Professional Documents
Culture Documents
Chapter 4 - Project-Management (Word 97 - 2003)
Chapter 4 - Project-Management (Word 97 - 2003)
The following questions have been taken from the Cambridge Checkpoints 2007
– VCE IT Applications – Potts. (Also check out the online quizzes at
www.cambridge.edu.au/checkpoints)
CHAPTER 4
Project Management
Question 1 [VCAA 2001] = 1 Mark
Explain the term Project Management.
Question 3
Once the project definition is completed, the project design takes place.
Two of the steps in the project design are establishing naming conventions
for files, tables, records and reports, and setting standards for testing.
Question 7
In what way would a project team use milestones?
Question 9
A group of students have decided to prepare a guidebook on nightclubs in
Melbourne. A number of tasks associated with the project have been
identified and are listed in the table below. The anticipated duration of
the task is also indicated.
Duration
Task Description
(days)
A Research topic 6
E Proofread 1
H Add graphics 2
J Print pages 2
K Bind pages 1
The tasks have been split between the students; however, a number of
the tasks have been determined to have dependencies.
1. Research must take place before the writing phase can begin.
2. A student can take the digital photos while colleagues carry out the
research.
3. Draft writing must take place before it can be entered into the word
processor.
6. Adding text to the pages occurs before the graphics are added.
7. A few students will work on the cover while the others are placing
the text and graphics into the desktop publishing package.
a. Draw the Gantt chart for the project outlined above on the grid
provided.
Task
A
B
C
D
E
F
G
H
I
J
K
0 2 4 6 8 10 12 14 16 18 20 22 24 26
Time in days
b. From your Gantt chart, determine the length of the critical path.
Question 13
A project consisting of eight tasks has a PERT diagram constructed as indicated
below. Duration is measured in days.
10 30
F,4 H,2
50 80
5 install benches 3 2
8 test computers 1 7
b. Identify one task that can be done at the same time as Task 3.
c. Using the information above, calculate the number of days in the critical
path.
Question 18
Complete these sentences.
The critical path is the particular sequence of events that represents the …………
…………………… time required to complete the project. If any task on the critical
path is ………………………………, then the project completion is also ………………
……………… .