Professional Documents
Culture Documents
Internship 1
Internship 1
After the completion of documentation work, the actual construction on plot begins. Following are the steps:
All civil engineering structures whether they are buildings, dams, bridges etc. are built on soils. A
foundation is required to transmit the load of the structure on a large area of soil. The foundation of
the structure should be so designed that the soil below does not fail in shear nor there is the
excessive settlement of the structure. The conventional method of foundation design is based on the
concept of bearing capacity.
Soil when stressed due to loading, tend to deform. The resistance to deformation of the soil depends
upon factors like water content, bulk density, angle of internal friction and the manner in which load is
applied on the soil. The maximum load per unit area which the soil or rock can carry without yielding
or displacement is termed as the bearing capacity of soils.
Soil properties like shear strength, density, permeability etc., affect the bearing capacity of soil. Dense
sand will have more bearing capacity than loose sand as unit weight of dense sand is more than loose
sand.
If the bearing capacity of soil at shallow depth is sufficient to safely take the load of the structure, a
shallow foundation is provided. Isolated footing, combined footing or strip footing are the option for
the shallow foundation. Deep foundations are provided when soil immediately below the structure
does not have the adequate bearing capacity. Pile, piers or well are the options for deep foundations.
Mat or raft foundations are useful for soil which is subjected to differential settlement or where there
is a wide variation in loading between adjacent columns.
Methods of determining bearing capacity
Presumptive Analysis
Analytical Methods
Plate Bearing Test
Penetration Test
A building is set out in order to clearly define the outline of the excavation and the center line of the walls, so
that construction can be carried out exactly according to the centre line method of setting out is generally
preferred and adopted. From the plan (fig 1), the centre line of the walls are calculated. Then the centre lines of
the room are set out by setting perpendiculars in the ratio 3:4:5. Suppose the corner points are a , b, c, d, e, f
and g which are market by pegs with nails on top.
1. The setting of the corner point is checked according to diagonals ac, bd, cf, and eg.
2. During excavation, the centre points a, b, c, d, e, f, g may be removed. Therefore the centre lines are
extended and the centre points are marketd about 2m away from the outer edge of excavation. Thus the
points A1,A2,B1,B2 and likewise, are marked outside the trench. Centerline is shown clearly by
stretching thread or rope. The centre point fixed 2m away from the excavation are marked with sit out
pegs.
3. From the plan details, the width of excavation to be done is also marked by thread with pegs at
appropriate position.
4. The excavation width is then marked by lime or by with furrow with spade.
5. If the plan is much to complicate and follows a zigzag pattern, then centre pegs are kept at suitable
positions according to site conditions.
Depth of foundation varies from 9’’ to 18’’ and normally for most of the cases it is considered as 12’’
depth .keep foundation width equals to its depth.
Column reinforcement
The column reinforcement bars should be stared form the footing. The upper column reinforcement bars are
cranked at the laps and connected. Special care should be taken in this to ensure the lap lengths. After erection
of main reinforcements, cover blocks were attached to column reinforcements to maintain the required cover for
column reinforcement. Most of column centers were located at intersections of grid lines.
Stirrup spacing
According to the column reinforcement details drawing the reinforcement details for a typical internal columns,
form to basement to ground floor is as follows.
Column stirrups were tightened up beam bottom level and rest is tightened once beam reinforcement is
fabricated. So bar benders was instructed how to provide the stirrups. Mark the stirrup spacing from the
basement floor level in the column main bars with a chalk as follow the detail drawing.
Brickwork specifications
Quality Assurance cheks and also care to be taken during & after construction Checks prior to start work
Use silt free (less than 6%) medium gritty clean sand for mortar. In silt content test we have discussed
how silt content effects the strength.
The approved grade of cement, less than 1-month- old should be used. We’ve also discussed why we
should avoid old stack cement?
Ensure that all required construction tools, accessories, and materials are available at the work place .
Thereafter each brick shall be removed and re-laid over the bed of mortar. After every three or four
blocks have been laid, their correct alignment, level, and verticality shall be carefully checked.
As each course is laid at the end/corner, it shall be checked alignment and level or straight – edge to
make certain that the faces of the bricks are all in the same plane. This precaution is necessary to ensure
truly straight and vertical walls.
Check up if the corners are at right angle using the framing square.
After 7 days of curing of mortar joints drive a nail into the joint to test the strength of joints at random.
Also, look for colour variation in the mortar joints to identify problem areas.
Waterproofing plaster in the case of retaining walls should be done for all external surfaces. Bitumen
touch-on and Thermopolis protection are done before backfilling in layers and compacting
STEP 6 LINTEL
Masonry work of buildings is carried out in one go till roof .openings for windows and doors are left during
masonry works .reinforced cement concret beams are laid down on the top of openings . so ,those loads of
structure above openings not directly come on the door frames .
STEP 7 ROOFING
Roof slab of building is poured after completion of masonry works. Now days ,roofing reinforced cement
concrete slab. Slab thickness and reinforcement details should be according to approved drawing.
The typical concrete mixing ratio for slabs is 1:2:4. This means:
One part cement
Two parts sand
Four parts coarse aggregate
This ratio provides an excellent balance between strength and workability, making it ideal for
supporting the weight of a structure.
However, it’s essential to consider factors such as the type of load the slab will bear, the required
compressive strength, and the environmental conditions before settling on a concrete mixing ratio for
your slab.
For example, if your slab will be exposed to harsh weather conditions or heavy loads, you may need
to adjust the ratio accordingly.
49.80m
100.08m
7Beams =49.80X7=348.60m
48.30X7= 338.10m
Form work is removed after 14 days of slab pouring. Now plaster work begins. Mortar for plaster work is
generally of 1:3 or 1:4 is used. Thickness of plaster layer should not be more than 0.75 inch. Cure the surface
about 7 days .so that, plaster gain proper strength.
Generally, internal walls of buildings are covered with plastered layer and external walls with pointing. It is
better plaster the external walls rather than pointing.
STEP 10 FLOORING
Flooring is the general term for a permanent covering of a floor, or for the work of installing such a floor
covering. Floor covering is a term to generically describe any finish material applied over a floor structure to
provide a walking surface. Both terms are used interchangeably but floor covering refers more to loose-laid
materials.
STEP 11PAINTING
Painting is the practice of applying paint, pigment, color or other medium to a solid surface (called the
"matrix or "support").The medium is commonly applied to the base with a brush, but other implements, such as
knives, sponges, and airbrushes, can be used.
In art, the term "painting" describes both the act and the result of the action (the final work is called "a
painting"). The support for paintings includes such surfaces as walls, paper, canvas, wood, glass, lacquer,
pottery, leaf, copper and concrete, and the painting may incorporate multiple other materials, including
sand, clay, paper, plaster, gold leaf, and even whole objects.
Painting is an important form of visual art, bringing in elements such
as drawing, composition, gesture, narration, and abstraction.
CONCLUSION
The main aim of studies within this project was to investigate how a structure is constructed with in its desired
properties. We have to get knowledge about the basic and advanced techniques of building construction as well
as saw the challenges which a civil engineer to face during construction i.e. labour problems, past management,
environmental challenges, etc. we cleared our many doubts regarding building construction. We had seen
dewatering system at project site for construction which is not used at our state any more, so it was a new thing
four. Although are subjects more important technicians, in the project we have been project studied some
mechanic or electro-mechanic machinery such as the ready mix plant because basic knowledge about their
working is important for an engineer but also because was the opportunity to see and understand them. Overall
it must be said that the construction methods and quality control on a construction project needs a very good
coordination and large quantities of man power, equipment and funds. During the period of half month all the
company staff helped us a lot to provide all the information about anyrequery. So we are gratefull to all the
staff of ANGLE COMPANY as well as we are so thankful to our Civil Engineering for their kind support.