CPM and Pert Method

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 24





















Late Early Slack
Activity
Finish Finish (weeks)
A 4 4 0
B 10 10 0
C 25 7 18
D 16 16 0
E 30 30 0
F 30 12 18
G 32 32 0
H 35 34 1
I 35 35 0
J 39 39 0
K 41 41 0
Optimistic Most likely Pessimistic
Activity Description
time time time
A Develop product specifications 2 4 6
B Design manufacturing process 3 7 10
C Source & purchase materials 2 3 5
D Source & purchase tooling & equipment 4 7 9
E Receive & install tooling & equipment 12 16 20
F Receive materials 2 5 8
G Pilot production run 2 2 2
H Evaluate product design 2 3 4
I Evaluate process performance 2 3 5
J Write documentation report 2 4 6
K Transition to manufacturing 2 2 2
optimistic + 4(most likely) + pessimistic
Expected time =
6
Optimistic Most likely Pessimistic Expected
Activity
time time time time
A 2 4 6 4
B 3 7 10 6.83
C 2 3 5 3.17
D 4 7 9 6.83
E 12 16 20 16
F 2 5 8 5
G 2 2 2 2
H 2 3 4 3
I 2 3 5 3.17
J 2 4 6 4
K 2 2 2 2


2
p−o
σ =
2

 6 

Activity Optimistic Most Likely Pessimistic Variance
A 2 4 6 0.44
B 3 7 10 1.36
C 2 3 5 0.25
D 4 7 9 0.69
E 12 16 20 1.78
F 2 5 8 1.00
G 2 2 2 0.00
H 2 3 4 0.11
I 2 3 5 0.25
J 2 4 6 0.44
K 2 2 2 0.00
Path Activities on Path Variance
Number Path (weeks)
1 A,B,D,E,G,H,J,k 4.82

2 A,B,D,E,G,I,J,K 4.96

3 A,C,F,G,H,J,K 2.24

4 A,C,F,G,I,J,K 2.38



specified time − path expected time  DT − EFP 


z= =  
path standard time  σP 
2

σPath 2 = variance of path

















Original critical path


Activity A Activity B Activity C Activity D Activity E

Critical path with project buffer


Activity A Activity B Activity C Activity D Activity E Project Buffer