Professional Documents
Culture Documents
Coren Report
Coren Report
Coren Report
MECHANICAL ENGINEER
AUGUST, 2022
Table of Contents
Table of Contents
CHAPTER ONE............................................................................................................................................................................ 5
CHAPTER TWO...........................................................................................................................................................................6
2.0 Summary of Work Experience...............................................................................................................................................6
CHAPTER THREE........................................................................................................................................................................ 7
3.0 DETAILS OF ENGINEERING WORK EXPERIENCE....................................................................................................................7
3.1 EMPLOYER........................................................................................................................................................................... 7
3.1.1 Kainji................................................................................................................................................................................. 7
3.1.2 Jebba................................................................................................................................................................................ 8
3.2 BRIEF OVERVIEW OF HYDRO POWER GENERATION............................................................................................................8
3.2.1 Energy Conversion in Hydro Electric Power Generation..................................................................................................9
3.3 Scope of work at Jebba Hydro Power Plant Mainstream Energy Solution limited..............................................................9
3.4 CAVITATION REPAIR...........................................................................................................................................................10
3.4.0 Abstract.......................................................................................................................................................................... 10
3.4. 1 INTRODUCTION.............................................................................................................................................................10
3.4.2 CAVITATION.................................................................................................................................................................... 11
3.4.3 MEASURES TO MINIMIZE CAVITATION INCLUDE:...........................................................................................................11
3.5 PROCEDURE FOR REPAIR OF CAVITATION: GOUGING........................................................................................................11
3.5.1 TESTING OF THE GOUGED AREA.....................................................................................................................................11
3.5.2 CARBON STEEL ELECTRODE BUILD UP............................................................................................................................12
3.5.3 ANTI CORROSIVE OVER LAY............................................................................................................................................12
3.5.4 REPAIR OF DRAFT TUBE FINS AND VENTS.......................................................................................................................12
3.5.5 PROCEDURE.................................................................................................................................................................... 12
3.5.6 REPAIR OF CAVITATION ON BLADE BODY AND TIPS........................................................................................................13
3.5.7 REPAIR OF CAVITATION ON WITHOUT GOUGING...........................................................................................................13
3.5.8 ELECTRODE SPECIFICATION............................................................................................................................................13
3.5.9 TOOLS AND EQUIPMENTS REQUIRED FOR CAVITATION REPAIR WORK..........................................................................13
3.5.9.1 SAFETY PRECAUTION...................................................................................................................................................14
3.5.10 Bill of Engineering Measurement and Evaluation [BEME] And Take off Sheet.............................................................16
3.5.11 SUBJECT........................................................................................................................................................................ 17
3.5.12 Project: The Scope of works is as indicated in the table below....................................................................................17
3
3.5.13 Bill of Engineering Measurement and Evaluation (BEME)............................................................................................18
3.6 Challenges encountered and Solutions...................................................................................................................19
3.6.1 Experience Gained...............................................................................................................................................19
CHAPTER FOUR........................................................................................................................................................................20
4 Conclusion...................................................................................................................................................................20
CHAPTER 5........................................................................................................................................................................... 21
5.1 Endorsement.................................................................................................................................................................21
5.2 Endorsement.................................................................................................................................................................21
4
CHAPTER ONE
1.0 INTRODUCTION
My name is Abiodun Destiny Akarutu, a native of Igarra, Akoko-Edo LGA of Edo State. I was born on 30th,
March, 1993 in Jebba,Moro local government, Kwara State. I attended NEPA Staff Nursery /primary school,
Jebba South between 1999 to 2004. I had my secondary school education in PHCN Staff Secondary School,
Jebba Niger State between 2004 to 2010. Then I processed to Ahmadu Bello university Zaria, Kaduna State,
where I studied mechanical engineering and I was awarded Bachelor of Engineering with Second Class
(Upper division) in mechanical engineering in 2015.
I proceeded for my National Youth Service Commission (NYSC) in Taraba State where I was attached with
Taraba Road Construction and Maintenance Agency (TARCMA) in 2016 for a one-year mandatory service.
There, I was attached with the maintenance department where we maintain heavy duty road construction
machinery. After my service, I returned to Mainstream Energy Solutions Limited (MESL) as a volunteer
trainee with the company from 2018 to 2019. In 2019, I was sponsored to National Power Training Institute of
Nigeria (NAPTIN) for a comprehensive power training and thorough understanding of the inter-relationship
between the various sectors of the Nigerian energy supply industries and the relationship between the
generation, transmission, and distribution sectors. The National Graduate Skills Development Program
training under NAPTIN spanned from 2019 through 2021 where I graduated as the best student in generation
and overall best graduating student in the training.
I had my Orientation Program in RTC, Kainji. My Class Module 1 and 2 also in RTC, Kainji. My Inter Sub
Sectorial Posting were Jebba Transmission Station and Ibadan Electricity Distribution Company for the
Transmission and Distribution field experience respectively. The technical report of my field experiences
includes Power System Components identification and system operations, maintenance (Routine Preventive
Maintenance), Annual Maintenance experience on the turbine and generator, Trouble report interventions
Overhauling. The departments of my work experience include Generator/Workshop Department and the
Turbine Department in the Mechanical Maintenance Department in Jebba Hydro Power Plant.
I presently work with Mainstream Energy Solutions Limited, Mechanical Maintenance Department, Jebba
Hydro Power Plant where I continuously get exposed to firsthand experience on evolving hydro-power plant
technologies, international plant safety practices and inter managerial skills.
5
CHAPTER TWO
2.0 Summary of Work Experience
Period Detail of Projects/Activities Duration Supervisor
(Months)
Name Signature
6
CHAPTER THREE
This section of the report explains the overview of my employer, hydro-power generation, and the detailed
maintenance projects involved with.
3.1 EMPLOYER
Mainstream Energy Solutions Limited (MESL) was incorporated in 2011 and licensed as a power generating
company MESL took over Kainji and Jebba Hydro Power Plants (HPP) with a total installed capacity of
1338.4MW through a concession agreement in November 2013.
The two hydro plants are cascaded 100km apart with Kainji dam being on the upstream of Jebba.
The two hydro power plants; the Kainji and Jebba have installed capacities of 760MW and 578.4MW
respectively.
Upon takeover in November 2013, the total available capacity of the two plants was 582MW. as of today, MESL
has proudly restored it to 922MW over the course of three years. We currently generate an average 20 percent of
Nigeria's power. Kainji was commissioned as Nigeria first Hydro Power plant in 1968 while Jebba Power plant
was commissioned in 1985.
MESL is a privately-owned company being governed by a Board of Directors and Executive Management that
oversee the day-to-day operations of the plants.
3.1.1 Kainji
Located on the course of the Niger River at Kainji gorge, New Bussa, the original development plan for Kainji
Plant provided for twelve units of 80MW each, with projected total installed capacity at 960MW. However, at the
completion of the project in 1978, the total installed capacity was 760MW with 8 units, leaving four number open
pits with no generating units installed. Statutory overhaul was not carried out on the Generating Units at Kainji in
over forty (40) Years of the plant’s existence, such that most of the units went out of operational service or de-
rated over the years. Presently 346 MW has been recovered out of the installed 760 MW.
7
3.1.2 Jebba
Jebba hydroelectric plant was officially commissioned on 13th April 1985 although commercial operations
commenced in 1983. It has six (6) fixed blade propeller hydraulic turbines with a total installed capacity of 578.4
MW that is, 96.4MW each.
Five units are available for generation. The sixth unit 2G6 is not available due to a major fire incident on the
Generator / AVR system which occurred on the 21st of April 2009. Recovery process has commenced
3.3 Scope of work at Jebba Hydro Power Plant Mainstream Energy Solution limited
I worked as a graduate engineer in this project with a team of skilled supervisors.
On 2G4 Hydro Turbine Generator Annual Maintenance 27th April 2022 to 18th May 2022,
S/NO Task Name Duration Start Time Finish Time
1 Opening of the draft tube access door/ 1 Day Wed Wed 27/04/22
beam manholes 27/04/22
2 Installation of rollers for the beam 1 Day Wed Wed 27/04/22
27/04/22
3 Erection of platform beam, cross members, 1 Day Wed Wed 27/04/22
and assembling of planks 27/04/22
3.4.0 Abstract
Cavitation is an important problem in hydraulic machines that negatively affects their performance and may cause
damages, for achieving higher efficiency of hydro turbines with time. Turbines show declined performance after
few years of operation, as they get severely damaged due to various reasons. Cavitation is a phenomenon which
manifests itself in the pitting of the metallic surfaces of turbine parts because of the formation of cavities. In the
present project research, studies undertaken in this field by several investigators have been discussed extensively,
different causes for the declined performance and efficiency of the hydro turbines and suitable remedial measures
suggested by various investigators have been discussed.
3.4. 1 INTRODUCTION
As the powerhouse is becoming older it is necessary to have qualified and trained personnel to maintain and repair
it. This maintenance can greatly reduce the repair cost and increase productivity, high efficiency, and longer
service life. Among all the renewable energy sources available, hydropower is considered as the most promising
source of energy. In many parts of the country, especially hill states streams coming down the hills posses’
sufficient potential energy that can be utilized. The hydraulic turbine used to convert the potential energy of water
to mechanical energy. Flowing water is directed on to the blades of a turbine runner, creating a force on the blades
Preventive maintenance is an important of every maintenance programme. It is essential if the unit is to deliver its
rated output. The basic objective of good maintenance is to prevent interruption of the unit thereby reducing the
down time of the machine. This can be achieved by strict adherence to the inspection, scheduling and follow up of
preventive maintenance programme. In addition to these scheduled programme, also good records of breakdown
repairs are kept knowing the frequency of maintenance and problem areas. Prior to the scheduled maintenance,
thorough inspection of the turbine and generator was carried out to ascertain if there is any malfunctioning part of
the unit, so that repairs could be incorporated to reduce the machine downtime for good cost estimate of the
maintenance and duration repairs.
10
3.4.2 CAVITATION
Cavitation is a failure of mechanism caused by formation and collapse of gas bubbles in a fluid over a metal
surface.
Cavitation pitting damage occurs as the result of the mechanical effect of repeated fluid impact on the surface of a
point that occurs during bubbles collapse and the formation of vapour bubbles in the liquid flowing through any
hydraulic turbine. Cavitation occurs when the static pressure of the liquid falls below its vapour pressure,
Cavitation erosion problems are found in turbine runner as well as in other parts of the turbine system.
3.5.5 PROCEDURE
After inspection and marking out of the affected areas
Preheating of the area is required with acetylene gas flame
Grinding of the area to remove all the unwanted eroded area on the fins and vents
Carry out penetration test to confirm no part of eroded part is left on the parent metal
Any of the vents discovered cut off because of erosion must be fabricated and replaced
Weld fill the grinded portion of the vents and fins to form the profile of the original fin and vents must be
achieved
Check with bright torch light to confirm there is no water seepage from the fins and vents
Carry out penetration test to confirm no flaws or porosity in the welding part
If the test is confirmed flaws free, smooth and polish the welded area thoroughly for easy water flow and
spin on the fins
The fins and vents should be painted with bitoxy marine protection paint to protect and give the fins a
smoother surface.
12
3.5.6 REPAIR OF CAVITATION ON BLADE BODY AND TIPS
Preheat the area with gas flame
Grind the corrosion affected area
Weld fill the area with E308 anti corrosive electrode
Grind off the weld fill to the profile of the blade
Smooth and polish the welded area to the original profile of blade body and tips
Carry out penetration test to check for flaws in the welding
The procedure is repeated for all the five blades
14
Figure 4: Indication of porosity in welding after penetration test
15
Figure 6: Picture of draft tube fin affected by cavitation after inspection
16
3.5.10 Bill of Engineering Measurement and Evaluation [BEME] And Take off Sheet.
Prequalification
Prequalification is normally used with Requests for Bids and is optional depending on the nature and complexity
of the Goods, Works, or Non-consulting Services.
In prequalification, minimum requirements are normally assessed on a pass/fail basis against such criteria as:
a) Eligibility
b) Nationality
c) Conflict of Interest
d) Bank Eligibility
e) Historical Contract Non-Performance
f) Suspension Based on Execution of Proposal Securing Declaration by the Employer
g) Financial Capabilities
h) Average Annual Turnover
i) Experience
j) General Experience
k) Specific Experience
All Applicants to a prequalification that substantially meet the qualification requirements are invited to submit a
Bid.
3.5.10.1 List of things consider during Evaluation CAC- corporate affairs commission
VAT- value added tax certificate
Income tax clearance certificate
Other list depending on the company
Pension remittance to the relevant tax and authorities
Original equipment manufacturer (OEM) Representation certificate
Evidence of field annual returns
Business objectives relating to the area of arrangement
3.5.11 SUBJECT
Report on Repairs of Areas Affected by Cavitation on Turbine Runner Hub, Turbine Runner Blades and all 8No
Pins at Unit 2G4 Draft Tube
REP: MESL/JHPP/674/PROC.11/Vol.1 /2018
The need to carry-out effective maintenance work on any unit is vital to sustain and improve the unit’s operating
condition. To avert sudden breakdown and cost implication of such, effective maintenance is normally carried out
periodically (in this case, annually).
From the previous observation of cavitation effects on Runner Hub and Runner Blade carried-out it was
anticipated by the User Department that similar effects will be found on the Draft Tube of Unit 2G4.
To effectively carry out the work Messrs. Sly- Okea Integrated Services who was involved and trained on
Welding works by Andritz Team whose performance tracked record on such work is considered proficient was
promptly contacted considering the timely requirement for execution of the works. Messrs Sly- Okea Integrated
Services submitted a proposal of N1,606,500 (One Million, Six Hundred and Six Thousand, Five Hundred Naira
Only) VAT Inclusive.
17
3.5.12 Project: The Scope of works is as indicated in the table below.
S/N Job Description Amount
1 Transportation of Personnel from Jebba to Site daily for the N 30,000.00
work periods (15 working days)
2 Gouging of the affected areas of the blade’s trunnions on the N 150,000.00
Runner Hub
3 Build up welding of the grinded area with E7018-1 H4R N 250,000.00
Electrode
4 Build-up by weld-filling of 8Nos Fins. N 300,000.00
5 Grinding of built-up welded areas on the 8Nos Fins. N 150,000.00
6 Grinding of the Runner Blade before weld-filling. N 100,000.00
7 Welding of the 5No Runner Blade body and tip with Stainless N 200,000.00
Steel Electrode.
8 Grinding and smoothing of the welded areas on the 5No Runner N 150,000.00
Blade.
9 Grinding and welding of 4No Turbo Vent. N 150,000.00
10 Painting of the welded surfaces with bitoxy paint A&B N 50,000.00
Total N
1,000,000.00
Table 3: Negotiated Scope of Work
From the above Scope the sum of N1,000,000.00 (One Million Naira Only) Vat inclusive was negotiated and
agreed upon after much deliberation with Messrs. Sly-Okea Integrated Services for the work.
In view of the above, it is hereby recommended for your approval, the issuance of works Order for Repairs of
Areas affected by Cavitation on Runner Hub, Runner Blades and 8No pins at Unit 2G4 Draft Tube in favor of
Messrs. Sly-Okea Integrated Services at a total cost of N1,000,000.00 (One Million Naira Only) VAT inclusive.
3.6.1Experience Gained
20
CHAPTER FOUR
4 Conclusion
As I have narrated above in this report, I have gained adequate Work Experience in Mechanical
Engineering (hydro power plant maintenance, auxiliary functionalities, welding, and cavitation
works, spill way hydraulics, governor hydraulics) as well as knowledge in procurement matters,
project management and contracts administration. I have now managed to bridge theories and
reality in the plant. I have faced many challenges while implementing projects and I have also been
able to look for the solution to those problems.
Further I certify that, this report results from my involvement in various hydro power plant
engineering works carried out and is not copied from any unauthorized materials and thus the
activities written in this report were carried out under close supervision of Registered Engineers.
Regarding the professional engineering work experience I have gained so far, I finally wish the
COREN to consider, evaluate and approve my application for registration as an Engineer
Name: ...............................................
Signature:…………………………… Date:
………………………………….
21
CHAPTER 5
5.1 Endorsement
I, the undersigned, have gone through the report that has been prepared and we endorse the
experience attained and reported by the writer. Based on our personal knowledge of the character
and professional reputation of the applicant, I recommend for acceptance of this Work
Experience report by the COREN in Partial fulfillment of the requirements for registration as
Registered Mechanical Engineer.
5.2 Endorsement
I, the undersigned, have gone through the report that has been prepared and we endorse the
experience attained and reported by the writer. Based on our personal knowledge of the character
and professional reputation of the applicant, I recommend for acceptance of this Work
Experience report by the COREN in Partial fulfillment of the requirements for registration
as Registered Mechanical Engineer.
22
REFERENCES
1 Escher Wyss Limited (1981) Volume 1 of 8 Data sheets and catalogues for Propeller Turbines, Governors,
Unwatering and Fire Protection System. Jebba Dam (Nigeria)
2 Escher Wyss Limited (1981) Volume 7 0f 8 Data sheets and catalogues for Propeller Turbines, governors,
Unwatering and fire protection system. Jebba Dam (Nigeria)
3 2016weldguru.com
4 Engr. A. Y. Ribadu (1997) Salient Electrical Features in Annual Maintenance of Hydroelectric Generator.
Lecture delivered at NSE Minna Branch, Shiroro (Nigeria)
5 Engr. Liadi Danjuma MNSE (2018) Repair of cavitation in hydraulic turbine
23