Professional Documents
Culture Documents
ARE-Study-Sessions 4.0 CDS Vignette
ARE-Study-Sessions 4.0 CDS Vignette
2017 Schedule
Saturday mornings, 11:00am - 1:00pm
1218 Arch St., Philadelphia, PA 19107
BD
SPD CDS PPP BS* SS* CS* SD
2/11 3/11 4/8 5/6 6/3 7/8 8/5
2/25 3/25 4/22 5/20 6/17 7/22 8/19
AREWKSHP
BUILDING SECTION VIGNETTE
AREWKSHP
Construction
Documents &
Services
100 MC Questions
From NCARB
+
1 Vignette
Construction Documents & Services
Overview
BUILDING SECTION VIGNETTE - Sample Passing Solution
Knowledge/
Skills
This is what I
consider the most
important step.
Take your time
here.
AREWKSHP
Construction
Documents &
Services
100 MC Questions
+
1 Vignette
Construction Documents & Services
Make sure you ID
Overview
BUILDING SECTION VIGNETTE - Sample Passing Solution
them correctly. 2hr Very similar to the test
Knowledge/
walls are drawn
Skills to
Program
Draw stacked
the bottom of the
Sample Multiple-
Choice Questions The structural system consists of top chord bearing steel joists 7. The space between each ceiling and floor or roof slab sketches or do the
deck. 1hr walls on masonry bearing walls with continuous concrete spread must be held to the minimum dimension required to
Building Section footings and a concrete slab on grade. accommodate light fixtures and the structural and math... your choice
pass 6" the ceiling
Vignette
mechanical components shown on the plans.
height. References 1. All ceilings and roofs are flat.
8. All ducts are placed below the joists.
2. Non-bearing corridor and lobby walls have a one-hour
(minimum) fire-resistance rating. 9. Provide 8” of clearance between the bottom of all
the ducts and the finished ceiling to accommodate
3. Exterior and bearing walls have a two-hour (minimum) light fixtures.
fire-resistance rating. From top of roof
10. Parapets must extend 2’-0” above the top of adjacent level
4. The ceiling height of the laboratory is 15’-0”, the ceiling roof decks.
height of the remaining first floor spaces is 8’-4”, and the
What we call in this ceiling height of the second floor spaces is 9’-0”. 11. The frost depth is 5’-0” below grade.
industry A.F.F. 5. Ceilings are used as return air plenums. All ceilings are
non-rated.
AREWKSHP
The Million-Dollar question
How do you get scored?
AREWKSHP
Different information in different layers. The zoom tool, is your best friend.
Use the layer tool to turn them on and Practice using it.
off just like in AutoCAD.
AREWKSHP
Make sure to check the
one coming out of the
riser
FIRST FLOOR
height
- Duct dimensions are given as width x length
so...
First floor duct + joist space = 24” + 24” = 4’-0” (Laboratory = 20” + 32” = 4’-4”
AREWKSHP
SECOND FLOOR
so...
Second floor duct + joist space = 20” + 24” = 3’-8” (Laboratory = 20” + 32” = 4’-4”
AREWKSHP
From NCARB exam guide
If it wasn't cut by the cut line,
Don't show it
Interior footing
showed as 1'-0"
deep.
1 Minor
2 Major 3 Major
1 Major
feature
What is wrong in this solution?
AREWKSHP
Wrong Partition
rating
AREWKSHP
What about this one?
AREWKSHP
It should go to the
bottom of the deck.
AREWKSHP
13"$5*$& 13"$5*$&
13"$5*$&
5. ADA
The Americans with Disabilities Act
established standards for accessibility
nationwide. These standards are
applicable to all jurisdictions and should
be applied to all projects.
AREWKSHP
5. ADA Building Blocks
[Clearances]
AREWKSHP
5. ADA
[Clearances]
AREWKSHP
5. ADA
[Clearances]
AREWKSHP
5. ADA
[Reach Distances]
AREWKSHP
5. ADA
[Reach Distances]
AREWKSHP
5. ADA
[Reach Distances]
AREWKSHP
5. ADA
[Accessible Routes]
AREWKSHP
5. ADA
[Accessible Routes]
AREWKSHP
5. ADA
[Accessible Routes]
AREWKSHP
5. ADA
[Accessible Routes]
AREWKSHP
5. ADA
[Elevators]
AREWKSHP
5. ADA
[Elevators]
AREWKSHP
5. ADA
[Elevators]
AREWKSHP
5. ADA
[Restrooms]
AREWKSHP
REVIEW QUESTIONS
&
IMPORTANT TOPICS
AREWKSHP
Important Topics:
It is important to review the following topics that will likely appear on the exam:
AREWKSHP
Discussion Question:
a. owner - architect
b. architect - contractor
c. consultant - contractor
d. owner - contractor
AREWKSHP
Discussion Question:
a. owner - architect
b. architect - contractor
c. consultant - contractor
d. owner - contractor
AREWKSHP
Discussion Question:
In general, what is the minimum amount of time an architect should give contractors
to prepare a bid?
a. 1 week
b. 2 weeks
c. 3 weeks
d. 4 weeks
AREWKSHP
Discussion Question:
In general, what is the minimum amount of time an architect should give contractors
to prepare a bid?
a. 1 week
b. 2 weeks
c. 3 weeks
d. 4 weeks
AREWKSHP
Discussion Question:
AREWKSHP
Discussion Question:
Contingency Allowance
AREWKSHP
Discussion Question:
AREWKSHP
Discussion Question:
Lien
AREWKSHP
Discussion Question:
1. A-series
2. B-series
3. C-series
4. D-series
5. G-series
AREWKSHP
Discussion Question:
1. A-series
2. B-series
3. C-series
4. D-series
5. G-series
5. Office administration documents for securing goods and services and administering
and closing our project agreements.
AREWKSHP
Most important to know.....but don't neglect the rest
Discussion Question:
AREWKSHP
Discussion Question:
AREWKSHP
Discussion Question:
a. owner
b. architect
c. contractor
d. surety
AREWKSHP
Discussion Question:
a. owner
Neither the
b. architect
Architect nor the
client is a bank
c. contractor
d. surety
AREWKSHP
Discussion Question:
Upon completion and distribution, the copyright on an architect’s drawings belongs to:
a. owner
b. architect
c. contractor
AREWKSHP
Discussion Question:
Upon completion and distribution, the copyright on an architect’s drawings belongs to:
a. owner
b. architect
c. contractor
These documents are considered “instruments of service” and may not be used for
other undertakings by an architect’s client.
AREWKSHP
Discussion Question:
a. supervisions
b. inspections
c. observations
d. examinations
AREWKSHP
Discussion Question:
a. supervisions
b. inspections
c. observations
d. examinations
AREWKSHP
Discussion Question:
When does the architect have the authority to order an aesthetic design change that
will add two weeks to the construction time?
AREWKSHP
Discussion Question:
When does the architect have the authority to order an aesthetic design change that
will add two weeks to the construction time?
An architect may order changes affecting the contract time or contract sum only with
the consent of the owner in the form of a construction change directive, or with the
additional consent of the contractor in a change order.
AREWKSHP
Discussion Question:
AREWKSHP
Discussion Question:
Conditional Use
Variance
AREWKSHP
Discussion Question:
The owner of a one-story, single family residence would like to expand their
undersized living room by 8 feet. The exterior wall of the existing living room is within
2 feet of the setback. What is the most likely course of action?
AREWKSHP
Discussion Question:
The owner of a one-story, single family residence would like to expand their
undersized living room by 8 feet. The exterior wall of the existing living room is within
2 feet of the setback. What is the most likely course of action?
- a lien release relieves an owner of a lien placed on the property due to outstanding
payment of labor and materials
- the cost of a 2 foot expansion would likely outweigh the benefit of the additional
space
AREWKSHP
Discussion Question:
AREWKSHP
Discussion Question:
Substantial Completion
Final Completion
AREWKSHP
Discussion Question:
A sum of money established in the contract, paid by the contractor to the owner for
failure to complete the job on schedule. Contract may also include a Bonus Clause for
completing the work in advance.
AREWKSHP
Discussion Question:
A sum of money established in the contract, paid by the contractor to the owner for
failure to complete the job on schedule. Contract may also include a Bonus Clause for
completing the work in advance.
Liquidated Damages
AREWKSHP
FURTHER READING
& PRACTICE Highly recommended to do for practice. You can
borrow it from the center.
CDS SESSION #3
• NALSA flash cards
• Ballast practice questions (these contain detailed explanations of answer choices both correct and
incorrect)
• Kaplan Final Exam (in the back of the Kaplan Site Planning and Design review book)
• Kaplan Questions and Answers (a separate publication composed entirely of multiple choice
questions and answers)
• Secretary of the Interior’s Standards for Rehabilitation What to know?
• ADA 2010 The differences between:
• Vignette! 1-Preservation
2-Rehabilitation
• Schiff Hardin Lectures 3-Restoration
• AIA Sample Contracts 4-Reconstruction
Nalsa-Archiflash has a synopsis
AREWKSHP
Thank You!
AREWKSHP