Pictures of Activities June-August 2020

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 121

JUNE 2020

05/06/2020

1
Beam bottom shuttering at C Reinforcement work of lift A1 on first floor at A wing

Cast columns on first floor at A wing

2
Beam bottom shuttering on first floor at C wing Shuttering of lift A2 on first floor at A wing

Concreting of staircase at C wing from GL


to FL

3
Concreting of staircase at C wing from GL to FL
Beam reinforcement on first floor at C wing (VIDEO)

06/06/2020

4
Staircase at C wing (concreted yesterday)

Reinforcement work of slab at C wing done yesterday;


checked by Mr Magdoom (RCC Consultant) today
morning

5
B wing shuttering of first floor slab Reinforcement of slab on first floor at C wing

B wing shuttering and centering of first floor Shuttering of lift pardi on first floor at A wing

6
Staging work on first floor for further shuttering on second floor slab Shuttering of columns on first floor at A wing
at A wing is in progress

08/06/2020

7
C wing slab reinforcement on first floor C wing slab shuttering

B wing slab shuttering on first floor Shuttering of lift A1 on first floor at A wing

8
09/06/2020

Concreting of lift A1 at A wing on first floor

9
Reinforcement work of water tank at C wing at north
face end

Beam bottom shuttering on second floor at A wing Shuttering of beam and slab of remaining portion at C wing

10
Shuttering of staircase above first floor at A wing

Outside shuttering on second floor at A wing

11
Electrical piping work through slab reinforcement on first
floor at C wing

Concreting of underground water tank at C wing


(VIDEO)

12
10/06/2020

Pump setting up

13
C wing slab ready to concrete tomorrow

Shuttering of staircase at C wing

Girder beam on first floor at B wing

14
Curing of underground water tank at C wing

Beam bottom shuttering on second floor at A wing De shuttering of lift A1 at A wing on first floor

15
Staircase shuttering from first floor to second floor Beam bottom shuttering for second floor at A wing
at A wing is in progress continued

11/06/2020

16
Beam bottom work on second floor at A wing continued Reinforcement work of girder beam at B wing on first floor
continued

Making rough surface by vibrator at the Curing work on first floor at A wing
joint of A wing and C wing slab

17
Concreting of first floor slab at C wing
(VIDEO)

Concreting of first floor slab at C wing completed

18
12/06/2020

Beam reinforcement work at B wing on first floor

19
Beam bottom shuttering on second floor at A wing

Scaffolding material arrived on site

Column starters on first floor at C wing

20
13/06/2020

Outside shuttering on first floor at B wing

Reinforcement work of column on first floor at C wing

21
Shuttering of beams on second floor at A
wing

De shuttering of first floor slab bottom at A wing

22
14/06/2020

Shuttering of beam bottom work on second floor at A wing

23
Slab reinforcement work on first floor at B wing Shuttering of columns on first floor at B wing

Shuttering of columns on first floor at B wing Shuttering of beam on second floor at A wing

24
15/06/2020

Concreting of lift pardi on GL at C wing Beam bottom shuttering of second floor at A wing

25
Concreting of lift pardi on GL at C wing

16/06/2020

26
Beam shuttering for second floor slab at A wing

Column starters on first floor at C wing

Shuttering work of second floor slab at A wing

Shuttering of staircase from first floor to


second floor at A wing

27
Beam reinforcement work on first floor at B wing

Column reinforcement work on first floor at C wing Curing of slab and beams at C wing

28
18/06/2020

Reinforcement work of lift pardi on first floor at C wing Columns on first floor at C wing scheduled to cast today

29
Materials shifting Shuttering of columns on first floor at C wing

Concreting of staircase and


remaining slab portion on first floor
at C wing

30
Beam bottom shuttering on second floor at A wing Beam reinforcement work on first floor slab at B wing

20/06/2020

31
Slab reinforcement work on first floor at B wing

De shuttering of cast columns on first floor at


C wing

Shuttering of lift pardi on first floor at C wing

Outside shuttering support on first floor at C wing

32
22/06/2020

Shuttering of beam on second floor at A wing

Provision of pipes pieces from toilet from toilet to


duct before casting of slab on first floor at B wing

33
Electrical piping work through slab reinforcement on first
floor at B wing
Slab shuttering on second floor at A wing started

Concreting of lift pardi on first floor at C wing


(Video)

34
30/06/2020

Outside shuttering support on first floor at C wing Oiling of slab and beam shuttering on second floor at A wing

35
De shuttering of cast columns on first floor at C wing

Beam bottom shuttering on


second floor at C wing

VIDEO

Concreting of columns on first


floor at B wing

36
JULY 2020

01/07/2020

37
Second floor slab view of A and C wing
Beam and slab shuttering on
second floor at B wing

Column reinforcement work on second floor slab at A wing Beam bottom shuttering on second floor at B wing

38
Shuttering of Lift pardi on first floor at B wing

Outside chajja shuttering on second floor at B and C wing

Concreting of Column on first floor


(Total 9 columns are scheduled to be concreted)

39
Beam and Slab shuttering on second floor at B wing

02/07/2020

40
Beam reinforcement work on second floor started Beam reinforcement work on second floor at A wing

Concreting of beams on first floor at C wing (north face) Shuttering work on second floor at B wing

41
Needle vibrating while concreting

06/07/2020

42
Beam reinforcement work on second floor slab at A wing

B and C wing second floor slab

43
Concreting of beams at C wing first floor at north face end

Beam bottom shuttering work on second floor at B wing

44
07/07/2020

De shuttering of column on first floor (C80) De shuttering of column on first floor which were cast
yesterday (C106)

45
Reinforcement work of beams on second floor at A wing continued. B and C wing slab on second floor. (Beam bottom shuttering work at B
(work stopped after lunch break due to heavy rain) wing continued till lunch break)

Concreting of lift pardi on first floor at B wing

46
08/07/2020

Column starter setting on first floor at C wing north face end Concreting of staircase from first floor to second floor at A wing

47
Beam and Slab shuttering on second floor at B wing continued Reinforcement work of slab on second floor at A wing continued

09/07/2020

48
Reinforcement work of slab on second floor at A wing started

Shuttering of slab on second floor at B wing continued

Site cleaning work ongoing

49
Outside shuttering work on second floor at A wing Outside shuttering work on second floor
slab at A wing continued

10/07/2020

50
Water tank with pump arrived on site

Steel cutting bending work ongoing

Outer Shuttering support work on second floor at A wing Shuttering of staircase from first floor to second floor at B wing

51
Centering and Shuttering of Second floor slab at C wing

11/07/2020

52
Shuttering work of slab on second floor at B wing continued

Concreting done of column starter on first


floor at C wing north face end

Concreting done of column starter on first floor at C wing north face end Reinforcement work of column on first floor at C wing started

53
Slab shuttering on second floor at A wing started
Shuttering of reinforced column on first
floor at C wing started

13/07/2020

54
Reinforcement work of slab on second floor at A wing

Shuttering of columns on first floor at C wing

Electrical piping work on second floor slab at A wing started

55
Concreting of columns on first floor at C wing

14/07/2020

56
Outside shuttering on second floor slab at A wing

Beam bottom work started on first floor at C WING

Shifting of materials

57
Plumbing pipe work on second floor slab at A wing Staircase shuttering on second floor at A wing

Column reinforcement work on second Chajja shuttering on second floor at A wing


floor at A wing

58
17/07/2020

First TM arrived on site Slab concreting on second


floor at A wing started

59
Beam bottom work started on second floor at C wing north face end

Providing cover blocks wherever left

Slab concreting completed

60
18/07/2020

Concreted slab view on second floor at A wing

61
Column reinforcement work on second floor at A wing started

Shuttering of second floor slab at C wing north face end

Reinforcement work of lift on second floor


at A wing started

62
20/07/2020

Reinforcement work of columns on second floor at A wing

Shuttering of lift pardi on second floor at A wing

63
Shuttering of slab on second floor at C wing north face end Column and beam reinforcement work started on second
floor slab at B WING

Shuttering of columns on second floor at A wing

64
21/07/2020

Curing of second floor slab at A Wing

65
Concreting of columns on second floor at A wing

Reinforcement of beam on second floor at B wing

Concreting of columns starters on second


floor at A wing

66
22/07/2020

Shuttering of columns on second floor at A wing

67
Beam reinforcement work on second floor slab at B wing is done Curing of slab on second floor at A wing

Concreting of column on second floor at A wing

68
Concreting of beam on first floor at C wing north face end

23/07/2020

69
Shuttering of beam on first floor at C wing north face end

Chajja reinforcement on second floor at B wing

Shuttering of stairacase from second floor at A wing

70
Shuttering ply arrived at site Beam bottom shuttering started on third floor at A wing

Concreting of staircase from first floor to second floor at B wing

71
24/07/2020

Concreting of columns on second floor at A wing

72
Outside shuttering on second floor at B wing Reinforcement work of beam on second floor at C wing

25/07/2020

73
Concreting of lift pardi on second floor at A wing

Outside shuttering on second floor slab at B wing continued

Binding wires to reinforced steel

74
27/07/2020

Slab reinforcement work on second floor at B wing

75
28/07/2020

Outside shuttering of second floor slab at B wing Electrical piping work started on second floor slab at B wing

76
Cube casting from concreting of columns on second floor at A wing Reinforcement work of slab on second floor at B wing is done

Hatching on lift pardi

77
29/07/2020

Outer shuttering work on second floor slab at B wing continued Shuttering of lift pardi on second floor at A wing

78
Electrical piping work on second floor slab at B wing continued B wing second floor slab view

30/07/2020

79
Concreting of staircase from first floor to second floor at C wing

Beam bottom shuttering work on third floor at A wing Columns starters fixed on first floor at C wing north face end

80
Cutting and bending of steel bars Electrical piping work on second floor slab at
B wing continued

Concreting of lift pardi on second floor at A wing is done

De shuttering of second floor slab at A wing started

81
AUGUST 2020

01/08/2020

82
Curing of second floor slab at B wing Shuttering of beams on third floor at A wing

Slab shuttering on third floor at A wing started

83
03/08/2020

Curing of second floor slab at B wing continued

De-shuttering of beam and slab


bottom on second floor at A wing

84
Shuttering work of slab on third floor at A wing Fixing and casting of column starters on first floor at C wing

04/08/2020

85
Second floor slab view of B & C wing Reinforcement of columns on second floor at B wing

Reinforcement of column on first floor at C wing

86
06/08/2020

Electrical wiring and switch board fixing at stilt level

87
Fixing and casting of column starters on second
floor slab at B wing

Cutting and bending work of reinforcement

88
Hatching on beams and columns 200 nos cement bags delivered on site

07/08/2020

89
Reinforcement of columns on second Reinforcement of lift on second floor at B wing
floor at B wing

Shuttering of columns on second floor at B wing

90
Concreting of 7 columns on second floor at B wing
(VIDEO)

08/08/2020

91
Shuttering of lift pardi B2 on second floor at B wing

Fixing and casting of lift B1 on second


floor at B wing

Fixing column starters on second floor at B wing De-shuttering of cast columns on second floor at B wing

92
(VIDEO)

Concreting of 5 columns on second floor at B wing

10/08/2020

93
Shuttering of columns on second floor at C wing Concreting of column and lift starters on second floor at B wing

Concreting of lift B1 on second floor at B wing

(VIDEO)

94
Beam reinforcement work started on third floor at A wing

12/08/2020

95
Outer shuttering work on third floor at A wing Shuttering of 5 column on second floor at B wing

Beam reinforcement done on third floor at A wing

96
Hatching on cast columns on second floor at B wing

13/08/2020

97
Shifting of steel on third floor for slab reinforcement Outer shuttering on third floor at A wing

Beam bottom shuttering on third floor at C wing 6” bricks delivered on site

98
Concreting of lift B1 on second floor at B wing

(VIDEO)

Concreting of 5 columns on second floor at B wing

99
14/08/2020

Reinforcement of staircase from second to third floor at A


wing

100
Beam bottom shuttering on third floor at B wing

Hatching on cast columns

Reinforcement of top slab of UG water tank at B wing

Shifting of bricks on first floor for


brickwork at A wing

101
17/08/2020

Concreting of slab porton and chajja on second floor at C wing done yesterday

102
Beam shuttering work continued on third floor at B wing

Reinforcement work of slab on third floor at A wing started


Shuttering of steps and sides of
staircase from second to third floor at A
wing

103
(VIDEO)

Concreting of top slab of UG water tank at B wing

18/08/2020

104
Beam and slab shuttering on third floor at B wing

Electrical piping work through reinforcement on third floor at A wing started

105
Layout of bricks (chapkam) for walls on first floor at A wing

Shuttering of lift starter on second floor at C wing

106
19/08/2020

Beam bottom shuttering on third floor at C wing

107
Concreting of staircase from second to third floor at A wing

Electrical piping work through reinforcement on third floor at A wing

108
20/08/2020

Electrical piping work is done on third floor at A wing

109
Provision of plumbing pipes in kitchen and toilets on third Casting of column C76 on
floor at A wing second floor at B wing

(VIDEO)

Concreting of lift starter on second floor at C wing

110
21/08/2020

Casting of tie beam in brickwall

111
Slab shuttering on third floor at B wing

24/08/2020

112
First TM arrived on site Concreting of third floor slab at A wing started

Concreting of third floor slab at A wing


(VIDEO)

113
Concreting of third floor slab at A wing

25/08/2020

114
Brickwork of walls on first floor at A
wing

Hatching on beams and columns on second floor

115
Reinforcement of lift on second floor at C wing

Curing of third floor slab at A wing Shuttering of third floor slab at B wing

116
26/08/2020

Brickwork of walls on first floor at A wing

117
Fixing of column starter on third floor at A wing

Reinforcement work of columns on third floor at A wing

118
Checking of lift starter with orientation, sizes
according center line plan

27/08/2020

119
Reinforcement of columns continued on third floor at A wing

Shuttering of lift pardi on second floor at C wing

120
Checking and fixing of lift and column starters on third floor at A wing

Concreting of remaining portion of slab on third


floor at C wing (VIDEO)

121

You might also like