Geotekindo - Option 2 - Commercial Proposal of DSM Works at KEK Sei Mangke Project R00
Geotekindo - Option 2 - Commercial Proposal of DSM Works at KEK Sei Mangke Project R00
Geotekindo - Option 2 - Commercial Proposal of DSM Works at KEK Sei Mangke Project R00
Project Information
Method of Works : Deep Cement Mixing (DCM)
Project Location : KEK Sei Mangke, Simalungun, North Sumatera
Works Specification
Volume of Works : 465,663.00 m3
Design Installation : Pile diameter 1.2m single head, square pattern, CTC spacing
2.55m (maintain the same replacement ratio), average column
length 22m, cement content 15%, w/c ratio=1.0, assumed soil
weight is 1.5ton/m3
Exclude:
- Working platform.
- Access road to project location.
- Overall project security.
- Local permit or local community coordination fee.
- Mixing trial test.
- Construction trial test.
- Pre and post improvement test.
Commercial Notes:
- Quotation is valid for 30 days and unit price basis.
- Working volume in quotation is initial estimation. Progress payment must be calculated based
on site actual volume.
- Monthly progress and payment should be made within 30 days upon submission of invoice
and supporting documents.
- If exchange rate higher than IDR 16,000.00 / USD and/or diesel fuel price higher than IDR
16,000.00 / litre, unit price become not valid and must be re-adjusted.
- Standby fee Rp. 50,000,000.00 / day if DCM equipment cannot work due to other party
responsibility.
We hope that we can be of further service to you in this project. If you have any queries regarding this
quotation, please do not hesitate to forward them to our attention.
Yours Sincerely,
PT. GEOTEKINDO
Marcello Djunaidy
Director
TOTAL 353,227,823,250
PPN 11% 38,855,060,558
GRAND TOTAL (INCLUDE PPN) 392,082,883,808
PT. GEOTEKINDO
Marcello Djunaidy
Director
A Preparation Works
1 Mobilization 30 1 ls
2 Site Preparation 14 1 ls
B DCM Works
1 DCM Construction (418.704 m') 155 465,663 m3 500 6