view_project/project_preview_open/2602 12/43
3/20/24, 3:07 PM
YET TO BE
14 ANY OTHER 0
PREPARED
YET TO BE
16 ELECTRICITY SUBSTATION 201
PREPARED
YET TO BE
17 PARKING 574
PREPARED
YET TO BE
18 RAIN WATER HARVESTING 24
PREPARED
https://haryanarera.gov.in/view_project/project_preview_open/2602 13/43
3/20/24, 3:07 PM
7. New projects:
i) Likely date of starting the construction work 15-04-2024
ii) Likely date of completing the project 16-10-2028
iii) Sizes of the plots to be offered in the project
Apartment/Shops/Other
22943.14 224 4
Buildings
Apartment/Shops/Other
1625.64 92 1
Buildings
Apartment/Shops/Other
161.46 13 1
Buildings
https://haryanarera.gov.in/view_project/project_preview_open/2602 14/43
3/20/24, 3:07 PM
Particulars Expenditure
Apartments 0
Shops 0
Plots 0
Year-2023
Particulars
Jan-Mar Apr-June July-Sep Oct-Dec
Apartments 0 0 0 0
Shops 0 0 0 0
Plots 0 0 0 0
Other 0 0 0 0
Year-2024
Particulars
Jan-Mar Apr-June July-Sep Oct-Dec
Apartments 0 155.38 330.38 483.44
Shops 0 0 0 0
Plots 0 0 0 0
Year-2025
Particulars
Jan-Mar Apr-June July-Sep Oct-Dec
Apartments 473.90 484.61 589.81 720.51
https://haryanarera.gov.in/view_project/project_preview_open/2602 15/43
3/20/24, 3:07 PM
Shops 0 0 0 0
Plots 0 0 0 0
Year-2026
Particulars
Jan-Mar Apr-June July-Sep Oct-Dec
Apartments 957.56 820.26 564.48 556.47
Shops 0 0 0 0
Plots 0 0 0 0
Year-2027
Particulars
Jan-Mar Apr-June July-Sep Oct-Dec
Apartments 528.69 270.71 15.66 0
Shops 0 0 0 0
Plots 0 0 0 0
Year-2028
Particulars
Jan-Mar Apr-June July-Sep Oct-Dec
Apartments 0
Shops 0
Plots 0
https://haryanarera.gov.in/view_project/project_preview_open/2602 16/43
3/20/24, 3:07 PM
(d) Infrastructure
Particulars Expenditure
Roads & Pavements 0
Clubhouse/community centres 0
Shopping area 0
Other 0
https://haryanarera.gov.in/view_project/project_preview_open/2602 17/43
3/20/24, 3:07 PM
Year-2024
Particulars Jan- Apr- July-
Oct-Dec
Mar June Sep
Year-2025
Particulars Jan- Apr- July-
Oct-Dec
Mar June Sep
Roads & Pavements 0 0 0 0
Water Supply System 0 0 0 0
Shopping area 0 0 0 0
Other 0 0 0 0
Particulars Year-2026
https://haryanarera.gov.in/view_project/project_preview_open/2602 18/43
3/20/24, 3:07 PM
Clubhouse/community centres 0 0 0 0
Shopping area 0 0 0 0
Other 0 0 0 0
Electrical Sub Station 0 0 0 22
Security and Firefighting Services 0 0 0 14
Street Light 0 0 31 0
Rain Water Harvesting 0 0 0 12
Year-2027
Particulars Jan- Apr- July-
Oct-Dec
Mar June Sep
Roads & Pavements 0 384 123 0
Water Supply System 164 0 0 0
Sewerage treatment & garbage disposal 0 0 0 0
Electricity Supply System 0 0 42 94
https://haryanarera.gov.in/view_project/project_preview_open/2602 19/43
3/20/24, 3:07 PM
Year-2028
Particulars
Jan-Mar Apr-June July-Sep Oct-Dec
It is hereby stated and declared and the above information is correct and true and
nothing has been concealed or misrepresented.
https://haryanarera.gov.in/view_project/project_preview_open/2602 20/43
3/20/24, 3:07 PM
FORM REP-I
Part - D
I hereby declare that the above information and particulars are based on record and
are true to the best of my knowledge and belief and nothing has been concealed.
https://haryanarera.gov.in/view_project/project_preview_open/2602 21/43
3/20/24, 3:07 PM
FORM REP-I
Part - E
https://haryanarera.gov.in/view_project/project_preview_open/2602 22/43
3/20/24, 3:07 PM
https://haryanarera.gov.in/view_project/project_preview_open/2602 23/43
3/20/24, 3:07 PM
It is undertaken that the project shall be completed within the time schedule given in
Part C and the same will not be delayed on account of non- receipt of any of the
statutory approval. The liability for the non-receipt of any of the statutory approval shall
be that of the promoter and in case of delay, compensation as per law may be given to
the allottees.
Signature _____________
Seal _____________
Date _____________
https://haryanarera.gov.in/view_project/project_preview_open/2602 24/43
3/20/24, 3:07 PM
FORM REP-I
Part - F
I hereby declare that the above information and particulars are based on record and
are true to the best of my knowledge and belief and nothing has been concealed.
Signature of the
Applicant / Authorised
Representative
Stamp _____________
Date _____________
https://haryanarera.gov.in/view_project/project_preview_open/2602 25/43
3/20/24, 3:07 PM
FORM REP-I
Part - G
Expenditure
Initially
Revised incurred upto the
estimated
cost (In date of
cost (In
Lakhs) application (In
Lakhs)
Lakhs)
https://haryanarera.gov.in/view_project/project_preview_open/2602 26/43
3/20/24, 3:07 PM
Expenditure
Initially
Revised incurred upto the
estimated
cost (In date of
cost (In
Lakhs) application (In
Lakhs)
Lakhs)
https://haryanarera.gov.in/view_project/project_preview_open/2602 27/43
3/20/24, 3:07 PM
Expenditure
Initially
Revised incurred upto the
estimated
cost (In date of
cost (In
Lakhs) application (In
Lakhs)
Lakhs)
https://haryanarera.gov.in/view_project/project_preview_open/2602 28/43
3/20/24, 3:07 PM
https://haryanarera.gov.in/view_project/project_preview_open/2602 29/43
3/20/24, 3:07 PM
Expenditure
Initially
Revised incurred upto the
estimated
cost (In date of
cost (In
Lakhs) application (In
Lakhs)
Lakhs)
https://haryanarera.gov.in/view_project/project_preview_open/2602 30/43
3/20/24, 3:07 PM
Expenditure
Initially
Revised incurred upto the
estimated
cost (In date of
cost (In
Lakhs) application (In
Lakhs)
Lakhs)
https://haryanarera.gov.in/view_project/project_preview_open/2602 31/43
3/20/24, 3:07 PM
I hereby declare that the above information and particulars are based on record and
are true to the best of my knowledge and belief and nothing has been concealed.
https://haryanarera.gov.in/view_project/project_preview_open/2602 32/43
3/20/24, 3:07 PM
FORM REP-I
Part - H
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
LIVING/DINING, ENTRANCE FOYER, CORRIDOR
LEADING TO BEDROOMS: VITRIFIED TILES
(600X600) OR (800X800) OR (600X1200) OR
(800X1600), BEDROOMS AND STUDY ROOM:
VITRIFIED TILES OR WOODEN TEXTURE TILE,(145
FLOORING DETAILS
X 600) (600X600) OR (800X800) OR (600X1200),OPEN
1 OF VARIOUS PARTS
TERRACE: KOTA STONE/OTHER LOCAL
OF HOUSE
STONE/CERAMIC TILES OF APPROPRIATE
QUALITY/STONE MOSAIC FLOOR, STAIRCASE
:CERAMIC TILES OR KOTA STONE OR
COMBINATION LOCAL STONE OF APPROPRIATE
SIZE.
DRAWING/DINING/BEDROOMS: SAND-CEMENT
WALL FINISHING
2 PLASTER AND A COAT OF POP WITH COATING OF
DETAILS
EMULSION PAINT.
1 STAINLESS STEEL SINK WITH ONE BOWL AND A
DRAIN BOARD, 1 SWIVEL TYPE SINK MIXER, 2 CP
ANGLE VALVE FOR IN AND OUT OF HOT WATER
GEYSER, 1 CP ANGLE VALVE FOR WATER
3 KITCHEN DETAILS PURIFIER UNIT/RO, NO TAP IS PROVIDED BELOW
SINK, PROVISION FOR PIPED LPG GAS WITH LPG
METER WILL BE PROVIDED,KITCHEN CABINETS
WITH HOB, CHIMNEY, DISHWASHER. GEYSER &
EXHAUST FAN.
SANITARY WARES:
HINDWARE/ROCA/KOHLER/JAQUAR/AMERICAN
STANDARD RAK/VITRA OR EQUIVALENT BATH
FITTINGS: BASIN MIXER, WALL MIXER AND
BATHROOM
4 SHOWER OF JAQUAR/ROCA/AMERICAN
FITTINGS
STANDARD/ GROHE OR EQUIVALENT, OTHER
ANGLE VALVE EITHER OF CP OR PTMT OF
STANDARD MAKE LIKE
JAL/CONTINENTAL/PRAYAG OR EQUIVALENT.
5 WOOD WORK ETC NOT APPLICABLE.
https://haryanarera.gov.in/view_project/project_preview_open/2602 33/43
3/20/24, 3:07 PM
https://haryanarera.gov.in/view_project/project_preview_open/2602 34/43
3/20/24, 3:07 PM
https://haryanarera.gov.in/view_project/project_preview_open/2602 35/43
3/20/24, 3:07 PM
https://haryanarera.gov.in/view_project/project_preview_open/2602 36/43
3/20/24, 3:07 PM
https://haryanarera.gov.in/view_project/project_preview_open/2602 37/43
3/20/24, 3:07 PM
https://haryanarera.gov.in/view_project/project_preview_open/2602 38/43
3/20/24, 3:07 PM
I hereby declare that the above information and particulars are based on record and
are true to the best of my knowledge and belief and nothing has been concealed.
https://haryanarera.gov.in/view_project/project_preview_open/2602 39/43
3/20/24, 3:07 PM
Date of
Sr. View
Document Description Document
No. Document
Upload
COPY OF LICENSE ALONG WITH SCHEDULE OF View
1 18-12-2023
LAND Document
IN CASE OF GROUP HOUSING/ COMMERCIAL View
2 18-12-2023
SITES, A COPY OF THE APPROVED SITE PLAN Document
IN CASE OF PLOTTED COLONY, THE LATEST View
3 18-12-2023
LAYOUT PLAN Document
4 RENEWAL OF LICENSE 41 OF 2010 18-12-2023 ------
5 LC-IV 18-12-2023 ------
View
6 ZONING PLAN 18-12-2023
Document
DOCUMENTS RELATING TO THE ENTRY OF
View
7 LICENSE AND COLLABORATION AGREEMENT IN 18-12-2023
Document
THE REVENUE RECORD
8 ENVIRONMENT CLEARANCE 18-12-2023 ------
View
9 DEMARCATION PLAN 18-12-2023
Document
10 SITE PLAN 18-12-2023 ------
11 LAST THREE YEARS BALANCE SHEET 27-12-2023 ------
12 ELECTRICITY SUPPLY PLAN 26-12-2023 ------
13 STREET LIGHT PLAN 26-12-2023 ------
https://haryanarera.gov.in/view_project/project_preview_open/2602 40/43
3/20/24, 3:07 PM
https://haryanarera.gov.in/view_project/project_preview_open/2602 41/43
3/20/24, 3:07 PM
I hereby declare that the above information and particulars are based on record and
are true to the best of my knowledge and belief and nothing has been concealed.