Item Description of Check Subcontractor Client 01 Confirm cladding installation complete. 02 Confirm entry kits and warning labels fitted. 03 Post cladding IR test. (Min value = 10M @ 500V) 04 Verify circuit description / identification is correct. 05 Verify that an RCCD is fitted in the circuit. (Certification Requirement) 06 Verify circuit connections and MCB ratings against latest distribution board schedule. 07 Confirm total installed tape length does not exceed manufacturer’s instruction. 08 Measure tape element resistance at distribution board. 09 Carry out point to point verification and earth loop resistance check at last junction box. 10 Energize circuit and confirm initial inrush current is acceptable. 11 Measure earth loop impedance at circuit extremities. (Max value for 16A MCB Type C = 1.5) 12 Verify RCCD trip time at circuit extremities. (Trip within 200ms @ 100% trip rating) 13 Verify correct setting and operation of thermostat controls. 14 Verify satisfactory heat output of tapes and confirm steady state current after 1 hour is acceptable. 15 Check tape temperature is satisfactory at appropriate locations. 16 Compile red line drawing changes where applicable. Note: Lower IR values may be acceptable with approval of Commissioning Engineer.