Geotekindo - Option 2 - Commercial Proposal of DSM Works at KEK Sei Mangke Project R00

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

Quotation – PT Geotekindo

PT. Watson Engineering Indonesia


The Suites Tower 3 Number : Q.013.01/VIII/23/MD
Jl. Outer Ring Road No 1 Date : Aug 28th, 2023
Kamal Muara, Penjaringan, Jakarta Utara 14470 Attachment(s) : 2 (two)

Attention : Mr. Alberd Tambunan


Subject : Quotation of Deep Cement Mixing Works (Option 2: Big Equipment)
Project : Medan Deep Cement Mixing

Dear Mr. Alberd Tambunan,


Here we would like to submit our quotation of the works as follows. Please be noted that we can
propose some optimization of the work if we can discuss the detail work in a meeting and the soil data
is available.

Project Information
Method of Works : Deep Cement Mixing (DCM)
Project Location : KEK Sei Mangke, Simalungun, North Sumatera

Works Specification
Volume of Works : 465,663.00 m3
Design Installation : Pile diameter 1.2m single head, square pattern, CTC spacing
2.55m (maintain the same replacement ratio), average column
length 22m, cement content 15%, w/c ratio=1.0, assumed soil
weight is 1.5ton/m3

Total Price (include VAT) : Rp 392,082,883,808.00

Terms & Condition:


Include:
- Income Tax (PPh) 2.65%.
- VAT (PPN) 11%.
- DCM construction.
- Cement material (we suggest the material provided by Client).
- Mobilization and demobilization of management staff, manpower and equipment.
- Site team (management staff and manpower) and equipment operator.
- Site facility (site office, warehouse, workshop, stockyard, etc).
- Internal security for material and equipment.
- Construction electricity, water and fuel.

Exclude:
- Working platform.
- Access road to project location.
- Overall project security.
- Local permit or local community coordination fee.
- Mixing trial test.
- Construction trial test.
- Pre and post improvement test.

Gold Coast Office – Liberty Tower 26th Floor


Pantai Indah Kapuk, Kamal Muara, Penjaringan, Jakarta Utara 14470
Phone: +62 21 5020 9866 / +62 21 5020 8566; Email: admin@geotekindo.com; www.geotekindo.com
Page 1 of 4
Technical Notes:
- Trial mix is mandatory prior to start construction to ensure cement content is enough to
achieve the improvement target.

Commercial Notes:
- Quotation is valid for 30 days and unit price basis.
- Working volume in quotation is initial estimation. Progress payment must be calculated based
on site actual volume.
- Monthly progress and payment should be made within 30 days upon submission of invoice
and supporting documents.
- If exchange rate higher than IDR 16,000.00 / USD and/or diesel fuel price higher than IDR
16,000.00 / litre, unit price become not valid and must be re-adjusted.
- Standby fee Rp. 50,000,000.00 / day if DCM equipment cannot work due to other party
responsibility.

We hope that we can be of further service to you in this project. If you have any queries regarding this
quotation, please do not hesitate to forward them to our attention.

Yours Sincerely,
PT. GEOTEKINDO

Marcello Djunaidy
Director

Gold Coast Office – Liberty Tower 26th Floor


Pantai Indah Kapuk, Kamal Muara, Penjaringan, Jakarta Utara 14470
Phone: +62 21 5020 9866 / +62 21 5020 8566; Email: admin@geotekindo.com; www.geotekindo.com
Page 2 of 4
Attachment I – QUOTATION TABLE

Quotation of DCM Work


KEK Sei Mangke Project
Unit Price Subtotal
No. Description Unit Volume Remarks
(Rp) (Rp)

A Preparation Work 2,700,000,000


1 Site Preparation ls 1.00 400,000,000 400,000,000 Site office, warehouse and workshop
2 HSE Expense ls 1.00 200,000,000 200,000,000
6 set of DCM Equipment
including:
Mobilization & Demobilization of - DCM Rig
3 set 6.00 350,000,000 2,100,000,000
Equipment - Generator
- Mixing Silo
- Excavator
3 Standby Fee unit*day 1.00 50,000,000 rate only

B DCM Work 350,527,823,250


Diameter 1.2m single head; square
pattern; CTC spacing 2.55m (same
1 DCM Construction (418.704 m') m3 465,663.00 350,000 162,982,050,000
replacement ratio); average column depth
22m; max SPT 25
Cement type I with 15% cement content,
2 DCM Material ton 104,774.18 1,790,000 187,545,773,250
1.0 w/c ratio, soil unit weight 1.5t/m3

TOTAL 353,227,823,250
PPN 11% 38,855,060,558
GRAND TOTAL (INCLUDE PPN) 392,082,883,808

PT. GEOTEKINDO

Marcello Djunaidy
Director

Gold Coast Office – Liberty Tower 26th Floor


Pantai Indah Kapuk, Kamal Muara, Penjaringan, Jakarta Utara 14470
Phone: +62 21 5020 9866 / +62 21 5020 8566; Email: admin@geotekindo.com; www.geotekindo.com
Page 3 of 4
Attachment II – PLANNED PROJECT SCHEDULE

Construction Schedule of DCM Works


Duration Month-0 Month-1 Month-2 Month-3 Month-4 Month-5 Month-6 Month-7
No. Description Volume Unit Daily Volume Total Unit
(Days) 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

A Preparation Works
1 Mobilization 30 1 ls
2 Site Preparation 14 1 ls
B DCM Works
1 DCM Construction (418.704 m') 155 465,663 m3 500 6

Gold Coast Office – Liberty Tower 26th Floor


Pantai Indah Kapuk, Kamal Muara, Penjaringan, Jakarta Utara 14470
Phone: +62 21 5020 9866 / +62 21 5020 8566; Email: admin@geotekindo.com; www.geotekindo.com
Page 4 of 4

You might also like