DPR June-August 2020
DPR June-August 2020
PROGRESS
REPORT
Work Done:
Shuttering of B wing slab & beam on first floor continued.
Reinforcement work of Lift A1 on first floor at A wing is in progress.
Concreting of staircase at C wing on Ground level.
Reinforcement work of slab & beam on first floor at C wing is done.
Instruction:
Curing of first floor slab and cast columns must be done regularly.
All the details and documents of activities done after reopening of site till today
must be shared with PMC.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Saturday Date: 06/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Shuttering and centering work at B wing continued.
Reinforcement work of Lift A1 on first floor at A wing is done.
Staging work on first floor at A wing for further shuttering of second floor slab & beams.
Revised reinforcement work of beams as instructed by Mr. Magdoom started on first floor
at C wing.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
RCC Consultant Mr. Magdoom came for checking of reinforcement of slab and
B30
B9
B76 – 77
Site engineer Mr. Sarvesh Vagal instructed steel fitters to make all the changes
given by consultant
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Sunday Date: 07/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Shuttering of columns on first floor at A wing.
Curing of columns and staircase.
Outside shuttering at C wing.
Revised reinforcement work at C wing slab continued.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Monday Date: 08/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Shuttering of Lift A1 on first floor at A wing.
Beam & Slab shuttering at B wing is done.
Cutting of steel bars for the reinforcement of underground water tank at C wing.
Outside shuttering at B & C wing.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Contractor Mr. Durgesh Gadgil visited site and guided carpenters & steel fitters for
More.
Site Engineer Mr. Sarvesh Vagal said, all the changes given by RCC Consultant
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Tuesday Date: 09/06/2020
Climate:
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Concreting of lift A1 on first floor at A wing.
Reinforcement work of underground water tank at C wing is done.
Beam bottom shuttering of second floor slab at A wing started.
Shuttering of staircase landing above first floor at A wing is in progress.
Shuttering of chajja above first floor at A wing is in progress.
Shuttering of beam and slab of remaining Gala portion between B & C wing is done.
Electrical piping work on first floor through slab reinforcement at C wing.
Concreting of underground water tank at C wing.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
First floor slab at C wing is ready to be Concreted and same will be done on
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Wednesday Date: 10/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Reinforcement of girder beam at B wing.
Shuttering of staircase at C wing from ground level to first floor.
Shuttering of beam bottom and chajja at A wing continued.
De shuttering of lift A1 at A wing is done.
Shuttering of staircase at A wing from first floor to second floor continued.
Concreting of column C103A is done.
Instruction:
Guidance and instructions were given to set up the concrete pump on desired
position for proposed concreting of slab tomorrow.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Concrete pump arrived at site for the scheduled casting of slab at C wing
tomorrow.
Shuttering of staircase at C wing from ground level to first floor is not correct;
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Thursday Date: 11/06/2020
Climate:
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Reinforcement of girder beam at B wing continued.
Shuttering of beam bottom and chajja at A wing continued.
Deshuttering work of first floor slab bottom at A wing started.
Joint surface between A wing slab and C wing slab is roughened and chemical is applied
before concreting of C wing slab.
Concreting of first floor slab at C wing.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipment on site, special instructions to contractor’s site supervisor, safety measures)
Contractor Mr. Durgesh Gadgil visited site and guided carpenters & steel fitters for
More.
Site Engineer Mr. Sarvesh Vagal said, all the changes given by RCC Consultant
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Friday Date: 12/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Shuttering work of beam bottom at A wing continued.
Revised shuttering of staircase at C wing from Ground level to first floor.
Reinforcement of beams at B wing.
Deshuttering of first floor slab bottom at A wing continued.
Column starters are prepared on first floor at C wing.
Instruction:
Sarvesh Vagal and Suraj More checked column starters on first floor at C wing.
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Saturday Date: 13/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Shuttering work of beam bottom for second floor slab at A wing continued.
Reinforcement of beams at B wing continued.
Deshuttering of first floor slab bottom at A wing continued.
Outside shuttering work on first floor at B wing.
Reinforcement work of columns C26,33,36 on first floor at C wing.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Sunday Date: 14/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Shuttering work of beam bottom for second floor slab at A wing continued.
Reinforcement of beams at B wing continued.
Outside shuttering work on first floor at B wing.
Shuttering work of columns C26, 33, 36 on first floor at C wing.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Scheduled casting of columns and lift pardi cancelled due to electrical problem.
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Monday Date: 15/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Shuttering work of beam bottom at A wing continued.
Reinforcement of beams at B wing continued.
Concreting of columns C26, 33, 36 on first floor at C wing.
Concreting of lift pardi at C wing on Ground floor.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Tuesday Date: 16/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Staircase shuttering work on first floor at A wing started.
Shuttering work of beams on second floor at A wing.
De shuttering of cast columns.
Curing of slab and cast columns at C wing.
Reinforcement work in B wing on first floor continued.
Reinforcement work of columns on first floor at C wing
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Wednesday Date: 17/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Shuttering of water tank at C wing North face.
Concreting of the same water tank.
Shuttering of columns on first floor at C wing.
Reinforcement work in B wing on first floor continued.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Thursday Date: 18/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
De shuttering of columns on first floor at A wing.
Concreting of staircase at C wing from PL to first floor.
Concreting of columns on first floor at C wing.
Bar bending and cutting work for beams and columns.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Friday Date: 19/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Slab reinforcement on first floor at C wing.
Concreting of columns on first floor slab at C wing.
De shuttering of cast columns and water tank.
Beam bottom shuttering on second floor slab at A wing is done.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Saturday Date: 20/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Bar bending and cutting work.
Shuttering of lift pardi on first floor at C wing.
Outside and chajja shuttering at B wing.
Slab reinforcement on first floor at B wing continued.
Curing of cast columns.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Sunday Date: 22/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Electrical piping work through slab reinforcement on first floor at B wing.
Plumbing work in ducts on first floor slab at B wing.
Beam shuttering on second floor at A wing is done. Slab shuttering started on the same.
Concreting of lift pardi on first floor at C wing.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Sunday Date: 23/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Electrical piping work through slab reinforcement on first floor at B wing continued.
Slab shuttering on second floor at A wing continued.
Beam bottom shuttering on second floor at C wing started.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Monday Date: 24/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Setting up of RMC pump beside B wing for scheduled concreting tomorrow.
Slab shuttering on second floor at A wing continued.
Cutting and bending of steel bars.
Beam bottom shuttering on second floor at C wing continued.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Beam and slab reinforcement checking is done by Mr. Sarvesh Vagal on first floor
at B wing.
First floor slab at B wing is correct and is ready to get cast tomorrow.
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Tuesday Date: 25/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Concreting of first floor slab and beams at B wing.
Slab shuttering on second floor at A wing continued.
Cutting and bending of steel bars.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
With this first floor slab of all wings ( i.e A, B & C ) are completed.
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Wednesday Date: 26/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Curing of Concreted slab on first floor at B wing.
Beam shuttering work on second floor at C wing continued.
Slab shuttering on second floor at A wing continued.
Column starters are placed on first floor slab at B wing.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Thursday Date: 27/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Reinforcement work of columns on first floor at B wing started.
Outside chajja shuttering on second floor at A wing.
Slab shuttering on second floor at C wing started.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Friday Date: 28/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Slab shuttering on second floor at C wing continued
Shuttering of columns on first floor at B wing.
Slab and beam shuttering work is done on second floor at A wing.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Saturday Date: 29/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Concreting of columns on first floor at C wing.
Slab shuttering work on second floor at C wing continued.
Outside chajja shuttering work on second floor slab is done.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Sunday Date: 30/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Oiling of shuttering of slab and beams on second floor at A wing.
De shuttering of Concreted columns on first floor at B wing.
Slab shuttering work on second floor at C wing continued.
Concreting of columns on first floor at B wing.
Cutting and bending work of steel bars for column reinforcement.
Instruction:
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Wednesday Date: 01/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Concreting of columns on first floor C41,46,55,74,77,81,82,83,84.
Outside chajja shuttering on second floor at B & C wing.
Column reinforcement work on second floor at A wing.
Shuttering of beam and slab on second floor at B wing.
Shuttering of lift pardi on first floor at B wing.
Instruction:
Column number marking with Casting and curing date must be done.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Thursday Date: 02/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Beam reinforcement work on second floor at A wing started.
Beam bottom shuttering on second floor at B wing.
De shuttering work of cast columns on first floor.
Concreting of columns on first floor C76,78,82.
Concreting of beams on first floor at C wing at North face.
Instruction:
Shuttering dimensions guided on second floor at B wing.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Thursday Date: 06/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Reinforcement work of beams on second floor at A wing.
Beam bottom shuttering on second floor at B wing continued.
Shuttering of staircase from first floor to second floor at B wing.
Concreting of beams on first floor at North face end at C wing.
Concreting of columns on first floor C 80,106.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
No work done for past three days ( i.e. 03/07/2020 to 05/07/2020 ) due to heavy
rains.
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Tuesday Date: 07/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Reinforcement work of beams on second floor at A wing continued.
De shuttering of columns on first floor which were cast yesterday. ( i.e. C80,106)
Concreting of lift pardi on first floor at B wing.
Beam bottom shuttering work on second floor at B wing continued.
Instruction:
Shuttering must be checked with alignment, sizes of respective columns before
casting.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Shuttering and reinforcement work stopped after lunch break due to heavy rains.
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Wednesday Date: 08/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Reinforcement work of beams on second floor at A wing continued.
Curing work on first floor slab columns.
Concreting of staircase from first floor to second floor at A wing.
Beam bottom shuttering work on second floor at B wing continued.
Instruction:
Columns starter at North face end at C wing on first floor were not correct as per
drawing, so instructed carpenters not to fix starters today and wait for further
instructions.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Builder Mr. Patil and contractor Mr. Durgesh Gadgil visited site.
Senior engineer Mr. Sarvesh Vagal also said to stop fixing column starters and
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Thursday Date: 09/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Reinforcement work of slab on second floor at A wing started.
Outside shuttering on second floor slab at A wing.
Shuttering of beams and slab on second floor at C wing continued.
Site cleaning work.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Builder Mr. Patil and contractor Mr. Durgesh Gadgil visited site.
Durgesh Gadgil instructed carpenters, steel fitters for further work schedules.
Columns on first floor at C wing at North face end will be aligned by plumb with
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Friday Date: 10/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Reinforcement work of cutting bending for second floor slab at A wing.
Outside shuttering on second floor slab at A wing.
Shuttering of beams and slab on second floor at C wing continued.
Site cleaning work continued.
Concreting of 10 column starters on first floor at North face end at C wing.
Instruction:
Fixing and setting of 12 column starters were guided as per drawings.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Builder Mr. Patil and contractor Mr. Durgesh Gadgil visited site.
Electrician will come tomorrow for fixing electrical issues on site, said by
Sarvesh Vagal.
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Saturday Date: 11/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Reinforcement work of columns on first floor at C wing started.
Shuttering of reinforced columns on first floor at C wing started.
Site cleaning and clearing continued.
Shuttering of slab on second floor at B wing.
Remaining 2 columns starters at C wing on first floor concreted.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Builder Mr. Patil and contractor Mr. Durgesh Gadgil visited site.
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Sunday Date: 12/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Reinforcement work of slab on second floor at A wing.
Reinforcement work of columns on first floor at C wing completed.
Shuttering of reinforced columns on first floor at C wing started.
Concreting of 5 columns on first floor at C wing is done.
De shuttering of first floor slab at B wing started.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Monday Date: 13/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
✓ ✓
Work Done:
Reinforcement work of slab on second floor at A wing is done.
Cutting and bending work of steel bars for beams started.
Shuttering of remaining columns on first floor at C wing at North face end is done.
Concreting of 7 columns on first floor at C wing is done.
De shuttering work of first floor slab at B wing continued.
Electrical piping work through slab reinforcement on second floor at A wing is started.
Instruction:
Column plumb level should be accurate and checked before casting.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
For speedy work, 5 new steel fitters joined, more will be added to team in coming
days.
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Tuesday Date: 14/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
✓ ✓
Work Done:
Electrical piping work through slab reinforcement on second floor slab at A wing
continued.
Plumbing work, i.e. fixing pipe cut-outs through beam reinforcement to ducts in kitchen
and toilets on second floor slab at A wing is done.
Cutting bending of steel bars for further beams and columns continued.
Shuttering of staircase treads and risers in staircase on second floor at A wing.
Outer and chajja shuttering on second floor slab at A wing.
De shuttering of cast columns on first floor at C wing.
Cleaning of site and shifting of materials
Instruction:
Plumbing work according to drawings is checked.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Mr. Sarvesh Vagal informed that delay in electrical work is due to intermediate
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Wednesday Date: 15/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Electrical piping work through slab reinforcement on second floor slab at A wing
continued.
Cutting bending of steel bars for further beams and columns continued.
Beam bottom work on second floor at C wing North face end started.
Cleaning of site and shifting of materials.
Instruction:
Slab reinforcement is checked and is correct as per drawing.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Contractor Mr. Durgesh Gadgil and Builder Mr. Prasad Patil visited site for slab
checking.
All the necessary work for casting of slab is completed and slab is ready to cast
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Thursday Date: 16/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Cutting bending of steel bars for further beams and columns continued.
Cleaning of site and shifting of materials.
Instruction:
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Friday Date: 17/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
✓ ✓
Work Done:
Casting of second floor slab at A wing is done.
Cutting bending of steel bars for further beams and columns continued.
Beam bottom work on second floor at C wing North face end continued.
Instruction:
Assuring that all the cover blocks are in place and putting wherever needed.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Contractor Mr. Durgesh Gadgil and Builder Mr. Prasad Patil visited site for
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Saturday Date: 18/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Curing of cast slab on second floor at A wing.
Reinforcement work of lift and columns on second floor at A wing started.
Column starters are fixed on second floor slab at A wing.
Concreting of column starters started.
Shuttering of second floor slab at C wing at north face end.
Instruction:
Columns starters are fixed under guidance as per drawings on second floor slab at
A wing.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Contractor Mr. Durgesh Gadgil and Builder Mr. Prasad Patil visited site.
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Sunday Date: 19/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Curing of cast slab on second floor at A wing.
Reinforcement work of lift A1 and columns on second floor at A wing continued.
Concreting of column starters on second floor slab at A wing.
Shuttering of second floor slab at C wing at north face end.
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Monday Date: 20/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Curing of cast slab on second floor at A wing.
Reinforcement work of lift A2 and columns on second floor slab at A wing.
Shuttering of lift pardi A1 and columns C1,2,3,4,5,6,7,8,9 on second floor slab at A wing.
Beam and column reinforcement work on second floor slab at B wing started.
Shuttering of second floor slab at C wing at north face end is done.
Instruction:
Columns must be checked before casting according to drawings and their
verticality, as there were some adjustments found on the first floor.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Contractor Mr. Durgesh Gadgil and Builder Mr. Prasad Patil visited site.
bags.
Site Engineer Mr. Sarvesh Vagal informed that cement bags will be delivered on
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Tuesday Date: 21/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Instructed to reduce the water content in concrete to an extent without affecting
workability of concrete.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Contractor Mr. Durgesh Gadgil and Builder Mr. Prasad Patil visited site.
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Wednesday Date: 22/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
After checking of columns, shuttering of 2 columns were misplaced by 10 mm, so
instructed carpenters to correct it before casting.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Contractor Mr. Durgesh Gadgil and Builder Mr. Prasad Patil visited site.
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Thursday Date: 23/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Contractor Mr. Durgesh Gadgil and Builder Mr. Prasad Patil visited site.
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Friday Date: 24/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
✓ ✓
Work Done:
Instruction:
Verticality of columns is checked before casting and gave necessary changes in
some found any errors.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Contractor Mr. Durgesh Gadgil and Builder Mr. Prasad Patil visited site.
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Saturday Date: 25/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Instructed labour in-charge to mark date of casting and curing on columns after de
shuttering on second floor at A wing.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Contractor Mr. Durgesh Gadgil and Builder Mr. Prasad Patil visited site.
Concrete cubes of A wing second floor slab (which were casted on 17/07/2020)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Sunday Date: 26/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Monday Date: 27/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
✓ ✓
Work Done:
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Tuesday Date: 28/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
✓ ✓
Work Done:
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Cube casting is done from column concreting on second floor at A wing for
testing.
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Wednesday Date: 29/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Column starters must be fixed and cast within 2 days on first floor at C wing at
north face end.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
RCC Consultant Mr. Magdoom visited site for checking of reinforcement of slab
Mr. Prasad Patil, Mr. Durgesh Gadgil and site engineer Mr. Sarvesh Vagal also
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Thursday Date: 30/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
As per drawings there are two electrical cut outs on second floor slab at B & C
wing and it should be provided before casting of slab, sarvesh Vagal informed.
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Friday Date: 31/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Mr. Durgesh Gadgil and Mr. Prasad Patil visited site during concreting.
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Saturday Date: 01/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Joints formed after concreting between B & C wing must be break by breaker to
avoid weaker sections at that portion.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Vagal.
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Sunday Date: 02/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Monday Date: 03/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Column starters were checked as per drawings and then instructed to fix them.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Tuesday Date: 04/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Thursday Date: 06/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
✓ ✓
Work Done:
Instruction:
Found errors in column starters were fixed on second floor at B wing according to
drawings.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Column starters at B wing are fixed correctly and are ready to cast, informed by
Sarvesh Vagal.
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Friday Date: 07/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Verticality and dimensions checked and gave changes wherever needed before
casting of columns on second floor at B wing.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Saturday Date: 08/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Sunday Date: 09/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Monday Date: 10/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Needle vibrator must be used frequently while concreting.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Tuesday Date: 11/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Column position and verticality checked before casting.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Wednesday Date: 12/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Thursday Date: 13/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Friday Date: 14/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
✓ ✓
Work Done:
Instruction:
Casting and curing date must be written on columns soon after de shuttering.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Sunday Date: 16/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Monday Date: 17/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
✓ ✓
Work Done:
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Tuesday Date: 18/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Lift starter checked with grid lines in X & Y axis and dimensions and orientation.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Mr. Prasad Patil and Mr. Durgesh Gadgil visited site for witnessing laying of brick
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Wednesday Date: 19/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Thursday Date: 20/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
✓ ✓
Work Done:
Instruction:
Columns verticality checked and instructed to mark casting and curing dates on
column again.
RCC consultant Mr. Magdoom visited site for checking of reinforcement and
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Friday Date: 21/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Sunday Date: 23/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Monday Date: 24/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Final checking of third floor slab at A wing before concreting is done.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Mr. Prasad Patil and Mr. Durgesh Gadgil visited site for concreting.
Brick work has stopped as window sizes are not given, architect will visit site
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Tuesday Date: 25/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Checking of room sizes as per architecture plans done on third floor at B wing.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Architect Mr. Milind Joshi visited site for giving updates in window sizes and
other checkings.
Mr. Prasad Patil and Mr. Durgesh Gadgil also visited site with architect.
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Wednesday Date: 26/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Checking of lift pardi with orientation, alignment and sizes is done.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Thursday Date: 27/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Checking of column starters according to plans and gave necessary changes
wherever errors found.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Friday Date: 28/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Sunday Date: 30/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)
Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Monday Date: 31/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry
Work Done:
Instruction:
Lift shuttering is checked for alignment, size before casting.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)