SAFE WORK PROCEDURE

(Performance Criteria - Perfection in job with no injury to persons or damage to property) or damage to property REV -00

1. DEPARTMENT : RMP- DOC. NO: KIPL/SWP/GB/ 03 DATE: 01/03/2023

2. SECTION / LOCATION : RMP JODA MIING NAME OF WORKING AGENCY: M/S KADTECH INFRAPROJECTS PVT.LTD
3. JOB TITLE : QUIRE MAT / BIOMAC USE AT SLOPE PROTECTION WORK ORDER No: 3800019054 / 109

JOB DURATION : Start Date: 14.11.2013 End Date: 27.04.2024


Persons Responsible Condition of Tools / Reference to
Sl.
Activities (Sequence of Work) Hazard Safety Precautions Name & P. No. Tackles required OK/Not document/criteria and
No.
Ok remarks

1 Preparation for fall of materials , finger Follow general guidelines toolbox meeting at start of Avijit shaha , follow safety
job and press , slip/trip/ fall the job , work permit system , six directional hazards and RamBabu standards -
handling of precautions and housekeeping and other checklist needs. Sharma , SS/GEN-25
amit Work permit
materials Load the materials lots as per size of space of vehicle and
chakorborty system
( store to site do not take out materials outside of vehicle . because it Sujeet ,SS/ENGG-13
and site to store may hit to other. And unload the materials at proper place Sinha , Barricading ,SS
) and even place. Take the work permit system before start /GEN-54
the job.. Daily meeting should be done before starting the Contractor
job ( TBT ), Keep materials properly if need help more safety
person . Barricade the area wherever need. Take two management
for TBM
person at least for handling and place at decided area.
,SS/ENGG-07
And use hand gloves to prevent press of finger. Do not Personal
loose material during shifting . Barricade the area where protective
need . Maintain the housekeeping at site at regular interval equipment
for prevention of slip , trip –fall.. Use mandatory PPES (PPE),SS/ENG
( safety shoes , hand gloves, helmet , goggle , fluorescent G-11 Material
jacket ) at site with hand gloves. handling
2 Hook at rigid Fall of person , break of Hook at rigid structure which should be more reliable and
structure and rope , failure of ascender strength , check the physical condition of the equipment and

Safety Professional Safety Professional Project Manager


(KADTECH ) (TSL)
Note: 1. This Safe Work Procedure shall be prepared by owner department countersigned by contractor's representative and safety department.
2. Sequence of work shall invoice step-by-step jobs.
3. All possible hazard including proximity hazard shall be amended and persons shall be identified.
4. With the change of working conditions, the procedure shall be amended and persons shall be trained
5. Review on status of implementation shall be done though task observation
6. Before start of the job, induction shall be given to persons engaged at site by departmental representative and Contractor’s Representative.
SAFE WORK PROCEDURE
(Performance Criteria - Perfection in job with no injury to persons or damage to property) or damage to property REV -00

1. DEPARTMENT : RMP- DOC. NO: KIPL/SWP/GB/ 03 DATE: 01/03/2023

2. SECTION / LOCATION : RMP JODA MIING NAME OF WORKING AGENCY: M/S KADTECH INFRAPROJECTS PVT.LTD
3. JOB TITLE : QUIRE MAT / BIOMAC USE AT SLOPE PROTECTION WORK ORDER No: 3800019054 / 109

JOB DURATION : Start Date: 14.11.2013 End Date: 27.04.2024


Persons Responsible Condition of Tools / Reference to
Sl.
Activities (Sequence of Work) Hazard Safety Precautions Name & P. No. Tackles required OK/Not document/criteria and
No.
Ok remarks
hang down and descender devices , IRATA certified height pass person must hang down due to
more cable and high risk. They will adjust the materials by
spreading it at two places. And instruction will be followed as
per concerned authorized person.
3 Biomac / quire Finger press , fall of Open one end of the material of roll that’s is about 5o mtr in Avijit shaha , Personal
mat spread materials , fall of person length. Two person will open and pass from top area to RamBabu protective
slope area. Then two height pass person will pass and adjust Sharma , equipment
Amit (PPE),SS/ENG
mat to that place and ensure it by looking it. then clamp
chakorborty G-11 Material
between two matching areas will be fixed as per practical Sujeet Sinha handling
requirement . Cut the mat and change the position of roll .
do not keep material roll / other thing at the edge of slope.
Competent person will perform the job. And check the
condition of equipment hanging . No extra person go near
there.
4

Safety Professional Safety Professional Project Manager


(KADTECH ) (TSL)
Note: 1. This Safe Work Procedure shall be prepared by owner department countersigned by contractor's representative and safety department.
2. Sequence of work shall invoice step-by-step jobs.
3. All possible hazard including proximity hazard shall be amended and persons shall be identified.
4. With the change of working conditions, the procedure shall be amended and persons shall be trained
5. Review on status of implementation shall be done though task observation
6. Before start of the job, induction shall be given to persons engaged at site by departmental representative and Contractor’s Representative.

You might also like