B.Sc. Aviation Practical Sheet

Task Card Number : 01 Date: 22 May 2021 Time to perform:2Hrs

Task Name. Identification, removal fitment of invertor.

Auth. IIAE/ Learjet24D Location: Hanger

Tools/Tester: CSD, PSD, Pliers, screw driver, Set spanner, Plug extractor, Torque wrench, Multi

meter, Megger

Consumable Goods: Rag Piece, Colin, Brushes, locking wire, Plastic bags, anti corrosion

solution.

Safety Measured:
1) No smoking inside or around hanger

2) Please do not keep equipments in walk way

3) Protective clothes and gloves must be dry and clean.

4) Put the supply switch off.

5) Warning tag must be displayed in electrical opened connection

Snag:

During the routine check up of inverter found it is not getting switch ON. After going for trouble
shooting found our primary inverter is suspected Un- serviceable. Hence to confirm from senior
the decision made to remove the inverter and check for serviceability.

Task Procedure:

Aim: Primillarly aircraft is provided DC Power supply by two independent DC starter generator and
operated parallel. Aircraft AC power requirement are provided by two static inverters installed in tail cone.
Each inverter is rated at 115 V 400 Hz and 1000 VA. During normal operation, the inverter operates in
parallel. Two switches are also installed in cockpit to operate these invertors.

Location:

Static inverters installed in tail cone between frame no. 30 and 29 of aircraft.. .
Activity:
Removal/ Installation

Removal of inverter:
1) Lower tail cone access door.
2) Disconnect both aircraft batteries.
3) Disconnect electrical plugs from inverters.
4) Remove attaching parts and inverter form aircraft.

Check Electrical System

 Check electrical wiring for damage.


 Check wire clamp and supports for security.
 Check all wiring is supported clear and sharp metal edges.
 Check wiring for liquid impregnation.
 Check terminal connections.
 Check bonding jumper.
 Check shorting of wire
 Check plugs connector.

Note: While checking all electrical connections and condition of connector, found one connector was
having short circuit. Replace it with new one and check the continuity. Found satisfactory working. ,.

Installation of inverter:

1) Install inverter and secure with attaching parts.


2) Connect electrical plug to inverter.
3) Connect aircraft batteries.

Post-Task Inspection
1) Check the full functional check and get satisfaction.
2) Wind up the service area and look for any FOD.
3) Complete the all documentations/entries.