Heat Trace Circuit

Tag Description: Tag No.:

P. O. No.: Inspection Classification Area/Unit:

Subcontractor: Subcontractor Owner Turnover System:

Work Package: Company Other Sub – System:


Item Description of Check Subcontractor Client
01 Confirm cladding installation complete.
02 Confirm entry kits and warning labels fitted.
03 Post cladding IR test. (Min value = 10M @ 500V)
04 Verify circuit description / identification is correct.
05 Verify that an RCCD is fitted in the circuit. (Certification
Requirement)
06 Verify circuit connections and MCB ratings against latest distribution
board schedule.
07 Confirm total installed tape length does not exceed manufacturer’s
instruction.
08 Measure tape element resistance at distribution board.
09 Carry out point to point verification and earth loop resistance check
at last junction box.
10 Energize circuit and confirm initial inrush current is acceptable.
11 Measure earth loop impedance at circuit extremities. (Max value for
16A MCB Type C = 1.5)
12 Verify RCCD trip time at circuit extremities. (Trip within 200ms @
100% trip rating)
13 Verify correct setting and operation of thermostat controls.
14 Verify satisfactory heat output of tapes and confirm steady state
current after 1 hour is acceptable.
15 Check tape temperature is satisfactory at appropriate locations.
16 Compile red line drawing changes where applicable.
Note: Lower IR values may be acceptable with approval of
Commissioning Engineer.