DAILY

PROGRESS
REPORT

(JUNE 2020 TO AUGUST 2020)


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Friday Date: 05/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :5
Shuttering Carpenters : 14 Electricians :-
Plumbers :- Painters :-
M/C :7 F/C :-

Work Done:
 Shuttering of B wing slab & beam on first floor continued.
 Reinforcement work of Lift A1 on first floor at A wing is in progress.
 Concreting of staircase at C wing on Ground level.
 Reinforcement work of slab & beam on first floor at C wing is done.

Instruction:
 Curing of first floor slab and cast columns must be done regularly.
 All the details and documents of activities done after reopening of site till today
must be shared with PMC.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Saturday Date: 06/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 15 Electricians :-
Plumbers :- Painters :-
M/C :5 F/C :-

Work Done:
 Shuttering and centering work at B wing continued.
 Reinforcement work of Lift A1 on first floor at A wing is done.
 Staging work on first floor at A wing for further shuttering of second floor slab & beams.
 Revised reinforcement work of beams as instructed by Mr. Magdoom started on first floor
at C wing.

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 RCC Consultant Mr. Magdoom came for checking of reinforcement of slab and

beam on first floor at C wing.

Changes given by consultant-

To add reinforcement changes in following beams,

 B30

20 mm bars (3 nos at bottom)

 B9

12 mm bars (2 nos at top)

 B76 – 77

20 mm bars ( 2 nos at top)

Project Leader/ Senior Engineer Comments:

 Site engineer Mr. Sarvesh Vagal instructed steel fitters to make all the changes

given by consultant


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Sunday Date: 07/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :4
Shuttering Carpenters : 15 Electricians :-
Plumbers :- Painters :-
M/C :4 F/C :-

Work Done:
 Shuttering of columns on first floor at A wing.
 Curing of columns and staircase.
 Outside shuttering at C wing.
 Revised reinforcement work at C wing slab continued.

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Monday Date: 08/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 15 Electricians :-
Plumbers :- Painters :-
M/C :5 F/C :-

Work Done:
 Shuttering of Lift A1 on first floor at A wing.
 Beam & Slab shuttering at B wing is done.
 Cutting of steel bars for the reinforcement of underground water tank at C wing.
 Outside shuttering at B & C wing.

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Contractor Mr. Durgesh Gadgil visited site and guided carpenters & steel fitters for

further sequence of work.

 Revised reinforcement work of beams is checked by Sarvesh Vagal and Suraj

More.

Project Leader/ Senior Engineer Comments:

 Site Engineer Mr. Sarvesh Vagal said, all the changes given by RCC Consultant

have been implied and are correct.


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Tuesday Date: 09/06/2020
Climate:
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 18 Electricians :-
Plumbers :- Painters :-
M/C :9 F/C :-

Work Done:
 Concreting of lift A1 on first floor at A wing.
 Reinforcement work of underground water tank at C wing is done.
 Beam bottom shuttering of second floor slab at A wing started.
 Shuttering of staircase landing above first floor at A wing is in progress.
 Shuttering of chajja above first floor at A wing is in progress.
 Shuttering of beam and slab of remaining Gala portion between B & C wing is done.
 Electrical piping work on first floor through slab reinforcement at C wing.
 Concreting of underground water tank at C wing.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

Project Leader/ Senior Engineer Comments:

 First floor slab at C wing is ready to be Concreted and same will be done on


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Wednesday Date: 10/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 18 Electricians :-
Plumbers :- Painters :-
M/C :7 F/C :-

Work Done:
 Reinforcement of girder beam at B wing.
 Shuttering of staircase at C wing from ground level to first floor.
 Shuttering of beam bottom and chajja at A wing continued.
 De shuttering of lift A1 at A wing is done.
 Shuttering of staircase at A wing from first floor to second floor continued.
 Concreting of column C103A is done.

Instruction:

 Guidance and instructions were given to set up the concrete pump on desired
position for proposed concreting of slab tomorrow.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Concrete pump arrived at site for the scheduled casting of slab at C wing

tomorrow.

Project Leader/ Senior Engineer Comments:

 Shuttering of staircase at C wing from ground level to first floor is not correct;

Thus, site engineer Sarvesh Vagal asked carpenters to correct it.


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Thursday Date: 11/06/2020
Climate:
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 18 Electricians :-
Plumbers :- Painters :-
M/C : 12 F/C :-

Work Done:
 Reinforcement of girder beam at B wing continued.
 Shuttering of beam bottom and chajja at A wing continued.
 Deshuttering work of first floor slab bottom at A wing started.
 Joint surface between A wing slab and C wing slab is roughened and chemical is applied
before concreting of C wing slab.
 Concreting of first floor slab at C wing.

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipment on site, special instructions to contractor’s site supervisor, safety measures)

 Contractor Mr. Durgesh Gadgil visited site and guided carpenters & steel fitters for

further sequence of work.

 Revised reinforcement work of beams is checked by Sarvesh Vagal and Suraj

More.

Project Leader/ Senior Engineer Comments:

 Site Engineer Mr. Sarvesh Vagal said, all the changes given by RCC Consultant

have been implied and are correct.


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Friday Date: 12/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 19 Electricians :-
Plumbers :- Painters :-
M/C :4 F/C :-

Work Done:
 Shuttering work of beam bottom at A wing continued.
 Revised shuttering of staircase at C wing from Ground level to first floor.
 Reinforcement of beams at B wing.
 Deshuttering of first floor slab bottom at A wing continued.
 Column starters are prepared on first floor at C wing.

Instruction:

 Instructions were given for revised shuttering of staircase.


Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Sarvesh Vagal and Suraj More checked column starters on first floor at C wing.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Saturday Date: 13/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 19 Electricians :-
Plumbers :- Painters :-
M/C :4 F/C :-

Work Done:
 Shuttering work of beam bottom for second floor slab at A wing continued.
 Reinforcement of beams at B wing continued.
 Deshuttering of first floor slab bottom at A wing continued.
 Outside shuttering work on first floor at B wing.
 Reinforcement work of columns C26,33,36 on first floor at C wing.

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Cement and sand arrived on site.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Sunday Date: 14/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 19 Electricians :-
Plumbers :- Painters :-
M/C :6 F/C :-

Work Done:
 Shuttering work of beam bottom for second floor slab at A wing continued.
 Reinforcement of beams at B wing continued.
 Outside shuttering work on first floor at B wing.
 Shuttering work of columns C26, 33, 36 on first floor at C wing.

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Scheduled casting of columns and lift pardi cancelled due to electrical problem.

Project Leader/ Senior Engineer Comments:

 Electrical problem will be solved by today evening, said by Sarvesh Vagal.


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Monday Date: 15/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 19 Electricians :-
Plumbers :- Painters :-
M/C :7 F/C :-

Work Done:
 Shuttering work of beam bottom at A wing continued.
 Reinforcement of beams at B wing continued.
 Concreting of columns C26, 33, 36 on first floor at C wing.
 Concreting of lift pardi at C wing on Ground floor.

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Work stopped early due to heavy rains.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Tuesday Date: 16/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 19 Electricians :-
Plumbers :- Painters :-
M/C :4 F/C :-

Work Done:
 Staircase shuttering work on first floor at A wing started.
 Shuttering work of beams on second floor at A wing.
 De shuttering of cast columns.
 Curing of slab and cast columns at C wing.
 Reinforcement work in B wing on first floor continued.
 Reinforcement work of columns on first floor at C wing

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Contractor Mr. Durgesh Gadgil visited site.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Wednesday Date: 17/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 20 Electricians :-
Plumbers :- Painters :-
M/C :6 F/C :-

Work Done:
 Shuttering of water tank at C wing North face.
 Concreting of the same water tank.
 Shuttering of columns on first floor at C wing.
 Reinforcement work in B wing on first floor continued.

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Thursday Date: 18/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 20 Electricians :-
Plumbers :- Painters :-
M/C :7 F/C :-

Work Done:
 De shuttering of columns on first floor at A wing.
 Concreting of staircase at C wing from PL to first floor.
 Concreting of columns on first floor at C wing.
 Bar bending and cutting work for beams and columns.

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Needle broke during concreting. Hence, concreting of columns stopped.

 Durgesh gadgil visited.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Friday Date: 19/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 20 Electricians :-
Plumbers :- Painters :-
M/C :8 F/C :-

Work Done:
 Slab reinforcement on first floor at C wing.
 Concreting of columns on first floor slab at C wing.
 De shuttering of cast columns and water tank.
 Beam bottom shuttering on second floor slab at A wing is done.

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Saturday Date: 20/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 19 Electricians :-
Plumbers :- Painters :-
M/C :5 F/C :-

Work Done:
 Bar bending and cutting work.
 Shuttering of lift pardi on first floor at C wing.
 Outside and chajja shuttering at B wing.
 Slab reinforcement on first floor at B wing continued.
 Curing of cast columns.

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 No work is scheduled tomorrow ( i.e. 21/06/2020) because of solar eclipse.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Sunday Date: 22/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 19 Electricians :2
Plumbers :- Painters :-
M/C :7 F/C :-

Work Done:
 Electrical piping work through slab reinforcement on first floor at B wing.
 Plumbing work in ducts on first floor slab at B wing.
 Beam shuttering on second floor at A wing is done. Slab shuttering started on the same.
 Concreting of lift pardi on first floor at C wing.

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Sunday Date: 23/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 19 Electricians :2
Plumbers :- Painters :-
M/C :5 F/C :-

Work Done:
 Electrical piping work through slab reinforcement on first floor at B wing continued.
 Slab shuttering on second floor at A wing continued.
 Beam bottom shuttering on second floor at C wing started.

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Monday Date: 24/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 19 Electricians :-
Plumbers :- Painters :-
M/C :5 F/C :-

Work Done:
 Setting up of RMC pump beside B wing for scheduled concreting tomorrow.
 Slab shuttering on second floor at A wing continued.
 Cutting and bending of steel bars.
 Beam bottom shuttering on second floor at C wing continued.

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Beam and slab reinforcement checking is done by Mr. Sarvesh Vagal on first floor

at B wing.

Project Leader/ Senior Engineer Comments:

 First floor slab at B wing is correct and is ready to get cast tomorrow.


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Tuesday Date: 25/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :5
Shuttering Carpenters : 19 Electricians :
Plumbers :- Painters :-
M/C : 12 F/C :-

Work Done:
 Concreting of first floor slab and beams at B wing.
 Slab shuttering on second floor at A wing continued.
 Cutting and bending of steel bars.

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Casting of first floor slab at B wing is done.

 With this first floor slab of all wings ( i.e A, B & C ) are completed.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Wednesday Date: 26/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :5
Shuttering Carpenters : 19 Electricians :
Plumbers :- Painters :-
M/C :5 F/C :-

Work Done:
 Curing of Concreted slab on first floor at B wing.
 Beam shuttering work on second floor at C wing continued.
 Slab shuttering on second floor at A wing continued.
 Column starters are placed on first floor slab at B wing.

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Thursday Date: 27/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :5
Shuttering Carpenters : 19 Electricians :
Plumbers :- Painters :-
M/C :6 F/C :-

Work Done:
 Reinforcement work of columns on first floor at B wing started.
 Outside chajja shuttering on second floor at A wing.
 Slab shuttering on second floor at C wing started.

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Friday Date: 28/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :5
Shuttering Carpenters : 18 Electricians :
Plumbers :- Painters :-
M/C :5 F/C :-

Work Done:
 Slab shuttering on second floor at C wing continued
 Shuttering of columns on first floor at B wing.
 Slab and beam shuttering work is done on second floor at A wing.

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Saturday Date: 29/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :5
Shuttering Carpenters : 19 Electricians :
Plumbers :- Painters :-
M/C :9 F/C :-

Work Done:
 Concreting of columns on first floor at C wing.
 Slab shuttering work on second floor at C wing continued.
 Outside chajja shuttering work on second floor slab is done.

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day: Sunday Date: 30/06/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :5
Shuttering Carpenters : 18 Electricians :
Plumbers :- Painters :-
M/C : 10 F/C :-

Work Done:
 Oiling of shuttering of slab and beams on second floor at A wing.
 De shuttering of Concreted columns on first floor at B wing.
 Slab shuttering work on second floor at C wing continued.
 Concreting of columns on first floor at B wing.
 Cutting and bending work of steel bars for column reinforcement.

Instruction:

 Reinforcement joggling is observed in several locations, told steel fitters to


minimise it.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Wednesday Date: 01/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :5
Shuttering Carpenters : 19 Electricians :-
Plumbers :- Painters :-
M/C : 10 F/C :-

Work Done:
 Concreting of columns on first floor C41,46,55,74,77,81,82,83,84.
 Outside chajja shuttering on second floor at B & C wing.
 Column reinforcement work on second floor at A wing.
 Shuttering of beam and slab on second floor at B wing.
 Shuttering of lift pardi on first floor at B wing.

Instruction:
 Column number marking with Casting and curing date must be done.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Thursday Date: 02/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 19 Electricians :-
Plumbers :- Painters :-
M/C : 10 F/C :-

Work Done:
 Beam reinforcement work on second floor at A wing started.
 Beam bottom shuttering on second floor at B wing.
 De shuttering work of cast columns on first floor.
 Concreting of columns on first floor C76,78,82.
 Concreting of beams on first floor at C wing at North face.

Instruction:
 Shuttering dimensions guided on second floor at B wing.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Thursday Date: 06/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :5
Shuttering Carpenters : 18 Electricians :-
Plumbers :- Painters :-
M/C :8 F/C :-

Work Done:
 Reinforcement work of beams on second floor at A wing.
 Beam bottom shuttering on second floor at B wing continued.
 Shuttering of staircase from first floor to second floor at B wing.
 Concreting of beams on first floor at North face end at C wing.
 Concreting of columns on first floor C 80,106.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 No work done for past three days ( i.e. 03/07/2020 to 05/07/2020 ) due to heavy

rains.

 Site contractor Mr. Durgesh Gadgil visited site.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Tuesday Date: 07/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :5
Shuttering Carpenters : 16 Electricians :-
Plumbers :- Painters :-
M/C : 10 F/C :-

Work Done:
 Reinforcement work of beams on second floor at A wing continued.
 De shuttering of columns on first floor which were cast yesterday. ( i.e. C80,106)
 Concreting of lift pardi on first floor at B wing.
 Beam bottom shuttering work on second floor at B wing continued.

Instruction:
 Shuttering must be checked with alignment, sizes of respective columns before
casting.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Shuttering and reinforcement work stopped after lunch break due to heavy rains.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Wednesday Date: 08/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :5
Shuttering Carpenters : 16 Electricians :-
Plumbers :- Painters :-
M/C : 12 F/C :-

Work Done:
 Reinforcement work of beams on second floor at A wing continued.
 Curing work on first floor slab columns.
 Concreting of staircase from first floor to second floor at A wing.
 Beam bottom shuttering work on second floor at B wing continued.

Instruction:
 Columns starter at North face end at C wing on first floor were not correct as per
drawing, so instructed carpenters not to fix starters today and wait for further
instructions.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Builder Mr. Patil and contractor Mr. Durgesh Gadgil visited site.

Project Leader/ Senior Engineer Comments:

 Senior engineer Mr. Sarvesh Vagal also said to stop fixing column starters and

wait for tomorrow.


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Thursday Date: 09/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :5
Shuttering Carpenters : 14 Electricians :-
Plumbers :- Painters :-
M/C :8 F/C :-

Work Done:
 Reinforcement work of slab on second floor at A wing started.
 Outside shuttering on second floor slab at A wing.
 Shuttering of beams and slab on second floor at C wing continued.
 Site cleaning work.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Builder Mr. Patil and contractor Mr. Durgesh Gadgil visited site.

 Durgesh Gadgil instructed carpenters, steel fitters for further work schedules.

Project Leader/ Senior Engineer Comments:

 Columns on first floor at C wing at North face end will be aligned by plumb with

ground floor level, said by Sarvesh Vagal.


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Friday Date: 10/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :4
Shuttering Carpenters : 14 Electricians :-
Plumbers :- Painters :-
M/C :7 F/C :-

Work Done:
 Reinforcement work of cutting bending for second floor slab at A wing.
 Outside shuttering on second floor slab at A wing.
 Shuttering of beams and slab on second floor at C wing continued.
 Site cleaning work continued.
 Concreting of 10 column starters on first floor at North face end at C wing.

Instruction:
 Fixing and setting of 12 column starters were guided as per drawings.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Builder Mr. Patil and contractor Mr. Durgesh Gadgil visited site.

 Water tanker with pump arrived on site.

Project Leader/ Senior Engineer Comments:

 Electrician will come tomorrow for fixing electrical issues on site, said by

Sarvesh Vagal.


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Saturday Date: 11/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :4
Shuttering Carpenters : 14 Electricians :-
Plumbers :- Painters :-
M/C :6 F/C :-

Work Done:
 Reinforcement work of columns on first floor at C wing started.
 Shuttering of reinforced columns on first floor at C wing started.
 Site cleaning and clearing continued.
 Shuttering of slab on second floor at B wing.
 Remaining 2 columns starters at C wing on first floor concreted.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Builder Mr. Patil and contractor Mr. Durgesh Gadgil visited site.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Sunday Date: 12/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 17 Electricians :-
Plumbers :- Painters :-
M/C :8 F/C :-

Work Done:
 Reinforcement work of slab on second floor at A wing.
 Reinforcement work of columns on first floor at C wing completed.
 Shuttering of reinforced columns on first floor at C wing started.
 Concreting of 5 columns on first floor at C wing is done.
 De shuttering of first floor slab at B wing started.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Monday Date: 13/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

✓ ✓

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :9
Shuttering Carpenters : 12 Electricians :6
Plumbers :- Painters :-
M/C :8 F/C :-

Work Done:
 Reinforcement work of slab on second floor at A wing is done.
 Cutting and bending work of steel bars for beams started.
 Shuttering of remaining columns on first floor at C wing at North face end is done.
 Concreting of 7 columns on first floor at C wing is done.
 De shuttering work of first floor slab at B wing continued.
 Electrical piping work through slab reinforcement on second floor at A wing is started.

Instruction:
 Column plumb level should be accurate and checked before casting.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Contractor Mr. Durgesh Gadgil visited site.

 For speedy work, 5 new steel fitters joined, more will be added to team in coming

days.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Tuesday Date: 14/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

✓ ✓

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :9
Shuttering Carpenters : 15 Electricians :4
Plumbers :2 Painters :-
M/C :8 F/C :-

Work Done:
 Electrical piping work through slab reinforcement on second floor slab at A wing
continued.
 Plumbing work, i.e. fixing pipe cut-outs through beam reinforcement to ducts in kitchen
and toilets on second floor slab at A wing is done.
 Cutting bending of steel bars for further beams and columns continued.
 Shuttering of staircase treads and risers in staircase on second floor at A wing.
 Outer and chajja shuttering on second floor slab at A wing.
 De shuttering of cast columns on first floor at C wing.
 Cleaning of site and shifting of materials

Instruction:
 Plumbing work according to drawings is checked.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Contractor Mr. Durgesh Gadgil visited site.

 Concreting of second floor slab at A wing is postponed by 1 to 2 days due to delay

in electrical pipe fitting work.

 Work stopped after afternoon due to heavy rains.

Project Leader/ Senior Engineer Comments:

 Mr. Sarvesh Vagal informed that delay in electrical work is due to intermediate

rain from past 2 days.


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Wednesday Date: 15/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 12 Electricians :4
Plumbers :- Painters :-
M/C :6 F/C :-

Work Done:
 Electrical piping work through slab reinforcement on second floor slab at A wing
continued.
 Cutting bending of steel bars for further beams and columns continued.
 Beam bottom work on second floor at C wing North face end started.
 Cleaning of site and shifting of materials.

Instruction:
 Slab reinforcement is checked and is correct as per drawing.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Concreting of second floor slab at A wing is scheduled tomorrow.

 Contractor Mr. Durgesh Gadgil and Builder Mr. Prasad Patil visited site for slab

checking.

Project Leader/ Senior Engineer Comments:

 All the necessary work for casting of slab is completed and slab is ready to cast

tomorrow, Site Engineer Mr. Sarvesh Vagal confirmed.


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Thursday Date: 16/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 12 Electricians :-
Plumbers :- Painters :-
M/C :6 F/C :-

Work Done:
 Cutting bending of steel bars for further beams and columns continued.
 Cleaning of site and shifting of materials.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and


equipments on site, special instructions to contractor’s site supervisor, safety
measures)
 Concreting of second floor slab at A wing is cancelled due to heavy rains.

 No major work is commenced on site due to heavy rains.

Project Leader/ Senior Engineer Comments:

 Casting of slab is postponed to tomorrow, Mr. Sarvesh Vagal informed.


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Friday Date: 17/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

✓ ✓

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :7
Shuttering Carpenters : 14 Electricians :-
Plumbers :- Painters :-
M/C : 19 F/C :-

Work Done:
 Casting of second floor slab at A wing is done.
 Cutting bending of steel bars for further beams and columns continued.
 Beam bottom work on second floor at C wing North face end continued.

Instruction:
 Assuring that all the cover blocks are in place and putting wherever needed.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Contractor Mr. Durgesh Gadgil and Builder Mr. Prasad Patil visited site for

witnessing casting of slab.

 Concreting of second floor slab at A wing is completed. (56.5 Cu.m)

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Saturday Date: 18/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :8
Shuttering Carpenters : 17 Electricians :-
Plumbers :- Painters :-
M/C :8 F/C :-

Work Done:
 Curing of cast slab on second floor at A wing.
 Reinforcement work of lift and columns on second floor at A wing started.
 Column starters are fixed on second floor slab at A wing.
 Concreting of column starters started.
 Shuttering of second floor slab at C wing at north face end.

Instruction:
 Columns starters are fixed under guidance as per drawings on second floor slab at
A wing.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Contractor Mr. Durgesh Gadgil and Builder Mr. Prasad Patil visited site.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Sunday Date: 19/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :7
Shuttering Carpenters : 15 Electricians :-
Plumbers :- Painters :-
M/C :8 F/C :-

Work Done:
 Curing of cast slab on second floor at A wing.
 Reinforcement work of lift A1 and columns on second floor at A wing continued.
 Concreting of column starters on second floor slab at A wing.
 Shuttering of second floor slab at C wing at north face end.

Instruction:
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 River sand of quantity 9 brass arrived on site.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Monday Date: 20/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :8
Shuttering Carpenters : 17 Electricians :-
Plumbers :- Painters :-
M/C :6 F/C :-

Work Done:
 Curing of cast slab on second floor at A wing.
 Reinforcement work of lift A2 and columns on second floor slab at A wing.
 Shuttering of lift pardi A1 and columns C1,2,3,4,5,6,7,8,9 on second floor slab at A wing.
 Beam and column reinforcement work on second floor slab at B wing started.
 Shuttering of second floor slab at C wing at north face end is done.

Instruction:
 Columns must be checked before casting according to drawings and their
verticality, as there were some adjustments found on the first floor.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Contractor Mr. Durgesh Gadgil and Builder Mr. Prasad Patil visited site.

 Concreting of columns and starters got cancelled due to unavailability of cement

bags.

Project Leader/ Senior Engineer Comments:

 Site Engineer Mr. Sarvesh Vagal informed that cement bags will be delivered on

site by today evening.


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Tuesday Date: 21/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :7
Shuttering Carpenters : - Electricians :-
Plumbers :- Painters :-
M/C :9 F/C :-

Work Done:

 Curing of cast slab on second floor at A wing.


 Reinforcement work of beams on second floor slab at B wing.
 Concreting of column starters on second floor slab at A wing.
 Concreting of columns C1,2,3,4,5,6,7,8,9 is done on second floor at A wing.

Instruction:
 Instructed to reduce the water content in concrete to an extent without affecting
workability of concrete.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Cement bags ( 240 Nos.) delivered on site in morning.

 Contractor Mr. Durgesh Gadgil and Builder Mr. Prasad Patil visited site.

 No carpentry work done today.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Wednesday Date: 22/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :7
Shuttering Carpenters : 8 Electricians :-
Plumbers :- Painters :-
M/C :9 F/C :-

Work Done:

 Curing of cast slab on second floor at A wing.


 Concreting of remaining beams on first floor at C wing at north face end.
 Reinforcement work of beams on second floor at B wing is done.
 Shuttering of columns C10, 11A, 11, 17, 18, 19, 20, 21, 22, 25 on second floor slab
at A wing.
 Concreting of columns C10, 11A, 11 on second floor slab at A wing.

Instruction:
 After checking of columns, shuttering of 2 columns were misplaced by 10 mm, so
instructed carpenters to correct it before casting.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Mix Aggregate of quantity 4.35 brass arrived on site.

 Contractor Mr. Durgesh Gadgil and Builder Mr. Prasad Patil visited site.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Thursday Date: 23/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :8
Shuttering Carpenters : 15 Electricians :-
Plumbers :- Painters :-
M/C :9 F/C :-

Work Done:

 Curing of cast slab on second floor at A wing.


 De shuttering of columns and beam which were cast yesterday.
 Shuttering of staircase at A wing from second floor to mid landing.
 Shuttering of remaining beams on first floor at C wing at north face end.
 Reinforcement work of chajja on second floor at B wing.
 Concreting of staircase at B wing from first floor to second floor.
 Concreting of remaining slab portion on second floor at A wing.
 Beam bottom work started on third floor at A wing.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Shuttering ply arrived on site.

 Contractor Mr. Durgesh Gadgil and Builder Mr. Prasad Patil visited site.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Friday Date: 24/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

✓ ✓

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :7
Shuttering Carpenters : 13 Electricians :-
Plumbers :- Painters :-
M/C :9 F/C :-

Work Done:

 Curing of cast slab on second floor at A wing.


 De shuttering of beams which were cast on previous day.
 Beam bottom shuttering work on third floor at A wing continued.
 Outside shuttering on second floor slab at B wing.
 Reinforcement work of beams on second floor at C wing.
 Cutting and bending of reinforcement for second floor slab at B wing.
 Concreting of columns C17,18,19,21,22,23,25 on second floor at a wing.
 Concreting of remaining beams on first floor at c wing at north face end.

Instruction:
 Verticality of columns is checked before casting and gave necessary changes in
some found any errors.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Contractor Mr. Durgesh Gadgil and Builder Mr. Prasad Patil visited site.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Saturday Date: 25/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :7
Shuttering Carpenters : 15 Electricians :-
Plumbers :- Painters :-
M/C : 11 F/C :-

Work Done:

 Curing of cast slab on second floor at A wing.


 De shuttering of columns which were cast on previous day.
 Beam bottom shuttering work on third floor at A wing continued.
 Outside shuttering on second floor slab at B wing continued.
 Reinforcement work of beams on second floor at C wing continued.
 Cutting and bending of reinforcement for second floor slab at B wing continued.
 Concreting of lift pardi on second floor at A wing.

Instruction:
 Instructed labour in-charge to mark date of casting and curing on columns after de
shuttering on second floor at A wing.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Contractor Mr. Durgesh Gadgil and Builder Mr. Prasad Patil visited site.

 Concrete cubes of A wing second floor slab (which were casted on 17/07/2020)

picked up by urban lab for testing.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Sunday Date: 26/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :7
Shuttering Carpenters : - Electricians :-
Plumbers :- Painters :-
M/C :- F/C :-

Work Done:

 Curing of cast slab on second floor at A wing.


 Slab reinforcement work on second floor slab at B wing started.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 22.16 tonnes steel delivered on site.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Monday Date: 27/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

✓ ✓

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :7
Shuttering Carpenters : - Electricians :-
Plumbers :- Painters :-
M/C :- F/C :-

Work Done:

 Curing of cast slab on second floor at A wing.


 Slab reinforcement work on second floor slab at B wing continued.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 No carpentry and labour work done since yesterday.

 Aggregates delivered on site. (10mm – 4.07 brass, 20mm – 4.07 brass)

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Tuesday Date: 28/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

✓ ✓

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :7
Shuttering Carpenters : 11 Electricians :4
Plumbers :- Painters :-
M/C : 10 F/C :-

Work Done:

 Curing of cast slab on second floor at A wing.


 Slab reinforcement work on second floor slab at B wing is done.
 Electrical piping work on second floor slab at B wing started.
 Outer shuttering on second floor slab at B wing.
 Concreting of columns C20,24,26,27 on second floor at A wing.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Cube casting is done from column concreting on second floor at A wing for

testing.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Wednesday Date: 29/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :-
Shuttering Carpenters : 14 Electricians :4
Plumbers :- Painters :-
M/C :6 F/C :-

Work Done:

 Curing of cast slab on second floor at A wing.


 Material shifting work is done.
 Outer shuttering work on second floor slab at B wing continued.
 Electrical piping work through slab reinforcement on second floor slab at B wing
continued.
 De shuttering of cast columns on second floor slab at A wing.

Instruction:
 Column starters must be fixed and cast within 2 days on first floor at C wing at
north face end.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 RCC Consultant Mr. Magdoom visited site for checking of reinforcement of slab

on second floor at B wing.

 Mr. Prasad Patil, Mr. Durgesh Gadgil and site engineer Mr. Sarvesh Vagal also

checked reinforcement with RCC Consultant.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Thursday Date: 30/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :4
Shuttering Carpenters : 14 Electricians :4
Plumbers :2 Painters :-
M/C :9 F/C :-

Work Done:

 Concreting of lift pardi on second floor slab at A wing.


 Column starters are fixed on first floor at C wing at north face end.
 Beam bottom shuttering work on third floor at A wing.
 De shuttering work of second floor slab at A wing.
 Cutting and bending of steel bars.
 Concreting of staircase from first floor to second floor at C wing.
 Electrical piping work through slab reinforcement on second floor slab at B wing
continued.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Cement bags delivered on site. (240 nos.)

Project Leader/ Senior Engineer Comments:

 As per drawings there are two electrical cut outs on second floor slab at B & C

wing and it should be provided before casting of slab, sarvesh Vagal informed.


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Friday Date: 31/07/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :4
Shuttering Carpenters : 14 Electricians :-
Plumbers :- Painters :-
M/C : 18 F/C :-

Work Done:

 Concreting of second floor slab at B wing is done.


 Concreting of half portion of C wing second floor slab is done.
 Beam bottom shuttering work on third floor at A wing.
 Cutting and bending of steel bars.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Casting of second floor slab at B wing is done. ( 68.5 Cu.m)

 Mr. Durgesh Gadgil and Mr. Prasad Patil visited site during concreting.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Saturday Date: 01/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :4
Shuttering Carpenters : 12 Electricians :-
Plumbers :- Painters :-
M/C :- F/C :-

Work Done:

 Curing of second floor slab at B wing.


 De shuttering of slab on second floor at A wing.
 Shuttering work of beams and slab on third floor at A wing.
 Cutting and bending of steel bars for columns on second floor at B wing.

Instruction:
 Joints formed after concreting between B & C wing must be break by breaker to
avoid weaker sections at that portion.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Mr. Prasad Patil visited site.

Project Leader/ Senior Engineer Comments:

 Concrete joints will be crushed before evening today, informed by Sarvesh

Vagal.


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Sunday Date: 02/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers :- Jr. Engineer : -


Masons :- Steel Fitters :4
Shuttering Carpenters : 12 Electricians :-
Plumbers :- Painters :-
M/C :- F/C :-

Work Done:

 Curing of second floor slab at B wing.


 De shuttering of slab on second floor at A wing continued.
 Shuttering work of beams and slab on third floor at A wing continued.
 Cutting and bending of steel bars for columns on second floor at B wing continued.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Monday Date: 03/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :-
Shuttering Carpenters : 12 Electricians :-
Plumbers :- Painters :-
M/C :7 F/C :-

Work Done:

 Curing of second floor slab at B wing.


 De shuttering of slab on second floor at A wing continued.
 Shuttering work of beams and slab on third floor at A wing continued.
 Fixing and casting of column starters on first floor at C wing.
 Concreting of remaining portion of slab on second floor at C wing.

Instruction:
 Column starters were checked as per drawings and then instructed to fix them.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 No reinforcement work done today.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Tuesday Date: 04/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :8
Shuttering Carpenters : - Electricians :-
Plumbers :- Painters :-
M/C :- F/C :-

Work Done:

 Reinforcement work of columns on second floor slab at B wing started.


 Reinforcement work of columns on first floor at C wing at north face end.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 No carpentry and concreting work done today due to heavy rains.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Thursday Date: 06/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

✓ ✓

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :7
Shuttering Carpenters : 10 Electricians :2
Plumbers :- Painters :-
M/C :6 F/C :-

Work Done:

 Fixing and casting of 10 column starters on second floor slab at B wing.


 Hatching of columns and beams at A wing.
 Cutting and bending work of steel bars for slab and beam reinforcement on third floor at A
wing.
 Electrical board fitting on ground floor.

Instruction:
 Found errors in column starters were fixed on second floor at B wing according to
drawings.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Site was shut yesterday (05/08/2020) due to heavy rains.

 Cement bags delivered on site. ( 200 Nos.)

Project Leader/ Senior Engineer Comments:

 Column starters at B wing are fixed correctly and are ready to cast, informed by

Sarvesh Vagal.


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Friday Date: 07/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :7
Shuttering Carpenters : 12 Electricians :-
Plumbers :- Painters :-
M/C :9 F/C :-

Work Done:

 Reinforcement work of columns on second floor slab at B wing.


 Reinforcement work of lift pardi on second floor at B wing.
 Shuttering of columns on second floor slab at B wing.
 Fixing of column starters on second floor at B wing.
 Concreting of 7 columns C74, 75, 77, 78, 79, 80, 81 on second floor slab at B wing.

Instruction:
 Verticality and dimensions checked and gave changes wherever needed before
casting of columns on second floor at B wing.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Mr. Durgesh Gadgil and Mr. Prasad Patil visited site.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Saturday Date: 08/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 14 Electricians :-
Plumbers :- Painters :-
M/C :9 F/C :-

Work Done:

 Shuttering of columns on second floor at B wing.


 De shuttering of cast columns on second floor at B wing.
 Fixing starters of columns and lift pardi on second floor at B wing.
 Cutting and bending work of steel bars for further reinforcement.
 Concreting of 5 columns C82, 83, 84, 85, 86 on second floor at B wing.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Mr. Durgesh Gadgil and Mr. Prasad Patil visited site.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Sunday Date: 09/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers :- Jr. Engineer : -


Masons :- Steel Fitters :4
Shuttering Carpenters : 12 Electricians :-
Plumbers :- Painters :-
M/C :5 F/C :-

Work Done:

 Curing of second floor slab at B wing.


 Shifting of materials on site.
 Hatching of columns and beams on first floor.
 Shuttering of 6 columns on second floor at C wing.
 Cutting bending and shifting of steel reinforcement on third floor slab at A wing.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Monday Date: 10/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :8
Shuttering Carpenters : - Electricians :-
Plumbers :- Painters :-
M/C : 11 F/C :-

Work Done:

 Curing of second floor slab at B wing.


 Concreting of column and lift starters on second floor slab at B wing.
 Concreting of lift pardi on second floor slab at B wing.
 Hatching of columns and beams on first floor.
 Beam reinforcement work on third floor slab at A wing started.

Instruction:
 Needle vibrator must be used frequently while concreting.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Mr. Durgesh Gadgil and Mr. Prasad Patil visited site.

 No carpentry work done today.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Tuesday Date: 11/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :8
Shuttering Carpenters : 12 Electricians :-
Plumbers :- Painters :-
M/C : 10 F/C :-

Work Done:

 Curing of second floor slab at B wing.


 Shuttering of column and lift pardi on second floor slab at B wing.
 Concreting of 7 columns C33,36,37,37A,42,49,56 on second floor slab at B & C wing.
 Hatching of columns and lift pardi on second floor at B wing.
 Reinforcement work of beams on third floor slab at A wing continued.

Instruction:
 Column position and verticality checked before casting.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Mr. Durgesh Gadgil and Mr. Prasad Patil visited site.

 Bricks delivered on site for masonry work.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Wednesday Date: 12/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal Jr. Engineer : Suraj More


Masons :- Steel Fitters :4
Shuttering Carpenters : 8 Electricians :-
Plumbers :- Painters :-
M/C :- F/C :-

Work Done:

 Outer support shuttering on third floor slab at A wing.


 Shuttering of 5 columns on second floor at B wing.
 Hatching of columns on second floor.
 Reinforcement of beams on third floor slab is done.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Work stopped after lunch break due to heavy rains.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Thursday Date: 13/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal, Amol Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 14 Electricians :-
Plumbers :- Painters :-
M/C : 12 F/C :-

Work Done:

 Outer support shuttering on third floor slab at A wing continued.


 Beam bottom shuttering on third floor at C wing started.
 Concreting of lift pardi B1 and columns C58,59,62,63,65,66,68 on second floor at B wing.
 Shifting of steel on third floor for slab reinforcement.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Mr. Prasad Patil and Mr. Durgesh Gadgil visited site.

 Contractors engineer Mr. Amol re-joined site work from today.

 Bricks ( 6 inch) delivered on site.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Friday Date: 14/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

✓ ✓

Site Engineers : Sarvesh Vagal, Amol Jr. Engineer : Suraj More


Masons :- Steel Fitters :8
Shuttering Carpenters : 14 Electricians :-
Plumbers :- Painters :-
M/C :8 F/C :-

Work Done:

 Beam bottom shuttering on third floor at B wing started.


 De-shuttering of previous day cast columns and lift pardi.
 Shuttering of columns C64,67,72 on second floor at B wing.
 Shifting of bricks on first floor at A wing for brickwork of walls.
 Hatching of columns on second floor at B wing.
 Reinforcement work of top slab of underground water tank at B wing.
 Reinforcement of staircase from second floor to third floor at A wing.

Instruction:
 Casting and curing date must be written on columns soon after de shuttering.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Mr. Prasad Patil and Mr. Durgesh Gadgil visited site.

 Site will be shut tomorrow due to national holiday of independence day.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Sunday Date: 16/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Amol Jr. Engineer :


Masons :- Steel Fitters :6
Shuttering Carpenters : 12 Electricians :-
Plumbers :- Painters :-
M/C : 10 F/C :-

Work Done:

 Beam bottom shuttering on third floor at B wing continued.


 Concreting of slab portion and chajja in front of lift on second floor at C wing.
 Concreting of 3 columns C64,67,72 on second floor slab at B wing.
 Shifting of steel bars on third floor at A wing for slab reinforcement work.
 Reinforcement work of top slab of underground water tank at B wing north face is done.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Monday Date: 17/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

✓ ✓

Site Engineers : Sarvesh Vagal, Amol Jr. Engineer : Suraj More


Masons :- Steel Fitters :8
Shuttering Carpenters : 14 Electricians :-
Plumbers :- Painters :-
M/C :9 F/C :-

Work Done:

 Beam bottom shuttering on third floor at B wing continued.


 De-shuttering of 3 cast columns on second floor at B wing.
 Shuttering of columns C57,60 on second floor at B wing.
 Shuttering work of staircase from second floor to third floor at A wing.
 Concreting of top slab of underground water tank at B wing north face.
 Reinforcement work of slab on third floor at A wing started.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Mr. Durgesh Gadgil visited site.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Tuesday Date: 18/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal, Amol Jr. Engineer : Suraj More


Masons :2 Steel Fitters :-
Shuttering Carpenters : 14 Electricians :2
Plumbers :- Painters :-
M/C :8 F/C :-

Work Done:

 Beam bottom and slab shuttering on third floor at B wing continued.


 Layout of bricks for walls on first floor at A wing.
 Shuttering of lift pardi starter on second floor at C wing.
 Electrical piping work through reinforcement on slab at third floor and staircase.
 Shifting of river sand and other materials.

Instruction:
 Lift starter checked with grid lines in X & Y axis and dimensions and orientation.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Mr. Prasad Patil and Mr. Durgesh Gadgil visited site for witnessing laying of brick

starters for walls on first floor at A wing.

 No reinforcement work done today.

 River sand ( 6 Brass ) delivered on site.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Wednesday Date: 19/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal, Amol Jr. Engineer : Suraj More


Masons :- Steel Fitters :8
Shuttering Carpenters : 14 Electricians :2
Plumbers :- Painters :-
M/C : 12 F/C :-

Work Done:

 Beam bottom and slab shuttering on third floor at B wing continued.


 Shuttering of column C76 on second floor at B wing.
 Concreting of columns C57,60 on second floor at C wing.
 Concreting of staircase from second floor to third floor at A wing.
 Reinforcement work of slab on third floor at A wing.
 Electrical piping work through reinforcement on slab at third floor continued.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Mr. Durgesh Gadgil visited site.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Thursday Date: 20/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

✓ ✓

Site Engineers : Sarvesh Vagal, Amol Jr. Engineer : Suraj More


Masons :- Steel Fitters :8
Shuttering Carpenters : 14 Electricians :3
Plumbers :2 Painters :-
M/C :9 F/C :-

Work Done:

 Beam bottom and slab shuttering on third floor at B wing continued.


 Outer shuttering on third floor slab at A wing.
 Concreting of column C76 on second floor at B wing.
 Concreting of lift starter on second floor at C wing.
 Reinforcement work of slab on third floor at A wing continued.
 Electrical piping work through reinforcement on slab at third floor continued.
 Plumbing pipes provided on third floor slab at A wing.

Instruction:
 Columns verticality checked and instructed to mark casting and curing dates on
column again.

Remarks:(Describe significant events, work accomplishment, materials and


equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 RCC consultant Mr. Magdoom visited site for checking of reinforcement and

shuttering of third floor slab at A wing.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Friday Date: 21/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal, Amol Jr. Engineer : Suraj More


Masons :- Steel Fitters :-
Shuttering Carpenters : - Electricians :-
Plumbers :- Painters :-
M/C : 10 F/C :-

Work Done:

 Shuttering for brick wall for chapkam.


 Concreting in brick wall till chapkam.
 Hatching on columns Concreted walls.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Concreting of third floor slab at A wing cancelled due to heavy rains.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Sunday Date: 23/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal, Amol Jr. Engineer : Suraj More


Masons :2 Steel Fitters :-
Shuttering Carpenters : 12 Electricians :-
Plumbers :- Painters :-
M/C :8 F/C :-

Work Done:

 Concreting of lift starter on second floor at C wing is done.


 Brickwork of outer walls on first floor at A wing started.
 Shuttering work of slab on third floor at B wing & C wing continued.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Monday Date: 24/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal, Amol Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : 8 Electricians :1
Plumbers :- Painters :-
M/C : 19 F/C :-

Work Done:

 Shuttering work of slab on third floor at B wing continued.


 Concreting of third floor slab at A wing is done.
 Cutting and bending work of steel bars.

Instruction:
 Final checking of third floor slab at A wing before concreting is done.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Casting of third floor slab at A wing is completed. ( Cu.m )

 Mr. Prasad Patil and Mr. Durgesh Gadgil visited site for concreting.

Project Leader/ Senior Engineer Comments:

 Brick work has stopped as window sizes are not given, architect will visit site

tomorrow and will update it, Sarvesh vagal informed.


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Tuesday Date: 25/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal, Amol Jr. Engineer : Suraj More


Masons :2 Steel Fitters :5
Shuttering Carpenters : 8 Electricians :-
Plumbers :- Painters :-
M/C :9 F/C :-

Work Done:

 Brickwork of walls on first floor at A wing continued.


 Repairing of construction lift is done.
 Reinforcement work of lift pardi on second floor at C wing.
 Hatching on beams and columns.
 Curing of third floor slab at A wing is done.
 Shifting and removal of shuttering equipments on site.

Instruction:
 Checking of room sizes as per architecture plans done on third floor at B wing.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Architect Mr. Milind Joshi visited site for giving updates in window sizes and

other checkings.

 Mr. Prasad Patil and Mr. Durgesh Gadgil also visited site with architect.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Wednesday Date: 26/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal, Amol Jr. Engineer : Suraj More


Masons :2 Steel Fitters :6
Shuttering Carpenters : 12 Electricians :-
Plumbers :- Painters :-
M/C :6 F/C :-

Work Done:

 Brickwork of walls on first floor at A wing continued.


 Fixing column starters on third floor at A wing.
 Reinforcement work of columns on third floor at A wing started.
 Repairing of construction lift continued.
 Shifting of sand and aggregates on site.

Instruction:
 Checking of lift pardi with orientation, alignment and sizes is done.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Mr. Prasad Patil visited site.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Thursday Date: 27/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal, Amol Jr. Engineer : Suraj More


Masons :2 Steel Fitters :6
Shuttering Carpenters : 15 Electricians :-
Plumbers :- Painters :-
M/C :9 F/C :-

Work Done:

 Brickwork of walls on first floor at A wing continued.


 Reinforcement work of columns on third floor at A wing continued.
 Shuttering of lift pardi on second floor at C wing is done.
 Shuttering of lift starter at A wing on third floor.
 Concreting of remaining portion of slab on third floor at C wing is done.
 Oiling on beam and slab shuttering on third floor at B wing.
 Fixing and casting of column starters on third floor at A wing.

Instruction:
 Checking of column starters according to plans and gave necessary changes
wherever errors found.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Mr. Prasad Patil visited site.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Friday Date: 28/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal, Amol Jr. Engineer : Suraj More


Masons :2 Steel Fitters :-
Shuttering Carpenters : - Electricians :-
Plumbers :- Painters :-
M/C :4 F/C :-

Work Done:

 Brickwork of walls on first floor at A wing continued.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 No major work is done today due to heavy rains.

 Metal 1 aggregates of quantity 4.08 brass delivered on site.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Sunday Date: 30/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal, Amol Jr. Engineer : Suraj More


Masons :- Steel Fitters :6
Shuttering Carpenters : - Electricians :-
Plumbers :- Painters :-
M/C :7 F/C :-

Work Done:

 Concreting of remaining column starters on third floor slab at A wing.


 Reinforcement work of columns on third floor slab at A wing is done.
 Reinforcement work of beams on third floor slab at B wing started.

Instruction:

Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Site was shut yesterday ( 29/08/2020 ) due to heavy rains.

Project Leader/ Senior Engineer Comments:


Site Name : Deepanjali CHS Ltd.,
C.T.S. Number : 252/6 K East Ward
Site Address : Deepanjali CHS Ltd., Shahaji Raje Marg, Vile Parle (E)
Architect : Arch Dimensions, Architects & Project Consultants
Consulting Engineer : R.D.Magdum – RCC Consultants
Developers : Nivara Infra Developers LLP, Mr. Prasad Patil B.E. (Civil)
Contractors : Durgesh V. Gadgil – Construction Consultants, TAneesh
Infra
M.E.P. :
Day : Monday Date: 31/08/2020
Climate :
Cloudy Windy Heavy Rains Sunny Humid / Dry

Site Engineers : Sarvesh Vagal, Amol Jr. Engineer : Suraj More


Masons :- Steel Fitters :7
Shuttering Carpenters : 12 Electricians :-
Plumbers :- Painters :-
M/C :9 F/C :-

Work Done:

 Shuttering of columns C21,22,25 on third floor at A wing.


 Concreting of lift pardi on second floor at C wing is done.
 Reinforcement work of beams on third floor slab at B wing started.
 Shifting of materials on site.
 Hatching on beams below third floor slab at A wing.

Instruction:
 Lift shuttering is checked for alignment, size before casting.
Remarks:(Describe significant events, work accomplishment, materials and
equipments on site, special instructions to contractor’s site supervisor, safety
measures)

 Mr. Prasad Patil visited site.

 Metal 2 aggregates of quantity 4.08 brass delivered on site.

Project Leader/ Senior Engineer Comments: