Professional Documents
Culture Documents
Method Statement - 07 DAREN BEACH
Method Statement - 07 DAREN BEACH
METHOD STATEMENT
FOR THE REPAIR AND REHABILITATION AT DAREN BEECH
Document No.:01-030-00
Table of Contents
CONTRACT 560-S28
CORROSION REPAIR AND PROTECTION
WORKS
METHOD STATEMENT
FOR THE DRAINAGE CHANNEL AT HAII AL BAHAR (REV.02)
1.0 TITLE.
2.0 SCOPE OF WORK
2.1 General description.
2.2 Plant and equipment.
2.3 Materials
2.4 Site planning & preparation
2.5 Work methodology.
2.5.1 Access Road and Mobilization
2.5.2 Installation of Traffic sign and Warning sign
2.5.3 Installation of Hard Barricade and safety pole
2.5.4 Diversion of Flow of water along existing Channel
2.5.5 Rehabilitation of Daren Beech
2.5.6 Site Clean up
2.5.7 Site Welfare
2.5.8 Site Restoration
2.6 Organisation, Responsibilities & Supervision.
2.7 Work Force.
3.0 HEALTH & SAFETY
3.1 Risk assessments
3.2 Risk Abatement
3.3 ES&H Contractor Requirements
3.4 Protective & Safety Equipment.
3.5 Contractual Requirements.
3.6 Information to personnel.
3.7 Emergency Procedures.
3.8 Permit Requirements.
6.0 APPENDICES
Rev. 0 Page 2 of 12
CONTRACT 560-S28
CORROSION REPAIR AND PROTECTION
WORKS
METHOD STATEMENT
FOR THE DRAINAGE CHANNEL AT HAII AL BAHAR (REV.02)
1. TITLE
2. SCOPE OF WORK
Permits to be attained
1. Encroachment Permit
2. Work Permit
3. Excavation Permit
4. Hot Works (if any)
Rev. 0 Page 3 of 12
CONTRACT 560-S28
CORROSION REPAIR AND PROTECTION
WORKS
METHOD STATEMENT
FOR THE DRAINAGE CHANNEL AT HAII AL BAHAR (REV.02)
2.3. Materials
Encroachment permit will be obtained first before starting of any activity in the site. Once the
area is determined and granted, the safety personnel will established the perimeter barricade
to warn others and to prevent the public from entering the worksite. Once all necessary
equipment is positioned, commenced the preparatory job, this isolation method will be strongly
employed throughout the duration of the project to prevent hazard to the public. Also a Safety
watchman will be kept continuously for public and workers safety
The damaged portion of the retaining wall will be replace with new retaining wall as per
approved design and drawing of RC.
As the bottom of foundation of the retaining wall is probably lower than water table
level, therefore dewatering system is required and considered as an important part of
the entire execution. To draw out water a sump pit will be made below the working
level. The water contained in the sump pit can be pumped out by means operation of
the Submersible Pumps at the bottom of pit. The outlet of the pump will towards on a
settlement basin within the vicinity where location will be prior planning.
The replacement part or end portion of the retaining will be broken by means of
mechanical equipment. The debris will be stacked in an area where there is no
hindrance to the traffic flow, area of work or work progress and then will properly be
removed immediately once breaking activity will be finished.
The removal of the debris will be done using a Loader and Dumpers.
Rev. 0 Page 4 of 12
CONTRACT 560-S28
CORROSION REPAIR AND PROTECTION
WORKS
METHOD STATEMENT
FOR THE DRAINAGE CHANNEL AT HAII AL BAHAR (REV.02)
Once demolition is finished or partly finished, excavation can be done. Stake and
layout the area to be excavated including the clearance for the slope according to the
depth of the excavation. The excavation of the retaining wall will be done. Slopes
of excavation shall be cut at the angle of repose for the soil conditions.
All spoil material excavated must be kept a distance away from the edge equal to the
depth of the excavation.
During excavation maintain the minimum distance from the slope of existing structure
at least 2 meter from moving equipment. Barricades and warning signs shall be
identified at the excavation.
Stakes, control survey points, and benchmarks shall be establish and maintained
during construction activities.
Provide adequate sheeting, bracing, shoring and other support to the sides and ends
of all excavation to provide the safety of all workers and to prevent the occurrence of
falls or runs from any portion of the ground outside the excavation or settlement from
previously constructed structures adjacent to the excavation.
The bottom of the excavation shall be keep free from over saturation. In no case
shall the soil be scrapped and dug by equipment near to the bedding formation level
as the result of the disturbance of the material below.
No filling materials shall be placed until all the concrete placement and construction
are completed below the elevation of finished grades.
The surface of the subsoil to receive filling shall be cleaned and prepared as
specified. All formworks, trash and debris shall be removed from the excavation.
The area is free of standing or running water and has been accepted by the Royal
Commission.
Excavation permit will be obtained from Safety department.
Excavation will be inspected daily by competent person for ensuring proper
method and proper handling of buried services, if any.
Means of access shall be provided for workers.
Place sand bags in between the gaps between retaining walls and stone in
order to avoid tilting and for the protection of slope.
Rev. 0 Page 5 of 12
CONTRACT 560-S28
CORROSION REPAIR AND PROTECTION
WORKS
METHOD STATEMENT
FOR THE DRAINAGE CHANNEL AT HAII AL BAHAR (REV.02)
Properly dispose the demolished materials. Demolished material shall not be allowed
to accumulate on site.
Remove and transport debris and rubbish in a manner that will prevent spillage on
existing canal adjacent to the working area.
Leave site clean, neat, and orderly and in condition to begin new construction.
Remove all tools used, equipment and materials from the demolition site upon
completion of work.
Welfare facilities on site shall be provided like rest areas, toilet or washrooms,
shaded area, chilled water dispensing area, smoking area, mosque/prayer area.
Refer Appendix-2, Plan showing the parking and traffic management plan for site.
Grade site to required elevation and profile and clean the area.
Clean and repair damages caused by installation and construction activities use for
temporary works.
Restore existing and permanent facilities used during construction to original or
better condition.
Construction Manager – will be the one to plan and coordinate all the activity in the
site and he will be responsible for coordinating with all other department as well.
Safety Personnel – will be the one to establish all necessary warning signs and
barricades establish the high risk areas in coordination with the Construction
Manager and constantly monitor the activity in terms of safety to all the workers.
Furthermore he will give advice on current and forecasted safety issues and concern.
Site Engineer - will be the one to implement the instruction of the Construction
Manager in the site, he will also directly supervise constantly the manpower and
equipment working in the area and implement all safety regulation and precaution set
by the safety personnel.
Quality Control Inspector – Will be the one to inspect and monitor the repaired
area before recommending to RC Engineer for inspection through RFI. (Request for
inspection)
Safety Manger – Will be responsible for managing day to day activities and will
identify hazards, evaluate risks, advise safe and best practices for the safety of all
personals.
Safety Officer – will report directly to safety manager, and will assist him to organise
the site as per RC approved procedures
Rev. 0 Page 6 of 12
CONTRACT 560-S28
CORROSION REPAIR AND PROTECTION
WORKS
METHOD STATEMENT
FOR THE DRAINAGE CHANNEL AT HAII AL BAHAR (REV.02)
Excavation Competent Person – Will be available at the site, and will advise the
construction procedure of excavation and other activities in order to keep safety first.
Supervisor – will be the one to supervise and assign the works as per schedule.
Carpenters – will be the one to install and remove the shuttering.
Mason – will be the one to perform the concrete works such as patching, surface
preparation and to install grouting.
Technician – will be the one to do application of the water proofing membrane.
Site Engineer – 1
Supervisors – 1
Riggers – 1
Flagman – 2
Skilled Helpers – 4
Masons/Technicians – 4
Carpenters – 4
Painter _ 3
Operators – 2
Drivers – 3
1. To prevent damage on public areas at the work site, an existing condition site
survey (with pictures, station numbers) will be performed, submitted/ and verified
by the RC. Any existing damage will be reported in this survey.
2. Any damage on light poles, access pavements, landscaping or other structures
caused during construction work will be rectified by the contractor.
3. To ensure that no risk or hazard to the public as a result of ongoing construction
activities.
Rev. 0 Page 8 of 12
CONTRACT 560-S28
CORROSION REPAIR AND PROTECTION
WORKS
METHOD STATEMENT
FOR THE DRAINAGE CHANNEL AT HAII AL BAHAR (REV.02)
Rev. 0 Page 9 of 12
CONTRACT 560-S28
CORROSION REPAIR AND PROTECTION
WORKS
METHOD STATEMENT
FOR THE DRAINAGE CHANNEL AT HAII AL BAHAR (REV.02)
15.2 based upon the findings of 3.1.3 Section 1 and 11 above the contractor shall
ensure that adequate stock of Personal Protective Equipment are readily either
available on site or issued to personnel. PPE shall be considered as consumable
items.
All the manual workers that will be working in the site will be informed and reminded
by conducting morning tool box meeting in order to continuously remind them of the
existing safety risk and it will be handled by the designated site supervisor and
sometimes with the presence of the safety personnel.
The following are the safety procedure that will be implemented in case of accident.
In case of traffic accident or person hit by the equipment notify immediately the
police and emergency crew do not engage in moving the person who are injured.
Emergency contact numbers will be prominently posted on bulletin board.
Police — 999
Ambulance — 997
Industrial Security — (03) 341 777
Fire brigade — 998
Waste Water — (03) 341 0109
SCECO — (03) 341 7341
Potable water — (03) 341 6095
Rev. 0 Page 10 of 12
CONTRACT 560-S28
CORROSION REPAIR AND PROTECTION
WORKS
METHOD STATEMENT
FOR THE DRAINAGE CHANNEL AT HAII AL BAHAR (REV.02)
The following are the required permit before implementing the activity:
Encroachment permit
Work permit (Excavation permit & Hot work permit if any)
Transport Permit
4. ENVIRONMENTAL ISSUES
5. QUALITY CONTROL
Prior to the construction activity RC Engineer shall inspect the area to verify the
area of the repair.
RC Engineer shall inspect the approved materials which will be incorporated into
works.
RC engineers shall inspect hold point release (HPR) and witness points as per ITP.
The possible critical work for this activity is during the excavation & concrete
pouring, could be the possible cave-in of excavated area due to softening of sub-soil
or erosion due to water seepage and the presence of concrete pump & mixer during
concrete pouring activities.
Rev. 0 Page 11 of 12
CONTRACT 560-S28
CORROSION REPAIR AND PROTECTION
WORKS
METHOD STATEMENT
FOR THE DRAINAGE CHANNEL AT HAII AL BAHAR (REV.02)
Request for Inspection of Work (RFI) shall be issued to RC Field Engineer 24 hours
in advance. RFI forms shall be issued.
6. APPENDICES
Rev. 0 Page 12 of 12