05/06/2020
1
Beam bottom shuttering at C Reinforcement work of lift A1 on first floor at A wing
2
Beam bottom shuttering on first floor at C wing Shuttering of lift A2 on first floor at A wing
3
Concreting of staircase at C wing from GL to FL
Beam reinforcement on first floor at C wing (VIDEO)
06/06/2020
4
Staircase at C wing (concreted yesterday)
5
B wing shuttering of first floor slab Reinforcement of slab on first floor at C wing
B wing shuttering and centering of first floor Shuttering of lift pardi on first floor at A wing
6
Staging work on first floor for further shuttering on second floor slab Shuttering of columns on first floor at A wing
at A wing is in progress
08/06/2020
7
C wing slab reinforcement on first floor C wing slab shuttering
B wing slab shuttering on first floor Shuttering of lift A1 on first floor at A wing
8
09/06/2020
9
Reinforcement work of water tank at C wing at north
face end
Beam bottom shuttering on second floor at A wing Shuttering of beam and slab of remaining portion at C wing
10
Shuttering of staircase above first floor at A wing
11
Electrical piping work through slab reinforcement on first
floor at C wing
12
10/06/2020
Pump setting up
13
C wing slab ready to concrete tomorrow
14
Curing of underground water tank at C wing
Beam bottom shuttering on second floor at A wing De shuttering of lift A1 at A wing on first floor
15
Staircase shuttering from first floor to second floor Beam bottom shuttering for second floor at A wing
at A wing is in progress continued
11/06/2020
16
Beam bottom work on second floor at A wing continued Reinforcement work of girder beam at B wing on first floor
continued
Making rough surface by vibrator at the Curing work on first floor at A wing
joint of A wing and C wing slab
17
Concreting of first floor slab at C wing
(VIDEO)
18
12/06/2020
19
Beam bottom shuttering on second floor at A wing
20
13/06/2020
21
Shuttering of beams on second floor at A
wing
22
14/06/2020
23
Slab reinforcement work on first floor at B wing Shuttering of columns on first floor at B wing
Shuttering of columns on first floor at B wing Shuttering of beam on second floor at A wing
24
15/06/2020
Concreting of lift pardi on GL at C wing Beam bottom shuttering of second floor at A wing
25
Concreting of lift pardi on GL at C wing
16/06/2020
26
Beam shuttering for second floor slab at A wing
27
Beam reinforcement work on first floor at B wing
Column reinforcement work on first floor at C wing Curing of slab and beams at C wing
28
18/06/2020
Reinforcement work of lift pardi on first floor at C wing Columns on first floor at C wing scheduled to cast today
29
Materials shifting Shuttering of columns on first floor at C wing
30
Beam bottom shuttering on second floor at A wing Beam reinforcement work on first floor slab at B wing
20/06/2020
31
Slab reinforcement work on first floor at B wing
32
22/06/2020
33
Electrical piping work through slab reinforcement on first
floor at B wing
Slab shuttering on second floor at A wing started
34
30/06/2020
Outside shuttering support on first floor at C wing Oiling of slab and beam shuttering on second floor at A wing
35
De shuttering of cast columns on first floor at C wing
VIDEO
36
JULY 2020
01/07/2020
37
Second floor slab view of A and C wing
Beam and slab shuttering on
second floor at B wing
Column reinforcement work on second floor slab at A wing Beam bottom shuttering on second floor at B wing
38
Shuttering of Lift pardi on first floor at B wing
39
Beam and Slab shuttering on second floor at B wing
02/07/2020
40
Beam reinforcement work on second floor started Beam reinforcement work on second floor at A wing
Concreting of beams on first floor at C wing (north face) Shuttering work on second floor at B wing
41
Needle vibrating while concreting
06/07/2020
42
Beam reinforcement work on second floor slab at A wing
43
Concreting of beams at C wing first floor at north face end
44
07/07/2020
De shuttering of column on first floor (C80) De shuttering of column on first floor which were cast
yesterday (C106)
45
Reinforcement work of beams on second floor at A wing continued. B and C wing slab on second floor. (Beam bottom shuttering work at B
(work stopped after lunch break due to heavy rain) wing continued till lunch break)
46
08/07/2020
Column starter setting on first floor at C wing north face end Concreting of staircase from first floor to second floor at A wing
47
Beam and Slab shuttering on second floor at B wing continued Reinforcement work of slab on second floor at A wing continued
09/07/2020
48
Reinforcement work of slab on second floor at A wing started
49
Outside shuttering work on second floor at A wing Outside shuttering work on second floor
slab at A wing continued
10/07/2020
50
Water tank with pump arrived on site
Outer Shuttering support work on second floor at A wing Shuttering of staircase from first floor to second floor at B wing
51
Centering and Shuttering of Second floor slab at C wing
11/07/2020
52
Shuttering work of slab on second floor at B wing continued
Concreting done of column starter on first floor at C wing north face end Reinforcement work of column on first floor at C wing started
53
Slab shuttering on second floor at A wing started
Shuttering of reinforced column on first
floor at C wing started
13/07/2020
54
Reinforcement work of slab on second floor at A wing
55
Concreting of columns on first floor at C wing
14/07/2020
56
Outside shuttering on second floor slab at A wing
Shifting of materials
57
Plumbing pipe work on second floor slab at A wing Staircase shuttering on second floor at A wing
58
17/07/2020
59
Beam bottom work started on second floor at C wing north face end
60
18/07/2020
61
Column reinforcement work on second floor at A wing started
62
20/07/2020
63
Shuttering of slab on second floor at C wing north face end Column and beam reinforcement work started on second
floor slab at B WING
64
21/07/2020
65
Concreting of columns on second floor at A wing
66
22/07/2020
67
Beam reinforcement work on second floor slab at B wing is done Curing of slab on second floor at A wing
68
Concreting of beam on first floor at C wing north face end
23/07/2020
69
Shuttering of beam on first floor at C wing north face end
70
Shuttering ply arrived at site Beam bottom shuttering started on third floor at A wing
71
24/07/2020
72
Outside shuttering on second floor at B wing Reinforcement work of beam on second floor at C wing
25/07/2020
73
Concreting of lift pardi on second floor at A wing
74
27/07/2020
75
28/07/2020
Outside shuttering of second floor slab at B wing Electrical piping work started on second floor slab at B wing
76
Cube casting from concreting of columns on second floor at A wing Reinforcement work of slab on second floor at B wing is done
77
29/07/2020
Outer shuttering work on second floor slab at B wing continued Shuttering of lift pardi on second floor at A wing
78
Electrical piping work on second floor slab at B wing continued B wing second floor slab view
30/07/2020
79
Concreting of staircase from first floor to second floor at C wing
Beam bottom shuttering work on third floor at A wing Columns starters fixed on first floor at C wing north face end
80
Cutting and bending of steel bars Electrical piping work on second floor slab at
B wing continued
81
AUGUST 2020
01/08/2020
82
Curing of second floor slab at B wing Shuttering of beams on third floor at A wing
83
03/08/2020
84
Shuttering work of slab on third floor at A wing Fixing and casting of column starters on first floor at C wing
04/08/2020
85
Second floor slab view of B & C wing Reinforcement of columns on second floor at B wing
86
06/08/2020
87
Fixing and casting of column starters on second
floor slab at B wing
88
Hatching on beams and columns 200 nos cement bags delivered on site
07/08/2020
89
Reinforcement of columns on second Reinforcement of lift on second floor at B wing
floor at B wing
90
Concreting of 7 columns on second floor at B wing
(VIDEO)
08/08/2020
91
Shuttering of lift pardi B2 on second floor at B wing
Fixing column starters on second floor at B wing De-shuttering of cast columns on second floor at B wing
92
(VIDEO)
10/08/2020
93
Shuttering of columns on second floor at C wing Concreting of column and lift starters on second floor at B wing
(VIDEO)
94
Beam reinforcement work started on third floor at A wing
12/08/2020
95
Outer shuttering work on third floor at A wing Shuttering of 5 column on second floor at B wing
96
Hatching on cast columns on second floor at B wing
13/08/2020
97
Shifting of steel on third floor for slab reinforcement Outer shuttering on third floor at A wing
98
Concreting of lift B1 on second floor at B wing
(VIDEO)
99
14/08/2020
100
Beam bottom shuttering on third floor at B wing
101
17/08/2020
Concreting of slab porton and chajja on second floor at C wing done yesterday
102
Beam shuttering work continued on third floor at B wing
103
(VIDEO)
18/08/2020
104
Beam and slab shuttering on third floor at B wing
105
Layout of bricks (chapkam) for walls on first floor at A wing
106
19/08/2020
107
Concreting of staircase from second to third floor at A wing
108
20/08/2020
109
Provision of plumbing pipes in kitchen and toilets on third Casting of column C76 on
floor at A wing second floor at B wing
(VIDEO)
110
21/08/2020
111
Slab shuttering on third floor at B wing
24/08/2020
112
First TM arrived on site Concreting of third floor slab at A wing started
113
Concreting of third floor slab at A wing
25/08/2020
114
Brickwork of walls on first floor at A
wing
115
Reinforcement of lift on second floor at C wing
Curing of third floor slab at A wing Shuttering of third floor slab at B wing
116
26/08/2020
117
Fixing of column starter on third floor at A wing
118
Checking of lift starter with orientation, sizes
according center line plan
27/08/2020
119
Reinforcement of columns continued on third floor at A wing
120
Checking and fixing of lift and column starters on third floor at A wing
121