Download as pdf or txt
Download as pdf or txt
You are on page 1of 55

lOMoARcPSD|35623485

21dj0058 pow - pow

Civil Engineering (Ateneo de Davao University)

Scan to open on Studocu

Studocu is not sponsored or endorsed by any college or university


Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)
lOMoARcPSD|35623485

REPUBLIC OF THE PHILIPPINES


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
QUEZON II DISTRICT ENGINEERING OFFICE
DALAHICAN ROAD, LUCENA CITY

CONVERGE AND SPECIAL SUPPORT PROGRAM:


Special Road Fund – Motor Vehicle User’s Charge
(MVUC) as per R.A. 11239, Preventive
Maintenance – Primary Roads, MSR Diversion Rd
– K0129+1006 – 130+568, K0130+624 –
K0130+827

(FY 2021 REGULAR INFRA)

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE DISTRICT ENGINEER
QUEZON II DISTRICT ENGINEERING OFFICE
Dalahican Road, Lucena City

Date : December 01, 2020

EXECUTIVE SUMMARY
For THE DISTRICT ENGINEER

Project ID :
Project Name : CONVERGE AND SPECIAL SUPPORT PROGRAM:
Special Road Fund – Motor Vehicle User’s Charge
(MVUC) as per R.A. 11239, Preventive Maintenance
– Primary Roads, MSR Diversion Rd – K0129+1006
– K0130+568, K0130+624 – K0130+827
Location of Project : Lucena City, Quezon
2. Project Category : Roads
3. Source of Fund : GAA 2021
4. Action Recommended : For Approval
5. Implementing Office : DPWH Quezon II District Engineering Office
6. Reviewing Offices : DPWH Quezon II District Engineering Office
7. Appropriation : P 83,840,000.00
8. ABC : P 80,905,600.00
9. Project Duration : 149 Calendar Days
10. Mode of Implementation : By Contract

PREPARED BY:

RAINIER D. PALAGANAS
Engineer II

SUBMITTED BY:

FAUSTINO MARK ANTHONY S. DE LA CRUZ


Chief, Planning and Design Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


QUEZON 2ND DISTRICT ENGINEERING OFFICE
FORM POW-2015-01-00
PROGRAM OF WORKS/BUDGET COST

Project : CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Net Length (a) Road 798.00 l.m.
Preventive Maintenance - Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827 (b) Bridge
Project ID : (c ) Others
Location : Lucena City, Quezon Target Start Date : 2021
Station Limits : K0129+1006 - K0130+568, K0130+624 - K0130+827 Total Project Duration : 149 Calendar days
Appropriation : P 83,840,000.00 No. of Pre-determined : 98 Calendar days
Source of Fund : GAA 2021 Unworkable Days 51 Calendar days

AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
PART A Facilities for the Engineer 0.41% 270,007.89 0.41% 270,007.89
PART B Other General Requirements 1.49% 972,341.47 1.49% 972,341.47
PART C Earthwork 3.26% 2,132,628.32 3.26% 2,132,628.32
PART D Subbase and Base Course 0.09% 59,815.25 0.09% 59,815.25
PART E Surface Courses (PLS. SEE FORM POW-2015-01C-00) 87.05% 56,949,181.28 87.05% 56,949,181.28
PART F Bridge Construction 0.00% 0.00 0.00% 0.00
PART G Drainage and Slope Protection Structures 0.00% 0.00 0.00% 0.00
PART H Miscellaneous Structures 7.70% 5,035,936.57 7.70% 5,035,936.57
PART I Provisional Sum 0.00% 0.00 0.00% 0.00
PART J Daywork 0.00% 0.00 0.00% 0.00

Total 100.00% 65,419,910.78 100.00% 65,419,910.78

EQUIPMENT: BREAKDOWN OF EXPENDITURES:


DESCRIPTION REQUIRED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
1. Labor 564,046.75 564,046.75 A. Total Direct Cost 65,419,910.78 65,419,910.78
2. Materials 61,080,082.69 61,080,082.69 B. OCM and Profit 11,633,041.60 11,633,041.60
3. Rental of Equipment 3,775,781.34 3,775,781.34 C. Value Added Tax (5%) 3,852,647.62 3,852,647.62
4. Provisional Sum / Daywork - - D. Total Construction Cost 80,905,600.00 80,905,600.00
(PLS. SEE FORM POW-2015-01B-00) 5. OCM and Profit 11,633,041.60 11,633,041.60 E. Eng'g & Administrative Overhead, 3.5% 2,934,400.00 2,934,400.00
6. Value Added Tax (5%) 3,852,647.62 3,852,647.62 F. RROW Acquisition - -
7. EAO, 3.5% 2,934,400.00 2,934,400.00 G. Physical Reserved (Contingency) - -
8. RROW Acquisition - -
9. Physical Reserved (Contingency) - -
10.TOTAL ESTIMATED COST 83,840,000.00 83,840,000.00 H. TOTAL ESTIMATED COST 83,840,000.00 83,840,000.00

Preparation and Submission: Evaluation: Approval:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:

RAINIER D. PALAGANAS FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN WILFREDO L. RACELIS MA. CHYMBELIN D. IBAL
Engineer II Chief, Planning & Design Section Chief, Construction Section Engineer III Assistant District Engineer
Maintenance Section OIC - Office of the Assistant District Engineer OIC - Office of the District Engineer
Date: December 01, 2020

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance - Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

FORM POW-2015-01A-00

ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)

AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED

PART A FACILITIES FOR THE ENGINEER

A.1.1 (3) Construction of Field Office for the Engineer 1.00 1.00 lump sum 102,428.19 102,428.19 102,428.19 102,428.19 116,153.57 116,153.57 0.16% 0.16%
Provision of Furnitures/Fixtures, Equipment & Applicances for the Field Office for the
A.1.1 (11) 1.00 1.00 lump sum 41,939.11 41,939.11 41,939.11 41,939.11 47,558.95 47,558.95 0.06% 0.06%
Engineer

A.1.2(6) Operation and Maintenance of 4x2 Pick Up Type Service Vehicle for the Engineer 4.97 4.97 month 123,405.59 123,405.59 24,830.10 24,830.10 26,071.61 26,071.61 0.19% 0.19%

A.1.4(1) Provision of Progress Photographs 149.00 149.00 each 2,235.00 2,235.00 15.00 15.00 17.01 17.01 0.00% 0.00%
TOTAL OF PART A 270,007.89 270,007.89 0.41% 0.41%
PART B OTHER GENERAL REQUIREMENTS

B.5 Project Billboard / Signboard 2.00 2.00 each 11,650.32 11,650.32 5,825.16 5,825.16 7,217.38 7,217.38 0.02% 0.02%
B.7(2) Occupational Safety and Health Program 1.00 1.00 lump sum 255,443.84 255,443.84 255,443.84 255,443.84 289,673.32 289,673.32 0.39% 0.39%
B.8(2) Traffic Management 1.00 1.00 lump sum 585,247.31 585,247.31 585,247.31 585,247.31 663,670.44 663,670.44 0.89% 0.89%
B.9 Mobilization / Demobilization 1.00 1.00 lump sum 120,000.00 120,000.00 120,000.00 120,000.00 126,000.00 126,000.00 0.18% 0.18%
TOTAL OF PART B 972,341.47 972,341.47 1.49% 1.49%
PART C EARTHWORKS

101(3)c1 Removal of Actual Structures/Obstruction (0.05m thick, ACP) 5,346.60 5,346.60 sq.m. 2,078,330.35 2,078,330.35 388.72 388.72 481.62 481.62 3.18% 3.18%

101(3)b5 Removal of Actual Structures/Obstruction (0.28m thick, PCCP (Unreinforced)) 60.30 60.30 sq.m. 10,972.19 10,972.19 181.96 181.96 225.46 225.46 0.02% 0.02%

102(2) Surplus Common Excavation 306.83 306.83 cu.m. 37,540.66 37,540.66 122.35 122.35 151.60 151.60 0.06% 0.06%
105(1)a Subgrade Preparation (Common Material) 357.99 357.99 sq.m. 5,785.12 5,785.12 16.16 16.16 20.02 20.02 0.01% 0.01%
TOTAL OF PART C 2,132,628.32 2,132,628.32 3.26% 3.26%
PART D SUBBASE AND BASE COURSE

200(1) Aggregate Subbase Course 65.70 65.70 cu.m. 59,815.25 59,815.25 910.43 910.43 1,128.02 1,128.02 0.09% 0.09%
TOTAL OF PART D 59,815.25 59,815.25 0.09% 0.09%
PART E SURFACE COURSES

302(2) Bituminous Tack Coat (Emulsified Asphalt) 41,372.30 41,372.30 sq.m. 2,562,600.26 2,562,600.26 61.94 61.94 76.74 76.74 3.92% 3.92%
310(1)b Bituminous Concrete Surface Wearing Course, Hot-Laid (40mm) 20,686.15 20,686.15 sq.m. 26,839,659.04 26,839,659.04 1,297.47 1,297.47 1,607.57 1,607.57 41.03% 41.03%
310(2)b Bituminous Concrete Surface Binder Course, Hot-Laid (40mm) 20,686.15 20,686.15 sq.m. 26,839,659.04 26,839,659.04 1,297.47 1,297.47 1,607.57 1,607.57 41.03% 41.03%

311(1)f1 Portland Cement Concrete Pavement (Unreinforced) (0.30 m thick, 14 days) 357.99 357.99 sq.m. 707,262.94 707,262.94 1,975.65 1,975.65 2,447.83 2,447.83 1.08% 1.08%

TOTAL OF PART E 56,949,181.28 56,949,181.28 87.05% 87.05%


PART F BRIDGE CONSTRUCTION

TOTAL OF PART F
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES

TOTAL OF PART G

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance - Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

FORM POW-2015-01A-00

ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT)

AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED

PART H FACILITIES FOR THE


MISCELLANEOUS ENGINEER
STRUCTURES

600(4) Curb and Gutter (Cast in Place) 63.00 63.00 l.m. 52,179.12 52,179.12 828.24 828.24 1,026.19 1,026.19 0.08% 0.08%
601(1) Sidewalk (100mm thk.) 75.60 75.60 sq.m. 54,157.57 54,157.57 716.37 716.37 887.59 887.59 0.08% 0.08%

605(2)ai2 Regulatory Signs (600mm, R6-8B, Miscellaneous Signs Pedestrian Crossing) 6.00 6.00 each 43,823.64 43,823.64 7,303.94 7,303.94 9,049.58 9,049.58 0.07% 0.07%

607(3)b Internally Illuminated (Solar) Pavement Levelled Marker/Stud Flush Type 404.00 404.00 each 3,774,325.56 3,774,325.56 9,342.39 9,342.39 11,575.22 11,575.22 5.77% 5.77%
612(1) Reflectorized Thermoplastic Pavement Markings White 855.76 855.76 sq.m. 616,215.66 616,215.66 720.08 720.08 892.18 892.18 0.94% 0.94%
618(1) Reflectorized Thermoplastic Rumble Strips 687.75 687.75 sq.m. 495,235.02 495,235.02 720.08 720.08 892.18 892.18 0.76% 0.76%
TOTAL OF PART H 5,035,936.57 5,035,936.57 7.70% 7.70%
PART I PROVISIONAL SUM

TOTAL OF PART I
PART J DAYWORK

TOTAL OF PART J
GRAND TOTAL 65,419,910.78 65,419,910.78 100.00% 100.00%

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance - Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827

Lucena City, Quezon


FORM POW-2015-01B-00
MINIMUM EQUIPMENT REQUIREMENT
Number of Number of
No. Equipment Description Capacity No. Equipment Description Capacity
Equipment Equipment
1 Low Bed Trailer 1 31
SF1900C 1920 mm milling width
WIRTGEN 1
2 /150 mm max depth 32
3 Pay Loader 1.50 cu.m. 1 33
4 Dump Truck 10 cu.m. 2 34
5 Backhoe with Pavement Breaker 0.80 cu.m. 1 35
6 Concrete Saw, Blade Ø 14" 7.5 Hp 1 36
7 Motorized Road Grader, G710A 1 37
8 Vibratory Roller, SP56 10 m.t. 1 38
9 Water Truck 16,000 lit. 1 39
10 Asphalt Distributor, 10 ft. Wide 5 tons 1 40
11 Power Broom 20 m. wide 1 41
12 Asphalt Paver 80 Hp 1 42
13 Pneumatic Tire Roller 10 m.t. 1 43
14 Tandem Steel Roller, CC421 10.1 m.t. 1 44
15 Concrete Vibrator 2 45
16 Concrete Screeder 5.5 Hp 1 46
17 Bar Cutter, Single Phase, 25 mm. 1 47
18 One Bagger Mixer 1 48
19 Cargo Truck 5T 1 49
20 Drilling Machine / Hammer, CP-55A 1 50
21 Demolition / Chipping Hammer (Breaker) TL700-AV 1 51
22 Portable Air Compressor (Diesel Engine), 15-35CF 1 52
23 Generator Set 5 kVa 1 53
24 Cargo Truck 2-5 MT 1 54
25 Application Machine 1 55
26 Kneading Machine 1 56
27 57
28 58
29 59
SUB-TOTAL 28 SUB-TOTAL 0
TOTAL 28

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance - Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827

Lucena City, Quezon

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART A FACILITIES FOR THE ENGINEER
As Submitted 0.16% 1.00 lump sum 77,978.59 24,449.60 - 102,428.19 8% 8,194.26 5,531.12 116,153.57
A.1.1 (3) Construction of Field Office for the Engineer
As Evaluated 0.16% 1.00 lump sum 77,978.59 24,449.60 - 102,428.19 8% 8,194.26 5,531.12 116,153.57
Provision of Furnitures/Fixtures, Equipment & Applicances for the Field Office for As Submitted 0.06% 1.00 lump sum 41,939.11 - - 41,939.11 8% 3,355.13 2,264.71 47,558.95
A.1.1 (11)
the Engineer As Evaluated 0.06% 1.00 lump sum 41,939.11 - - 41,939.11 8% 3,355.13 2,264.71 47,558.95
As Submitted 0.19% 4.97 month 64,385.85 59,019.74 - 123,405.59 0% - 6,170.28 129,575.87
A.1.2(6) Operation and Maintenance of 4x2 Pick Up Type Service Vehicle for the Engineer
As Evaluated 0.19% 4.97 month 64,385.85 59,019.74 - 123,405.59 0% - 6,170.28 129,575.87
As Submitted 0.00% 149.00 each 2,235.00 - - 2,235.00 8% 178.80 120.69 2,534.49
A.1.4(1) Provision of Progress Photographs
As Evaluated 0.00% 149.00 each 2,235.00 - - 2,235.00 8% 178.80 120.69 2,534.49
As Submitted 0.41% 186,538.55 83,469.34 - 270,007.89 11,728.19 14,086.80 295,822.88
TOTAL OF PART A
As Evaluated 0.41% 186,538.55 83,469.34 - 270,007.89 11,728.19 14,086.80 295,822.88
PART B OTHER GENERAL REQUIREMENTS
As Submitted 0.02% 2.00 each 9,320.00 2,330.32 - 11,650.32 18% 2,097.06 687.37 14,434.75
B.5 Project Billboard / Signboard
As Evaluated 0.02% 2.00 each 9,320.00 2,330.32 - 11,650.32 18% 2,097.06 687.37 14,434.75
As Submitted 0.39% 1.00 lump sum 37,522.40 199,660.00 18,261.44 255,443.84 8% 20,435.51 13,793.97 289,673.32
B.7(2) Occupational Safety and Health Program
As Evaluated 0.39% 1.00 lump sum 37,522.40 199,660.00 18,261.44 255,443.84 8% 20,435.51 13,793.97 289,673.32
As Submitted 0.89% 1.00 lump sum 554,096.51 12,680.40 18,470.40 585,247.31 8% 46,819.78 31,603.35 663,670.44
B.8(2) Traffic Management
As Evaluated 0.89% 1.00 lump sum 554,096.51 12,680.40 18,470.40 585,247.31 8% 46,819.78 31,603.35 663,670.44
As Submitted 0.18% 1.00 lump sum - - 120,000.00 120,000.00 0% - 6,000.00 126,000.00
B.9 Mobilization / Demobilization
As Evaluated 0.18% 1.00 lump sum - - 120,000.00 120,000.00 0% - 6,000.00 126,000.00
As Submitted 1.49% 600,938.91 214,670.72 156,731.84 972,341.47 69,352.35 52,084.69 1,093,778.51
TOTAL OF PART B
As Evaluated 1.49% 600,938.91 214,670.72 156,731.84 972,341.47 69,352.35 52,084.69 1,093,778.51
PART C EARTHWORKS
As Submitted 3.18% 5,346.60 sq.m. - - 2,078,330.35 2,078,330.35 18% 374,099.46 122,621.49 2,575,051.30
101(3)c1 Removal of Actual Structures/Obstruction (0.05m thick, ACP)
As Evaluated 3.18% 5,346.60 sq.m. - - 2,078,330.35 2,078,330.35 18% 374,099.46 122,621.49 2,575,051.30
As Submitted 0.02% 60.30 sq.m. 72.36 436.30 10,463.53 10,972.19 18% 1,974.99 647.36 13,594.54
101(3)b5 Removal of Actual Structures/Obstruction (0.28m thick, PCCP (Unreinforced))
As Evaluated 0.02% 60.30 sq.m. 72.36 436.30 10,463.53 10,972.19 18% 1,974.99 647.36 13,594.54
As Submitted 0.06% 306.83 cu.m. - 1,110.06 36,430.60 37,540.66 18% 6,757.32 2,214.90 46,512.88
102(2) Surplus Common Excavation
As Evaluated 0.06% 306.83 cu.m. - 1,110.06 36,430.60 37,540.66 18% 6,757.32 2,214.90 46,512.88
As Submitted 0.01% 357.99 sq.m. - 259.00 5,526.12 5,785.12 18% 1,041.32 341.32 7,167.76
105(1)a Subgrade Preparation (Common Material)
As Evaluated 0.01% 357.99 sq.m. - 259.00 5,526.12 5,785.12 18% 1,041.32 341.32 7,167.76
As Submitted 3.26% 72.36 1,805.36 2,130,750.60 2,132,628.32 383,873.09 125,825.07 2,642,326.48
TOTAL OF PART C
As Evaluated 3.26% 72.36 1,805.36 2,130,750.60 2,132,628.32 383,873.09 125,825.07 2,642,326.48
PART D SUBBASE AND BASE COURSE
As Submitted 0.09% 65.70 cu.m. 53,444.32 285.14 6,085.79 59,815.25 18% 10,766.75 3,529.10 74,111.10
200(1) Aggregate Subbase Course
As Evaluated 0.09% 65.70 cu.m. 53,444.32 285.14 6,085.79 59,815.25 18% 10,766.75 3,529.10 74,111.10
As Submitted 0.09% 53,444.32 285.14 6,085.79 59,815.25 10,766.75 3,529.10 74,111.10
TOTAL OF PART D
As Evaluated 0.09% 53,444.32 285.14 6,085.79 59,815.25 10,766.75 3,529.10 74,111.10

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance - Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827

Lucena City, Quezon

FORM POW-2015-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
ITEM NO. DESCRIPTION % QTY. UNIT 5% VAT TOTAL COST
MATERIAL LABOR EQUIPMENT TOTAL % VALUE
PART E FACILITIES FORCOURSES
SURFACE THE ENGINEER
As Submitted 3.92% 41,372.30 sq.m. 2,433,518.69 26,402.04 102,679.53 2,562,600.26 18% 461,268.05 151,193.42 3,175,061.73
302(2) Bituminous Tack Coat (Emulsified Asphalt)
As Evaluated 3.92% 41,372.30 sq.m. 2,433,518.69 26,402.04 102,679.53 2,562,600.26 18% 461,268.05 151,193.42 3,175,061.73
As Submitted 41.03% 20,686.15 sq.m. 26,121,022.19 82,790.37 635,846.48 26,839,659.04 18% 4,831,138.63 1,583,539.88 33,254,337.55
310(1)b Bituminous Concrete Surface Wearing Course, Hot-Laid (40mm)
As Evaluated 41.03% 20,686.15 sq.m. 26,121,022.19 82,790.37 635,846.48 26,839,659.04 18% 4,831,138.63 1,583,539.88 33,254,337.55
As Submitted 41.03% 20,686.15 sq.m. 26,121,022.19 82,790.37 635,846.48 26,839,659.04 18% 4,831,138.63 1,583,539.88 33,254,337.55
310(2)b Bituminous Concrete Surface Binder Course, Hot-Laid (40mm)
As Evaluated 41.03% 20,686.15 sq.m. 26,121,022.19 82,790.37 635,846.48 26,839,659.04 18% 4,831,138.63 1,583,539.88 33,254,337.55
As Submitted 1.08% 357.99 sq.m. 694,973.15 7,241.63 5,048.16 707,262.94 18% 127,307.33 41,728.51 876,298.78
311(1)f1 Portland Cement Concrete Pavement (Unreinforced) (0.30 m thick, 14 days)
As Evaluated 1.08% 357.99 sq.m. 694,973.15 7,241.63 5,048.16 707,262.94 18% 127,307.33 41,728.51 876,298.78
As Submitted 87.05% 55,370,536.22 199,224.41 1,379,420.65 56,949,181.28 10,250,852.64 3,360,001.69 70,560,035.61
TOTAL OF PART E
As Evaluated 87.05% 55,370,536.22 199,224.41 1,379,420.65 56,949,181.28 10,250,852.64 3,360,001.69 70,560,035.61
PART F BRIDGE CONSTRUCTION

As Submitted
TOTAL OF PART F
As Evaluated
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES

As Submitted
TOTAL OF PART G
As Evaluated
PART H MISCELLANEOUS STRUCTURES
As Submitted 0.08% 63.00 l.m. 46,742.85 3,599.30 1,836.97 52,179.12 18% 9,392.24 3,078.57 64,649.93
600(4) Curb and Gutter (Cast in Place)
As Evaluated 0.08% 63.00 l.m. 46,742.85 3,599.30 1,836.97 52,179.12 18% 9,392.24 3,078.57 64,649.93
As Submitted 0.08% 75.60 sq.m. 47,485.87 4,103.71 2,567.99 54,157.57 18% 9,748.36 3,195.30 67,101.23
601(1) Sidewalk (100mm thk.)
As Evaluated 0.08% 75.60 sq.m. 47,485.87 4,103.71 2,567.99 54,157.57 18% 9,748.36 3,195.30 67,101.23
As Submitted 0.07% 6.00 each 40,726.62 1,747.74 1,349.28 43,823.64 18% 7,888.26 2,585.60 54,297.50
605(2)ai2 Regulatory Signs (600mm, R6-8B, Miscellaneous Signs Pedestrian Crossing)
As Evaluated 0.07% 6.00 each 40,726.62 1,747.74 1,349.28 43,823.64 18% 7,888.26 2,585.60 54,297.50
As Submitted 5.77% 404.00 each 3,728,200.88 18,457.85 27,666.83 3,774,325.56 18% 679,378.60 222,685.21 4,676,389.37
607(3)b Internally Illuminated (Solar) Pavement Levelled Marker/Stud Flush Type
As Evaluated 5.77% 404.00 each 3,728,200.88 18,457.85 27,666.83 3,774,325.56 18% 679,378.60 222,685.21 4,676,389.37
As Submitted 0.94% 855.76 sq.m. 557,416.39 20,338.06 38,461.21 616,215.66 18% 110,918.82 36,356.72 763,491.20
612(1) Reflectorized Thermoplastic Pavement Markings White
As Evaluated 0.94% 855.76 sq.m. 557,416.39 20,338.06 38,461.21 616,215.66 18% 110,918.82 36,356.72 763,491.20
As Submitted 0.76% 687.75 sq.m. 447,979.72 16,345.12 30,910.18 495,235.02 18% 89,142.30 29,218.87 613,596.19
618(1) Reflectorized Thermoplastic Rumble Strips
As Evaluated 0.76% 687.75 sq.m. 447,979.72 16,345.12 30,910.18 495,235.02 18% 89,142.30 29,218.87 613,596.19
As Submitted 7.70% 4,868,552.33 64,591.78 102,792.46 5,035,936.57 906,468.58 297,120.27 6,239,525.42
TOTAL OF PART H
As Evaluated 7.70% 4,868,552.33 64,591.78 102,792.46 5,035,936.57 906,468.58 297,120.27 6,239,525.42
PART I PROVISIONAL SUM
As Submitted
As Evaluated
As Submitted
TOTAL OF PART I
As Evaluated
PART J DAYWORK
As Submitted
As Evaluated
As Submitted
TOTAL OF PART J
As Evaluated
As Submitted 100.00% 61,080,082.69 564,046.75 3,775,781.34 65,419,910.78 11,633,041.60 3,852,647.62 80,905,600.00
GRAND TOTAL
As Evaluated 100.00% 61,080,082.69 564,046.75 3,775,781.34 65,419,910.78 11,633,041.60 3,852,647.62 80,905,600.00

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


QUEZON 2ND DISTRICT ENGINEERING OFFICE
FORM ABC-2015-02-00
CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance - Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 -
K0130+827
Lucena City, Quezon

SUMMARY OF APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 149 C.D.
TOTAL MARK-UP
ITEM NO. DESCRIPTION ESTIMATED DIRECT COST VAT TOTAL INDIRECT COST TOTAL COST
% VALUE
AS SUBMITTED 270,007.89 4.34% 11,728.19 14,086.80 25,814.99 295,822.88
PART A FACILITIES FOR THE ENGINEER
AS EVALUATED 270,007.89 4.34% 11,728.19 14,086.80 25,814.99 295,822.88
AS SUBMITTED 972,341.47 7.13% 69,352.35 52,084.69 121,437.04 1,093,778.51
PART B OTHER GENERAL REQUIREMENTS
AS EVALUATED 972,341.47 7.13% 69,352.35 52,084.69 121,437.04 1,093,778.51
AS SUBMITTED 2,132,628.32 18.00% 383,873.09 125,825.07 509,698.16 2,642,326.48
PART C EARTHWORKS
AS EVALUATED 2,132,628.32 18.00% 383,873.09 125,825.07 509,698.16 2,642,326.48
AS SUBMITTED 59,815.25 18.00% 10,766.75 3,529.10 14,295.85 74,111.10
PART D SUBBASE AND BASE COURSE
AS EVALUATED 59,815.25 18.00% 10,766.75 3,529.10 14,295.85 74,111.10
AS SUBMITTED 56,949,181.28 18.00% 10,250,852.64 3,360,001.69 13,610,854.33 70,560,035.61
PART E SURFACE COURSE
AS EVALUATED 56,949,181.28 18.00% 10,250,852.64 3,360,001.69 13,610,854.33 70,560,035.61
AS SUBMITTED
PART F BRIDGE CONSTRUCTION
AS EVALUATED
AS SUBMITTED
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
AS EVALUATED
AS SUBMITTED 5,035,936.57 18.00% 906,468.58 297,120.27 1,203,588.85 6,239,525.42
PART H MISCELLANEOUS STRUCTURES
AS EVALUATED 5,035,936.57 18.00% 906,468.58 297,120.27 1,203,588.85 6,239,525.42
AS SUBMITTED
PART I PROVISIONAL SUM
AS EVALUATED
AS SUBMITTED
PART J DAYWORK
AS EVALUATED
AS SUBMITTED 65,419,910.78 11,633,041.60 3,852,647.62 15,485,689.22 80,905,600.00
TOTAL
AS EVALUATED 65,419,910.78 11,633,041.60 3,852,647.62 15,485,689.22 80,905,600.00

Preparation and Submission: Evaluation: Approval:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost: Recommending Approval: Approved:

RAINIER D. PALAGANAS FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN WILFREDO L. RACELIS MA. CHYMBELIN D. IBAL
Engineer II Chief, Planning & Design Section Chief, Construction Section Engineer III Assistant District Engineer
Maintenance Section OIC - Office of the Assistant District Engineer OIC - Office of the District Engineer
Date: December 01, 2020

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


QUEZON 2ND DISTRICT ENGINEERING OFFICE
FORM ABC-2015-02A-00
CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance - Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 149 C.D.
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST
PART A FACILITIES FOR THE ENGINEER
AS SUBMITTED 1.00 lump sum 102,428.19 8% 8,194.26 5,531.12 13,725.38 116,153.57 116,153.57
A.1.1 (3) Construction of Field Office for the Engineer
AS EVALUATED 1.00 lump sum 102,428.19 8% 8,194.26 5,531.12 13,725.38 116,153.57 116,153.57
Provision of Furnitures/Fixtures, Equipment & Applicances for AS SUBMITTED 1.00 lump sum 41,939.11 8% 3,355.13 2,264.71 5,619.84 47,558.95 47,558.95
A.1.1 (11)
the Field Office for the Engineer AS EVALUATED 1.00 lump sum 41,939.11 8% 3,355.13 2,264.71 5,619.84 47,558.95 47,558.95
Operation and Maintenance of 4x2 Pick Up Type Service AS SUBMITTED 4.97 month 123,405.59 0% - 6,170.28 6,170.28 129,575.87 26,071.60
A.1.2(6)
Vehicle for the Engineer AS EVALUATED 4.97 month 123,405.59 0% - 6,170.28 6,170.28 129,575.87 26,071.60
AS SUBMITTED 149.00 each 2,235.00 8% 178.80 120.69 299.49 2,534.49 17.01
A.1.4(1) Provision of Progress Photographs
AS EVALUATED 149.00 each 2,235.00 8% 178.80 120.69 299.49 2,534.49 17.01
AS SUBMITTED 270,007.89 11,728.19 14,086.80 25,814.99 295,822.88
TOTAL OF PART A
AS EVALUATED 270,007.89 11,728.19 14,086.80 25,814.99 295,822.88
PART B OTHER GENERAL REQUIREMENTS
AS SUBMITTED 2.00 each 11,650.32 18% 2,097.06 687.37 2,784.43 14,434.75 7,217.38
B.5 Project Billboard / Signboard
AS EVALUATED 2.00 each 11,650.32 18% 2,097.06 687.37 2,784.43 14,434.75 7,217.38
AS SUBMITTED 1.00 lump sum 255,443.84 8% 20,435.51 13,793.97 34,229.48 289,673.32 289,673.32
B.7(2) Occupational Safety and Health Program
AS EVALUATED 1.00 lump sum 255,443.84 8% 20,435.51 13,793.97 34,229.48 289,673.32 289,673.32
AS SUBMITTED 1.00 lump sum 585,247.31 8% 46,819.78 31,603.35 78,423.13 663,670.44 663,670.44
B.8(2) Traffic Management
AS EVALUATED 1.00 lump sum 585,247.31 8% 46,819.78 31,603.35 78,423.13 663,670.44 663,670.44
AS SUBMITTED 1.00 lump sum 120,000.00 0% - 6,000.00 6,000.00 126,000.00 126,000.00
B.9 Mobilization / Demobilization
AS EVALUATED 1.00 lump sum 120,000.00 0% - 6,000.00 6,000.00 126,000.00 126,000.00
AS SUBMITTED 972,341.47 69,352.35 52,084.69 121,437.04 1,093,778.51
TOTAL OF PART B
AS EVALUATED 972,341.47 69,352.35 52,084.69 121,437.04 1,093,778.51
PART C EARTHWORKS
AS SUBMITTED 5,346.60 sq.m. 2,078,330.35 18% 374,099.46 122,621.49 496,720.95 2,575,051.30 481.62
101(3)c1 Removal of Actual Structures/Obstruction (0.05m thick, ACP)
AS EVALUATED 5,346.60 sq.m. 2,078,330.35 18% 374,099.46 122,621.49 496,720.95 2,575,051.30 481.62
Removal of Actual Structures/Obstruction (0.28m thick, PCCP AS SUBMITTED 60.30 sq.m. 10,972.19 18% 1,974.99 647.36 2,622.35 13,594.54 225.45
101(3)b5
(Unreinforced)) AS EVALUATED 60.30 sq.m. 10,972.19 18% 1,974.99 647.36 2,622.35 13,594.54 225.45
AS SUBMITTED 306.83 cu.m. 37,540.66 18% 6,757.32 2,214.90 8,972.22 46,512.88 151.59
102(2) Surplus Common Excavation
AS EVALUATED 306.83 cu.m. 37,540.66 18% 6,757.32 2,214.90 8,972.22 46,512.88 151.59
AS SUBMITTED 357.99 sq.m. 5,785.12 18% 1,041.32 341.32 1,382.64 7,167.76 20.02
105(1)a Subgrade Preparation (Common Material)
AS EVALUATED 357.99 sq.m. 5,785.12 18% 1,041.32 341.32 1,382.64 7,167.76 20.02
AS SUBMITTED 2,132,628.32 383,873.09 125,825.07 509,698.16 2,642,326.48
TOTAL OF PART C
AS EVALUATED 2,132,628.32 383,873.09 125,825.07 509,698.16 2,642,326.48
PART D SUBBASE AND BASE COURSE
AS SUBMITTED 65.70 cu.m. 59,815.25 18% 10,766.75 3,529.10 14,295.85 74,111.10 1,128.02
200(1) Aggregate Subbase Course
AS EVALUATED 65.70 cu.m. 59,815.25 18% 10,766.75 3,529.10 14,295.85 74,111.10 1,128.02
AS SUBMITTED 59,815.25 10,766.75 3,529.10 14,295.85 74,111.10
TOTAL OF PART D
AS EVALUATED 59,815.25 10,766.75 3,529.10 14,295.85 74,111.10
Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

RAINIER D. PALAGANAS FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN


Engineer II Chief, Planning & Design Section Chief, Construction Section
Maintenance Section
Date: December 01, 2020

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


QUEZON 2ND DISTRICT ENGINEERING OFFICE
FORM ABC-2015-02A-00
CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance - Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 149 C.D.
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST
PART E SURFACE COURSE
AS SUBMITTED 41,372.30 sq.m. 2,562,600.26 18% 461,268.05 151,193.42 612,461.47 3,175,061.73 76.74
302(2) Bituminous Tack Coat (Emulsified Asphalt)
AS EVALUATED 41,372.30 sq.m. 2,562,600.26 18% 461,268.05 151,193.42 612,461.47 3,175,061.73 76.74
Bituminous Concrete Surface Wearing Course, Hot-Laid AS SUBMITTED 20,686.15 sq.m. 26,839,659.04 18% 4,831,138.63 1,583,539.88 6,414,678.51 33,254,337.55 1,607.56
310(1)b
(40mm) AS EVALUATED 20,686.15 sq.m. 26,839,659.04 18% 4,831,138.63 1,583,539.88 6,414,678.51 33,254,337.55 1,607.56
AS SUBMITTED 20,686.15 sq.m. 26,839,659.04 18% 4,831,138.63 1,583,539.88 6,414,678.51 33,254,337.55 1,607.57
310(2)b Bituminous Concrete Surface Binder Course, Hot-Laid (40mm)
AS EVALUATED 20,686.15 sq.m. 26,839,659.04 18% 4,831,138.63 1,583,539.88 6,414,678.51 33,254,337.55 1,607.57
Portland Cement Concrete Pavement (Unreinforced) (0.30 m AS SUBMITTED 357.99 sq.m. 707,262.94 18% 127,307.33 41,728.51 169,035.84 876,298.78 2,447.83
311(1)f1
thick, 14 days) AS EVALUATED 357.99 sq.m. 707,262.94 18% 127,307.33 41,728.51 169,035.84 876,298.78 2,447.83
AS SUBMITTED 56,949,181.28 10,250,852.64 3,360,001.69 13,610,854.33 70,560,035.61
TOTAL OF PART E
AS EVALUATED 56,949,181.28 10,250,852.64 3,360,001.69 13,610,854.33 70,560,035.61
PART F BRIDGE CONSTRUCTION
AS SUBMITTED
AS EVALUATED
AS SUBMITTED
TOTAL OF PART F
AS EVALUATED
PART G DRAINAGE AND SLOPE PROTECTION STRUCTURES
AS SUBMITTED
AS EVALUATED
AS SUBMITTED
TOTAL OF PART G
AS EVALUATED
PART H MISCELLANEOUS STRUCTURES
AS SUBMITTED 63.00 l.m. 52,179.12 18% 9,392.24 3,078.57 12,470.81 64,649.93 1,026.19
600(4) Curb and Gutter (Cast in Place)
AS EVALUATED 63.00 l.m. 52,179.12 18% 9,392.24 3,078.57 12,470.81 64,649.93 1,026.19
AS SUBMITTED 75.60 sq.m. 54,157.57 18% 9,748.36 3,195.30 12,943.66 67,101.23 887.58
601(1) Sidewalk (100mm thk.)
AS EVALUATED 75.60 sq.m. 54,157.57 18% 9,748.36 3,195.30 12,943.66 67,101.23 887.58
Regulatory Signs (600mm, R6-8B, Miscellaneous Signs AS SUBMITTED 6.00 each 43,823.64 18% 7,888.26 2,585.60 10,473.86 54,297.50 9,049.58
605(2)ai2
Pedestrian Crossing) AS EVALUATED 6.00 each 43,823.64 18% 7,888.26 2,585.60 10,473.86 54,297.50 9,049.58
Internally Illuminated (Solar) Pavement Levelled Marker/Stud AS SUBMITTED 404.00 each 3,774,325.56 18% 679,378.60 222,685.21 902,063.81 4,676,389.37 11,575.22
607(3)b
Flush Type AS EVALUATED 404.00 each 3,774,325.56 18% 679,378.60 222,685.21 902,063.81 4,676,389.37 11,575.22
AS SUBMITTED 855.76 sq.m. 616,215.66 18% 110,918.82 36,356.72 147,275.54 763,491.20 892.18
612(1) Reflectorized Thermoplastic Pavement Markings White
AS EVALUATED 855.76 sq.m. 616,215.66 18% 110,918.82 36,356.72 147,275.54 763,491.20 892.18
AS SUBMITTED 687.75 sq.m. 495,235.02 18% 89,142.30 29,218.87 118,361.17 613,596.19 892.18
618(1) Reflectorized Thermoplastic Rumble Strips
AS EVALUATED 687.75 sq.m. 495,235.02 18% 89,142.30 29,218.87 118,361.17 613,596.19 892.18
AS SUBMITTED 5,035,936.57 906,468.58 297,120.27 1,203,588.85 6,239,525.42
TOTAL OF PART H
AS EVALUATED 5,035,936.57 906,468.58 297,120.27 1,203,588.85 6,239,525.42
Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

RAINIER D. PALAGANAS FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN


Engineer II Chief, Planning & Design Section Chief, Construction Section
Maintenance Section
Date: December 01, 2020

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


QUEZON 2ND DISTRICT ENGINEERING OFFICE
FORM ABC-2015-02A-00
CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance - Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

APPROVED BUDGET FOR THE CONTRACT


Contract Duration : 149 C.D.
ESTIMATED DIRECT TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT VAT TOTAL COST UNIT COST
COST % VALUE COST
PART I PROVISIONAL SUM
AS SUBMITTED
AS EVALUATED
AS SUBMITTED
TOTAL OF PART I
AS EVALUATED
PART J DAYWORK
AS SUBMITTED
AS EVALUATED
AS SUBMITTED
TOTAL OF PART J
AS EVALUATED
AS SUBMITTED 65,419,910.78 11,633,041.60 3,852,647.62 15,485,689.22 80,905,600.00
GRAND TOTAL
AS EVALUATED 65,419,910.78 11,633,041.60 3,852,647.62 15,485,689.22 80,905,600.00

Preparation and Submission: Evaluation:

Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:

RAINIER D. PALAGANAS FAUSTINO MARK ANTHONY S. DE LA CRUZ JUAN J. PANGANIBAN


Engineer II Chief, Planning & Design Section Chief, Construction Section
Maintenance Section
Date: December 01, 2020

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive
Maintenance - Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827

Lucena City, Quezon

BACK- UP COMPUTATION

PART A FACILITIES FOR THE ENGINEER


A.1.1 (3) Construction of Field Office for the Engineer
Qty= 1.00 l.s.

A.1.1 (11) Provision of Furnitures/Fixtures, Equipment & Applicances for the Field Office for the Engineer
Qty= 1.00 l.s.

A.1.2(6) Operation and Maintenance of 4x2 Pick Up Type Service Vehicle for the Engineer
Qty= 4.97 mo.

A.1.4(1) Provision of Progress Photographs


Qty= 149.00 each.

PART B OTHER GENERAL REQUIREMENTS


B.5 Project Billboard / Signboard
Qty= 2.00 ea.

B.7(2) Occupational Safety and Health Program


Qty= 1.00 l.s.

B.8(2) Traffic Management


Qty= 1.00 l.s.

B.9 Mobilization / Demobilization


Qty= 1.00 l.s.

PART C EARTHWORKS
101(3)c1 Removal of Actual Structures/Obstruction (0.05m thick, ACP)

STATION Length Width Area

K0129+1006.00 - K0130+568.00 595.00 l.m. 6.70 m. 3,986.50 sq.m.

K0130+624.00 - K0130+827.00 203.00 l.m. 6.70 m. 1,360.10 sq.m.

TOTAL: 798.00 l.m. 5,346.60 sq.m.

Qty. = 5,346.60 sq.m.

101(3)b5 Removal of Actual Structures/Obstruction (0.28m thick, PCCP (Unreinforced))

RE-BLOCKING
STATION Length Width Quantity Area
K0130+142.00 - K0130+151.00 RS
4.50 l.m. 3.35 m. 4.00 60.30 sq.m.
(Infront of ACES Campus Building)
TOTAL 60.30 sq.m.

Qty. = 60.30 sq.m.

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

102(2) Surplus Common Excavation


CONCRETING
STATION Area (L x W) Thickness Quantity Volume
K0130+073.50 - K0130+105.00 LS
13.73 sq.m. 1.00 m. 7.00 96.11 cu.m.
(Outermost lane)
K0130+633.50 - K0130+665.00 RS
15.08 sq.m. 1.00 m. 7.00 105.56 cu.m.
(3rd lane)
K0130+633.50 - K0130+665.00 RS
13.73 sq.m. 1.00 m. 7.00 96.11 cu.m.
(Outermost lane)
SUB TOTAL: 297.78 cu.m.

RE-BLOCKING
STATION Area (L x W) Thickness Quantity Volume
K0130+142.00 - K0130+151.00 RS
15.08 sq.m. 0.15 m. 4.00 9.05 cu.m.
(Infront of ACES Campus Building)
SUB TOTAL: 9.05 cu.m.

Qty. = 306.83 cu.m.

105(1)a Subgrade Preparation (Common Material)


CONCRETING
STATION Length Width Quantity Area
K0130+073.50 - K0130+105.00 LS
4.50 l.m. 3.05 m. 7.00 96.08 sq.m.
(Outermost lane)
K0130+633.50 - K0130+665.00 RS
4.50 l.m. 3.35 m. 7.00 105.53 sq.m.
(3rd lane)
K0130+633.50 - K0130+665.00 RS
4.50 l.m. 3.05 m. 7.00 96.08 sq.m.
(Outermost lane)
SUB TOTAL: 297.69 sq.m.

RE-BLOCKING
STATION Length Width Quantity Area
K0130+142.00 - K0130+151.00 RS
4.50 l.m. 3.35 m. 4.00 60.30 sq.m.
(Infront of ACES Campus Building)
SUB TOTAL: 60.30 sq.m.

Qty. = 357.99 sq.m.

PART D SUBBASE AND BASE COURSE


200(1) Aggregate Subbase Course
CONCRETING
STATION Area (L x W) Thickness Quantity Volume
K0130+073.50 - K0130+105.00 LS
13.73 sq.m. 0.15 m. 7.00 14.42 cu.m.
(Outermost lane)
K0130+633.50 - K0130+665.00 RS
15.08 sq.m. 0.15 m. 7.00 15.83 cu.m.
(3rd lane)
K0130+633.50 - K0130+665.00 RS
13.73 sq.m. 0.15 m. 7.00 14.42 cu.m.
(Outermost lane)
SUB TOTAL: 44.67 cu.m.

RE-BLOCKING
STATION Area (L x W) Thickness Quantity Volume
K0130+142.00 - K0130+151.00 RS
15.08 sq.m. 0.15 m. 4.00 9.05 cu.m.
(Infront of ACES Campus Building)
SUB TOTAL: 9.05 cu.m.

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONCRETE CURB & GUTTER AND SIDEWALK


STATION Length Width Thickness Volume
K0130+073.50 - K0130+105.00 LS 31.50 m. 1.90 m. 0.10 m. 5.99 cu.m.
K0130+633.50 - K0130+665.00 RS 31.50 m. 1.90 m. 0.10 m. 5.99 cu.m.
SUB TOTAL: 11.98 cu.m.

Qty. = 65.70 cu.m.

PART E SURFACE COURSES


302(2) Bituminous Tack Coat (Emulsified Asphalt)
Qty. = 41,372.30 sq.m.

Area
Bituminous Concrete Surface Wearing Course,
20,686.15 sq.m.
Hot-Laid (40mm)
Bituminous Concrete Surface Binder Course,
20,686.15 sq.m.
Hot-Laid (40mm)
Area = 41,372.30 sq.m.

310(1)b Bituminous Concrete Surface Wearing Course, Hot-Laid (40mm)

Qty. = 20,686.15 sq.m. (SEE QUANTITY SHEET)

310(2)b Bituminous Concrete Surface Binder Course, Hot-Laid (40mm)

Qty. = 20,686.15 sq.m. (SEE QUANTITY SHEET)

311(1)f1 Portland Cement Concrete Pavement (Unreinforced) (0.30 m thick, 14 days)


CONCRETING
STATION Length Width Quantity Area
K0130+073.50 - K0130+105.00 LS
4.50 l.m. 3.05 m. 7.00 96.08 sq.m.
(Outermost lane)
K0130+633.50 - K0130+665.00 RS
4.50 l.m. 3.35 m. 7.00 105.53 sq.m.
(3rd lane)
K0130+633.50 - K0130+665.00 RS
4.50 l.m. 3.05 m. 7.00 96.08 sq.m.
(Outermost lane)
SUB TOTAL: 297.69 sq.m.

RE-BLOCKING
STATION Length Width Quantity Area
K0130+142.00 - K0130+151.00 RS
4.50 l.m. 3.35 m. 4.00 60.30 sq.m.
(Infront of ACES Campus Building)

SUB TOTAL: 60.30 sq.m.

Qty. = 357.99 sq.m.

PART H MISCELLANEOUS STRUCTURES


600(4) Curb and Gutter (Cast in Place)
STATION Length
K0130+073.50 - K0130+105.00 LS 31.50 l.m.
K0130+633.50 - K0130+665.00 RS 31.50 l.m.
TOTAL: 63.00 l.m.

Qty. = 63.00 l.m.

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

601(1) Sidewalk (100mm thk.)


STATION Length Width Area
K0130+073.50 - K0130+105.00 LS 31.50 l.m. 1.20 m. 37.80 sq.m.
K0130+633.50 - K0130+665.00 RS 31.50 l.m. 1.20 m. 37.80 sq.m.
TOTAL: 75.60 sq.m.

Qty. = 75.60 sq.m.

605(2)ai2 Regulatory Signs (600mm, R6-8B, Miscellaneous Signs Pedestrian Crossing)


STATION QUANTITY
K0130+156.00 LS 1.00 ea.
K0130+156.00 RS 1.00 ea.
K0130+359.00 LS 1.00 ea.
K0130+359.00 RS 1.00 ea.
K0130+699.00 LS 1.00 ea.
K0130+699.00 RS 1.00 ea.
TOTAL 6.00 ea.

Qty.= 6.00 ea. (See Plan for Schedule)

607(3)b Internally Illuminated (Solar) Pavement Levelled Marker/Stud Flush Type


AT EDGE LINE (NEAR BARRIER)
Quantity
STATION Length
(Both Edge Line)
K0129+1006.00 - K0129+1033.00(BK)
27.00 l.m. 12.00
K0130+000.00 (AH)
K0129+1033.00(BK) - K0130+210.00
210.00 l.m. 72.00
K0130+000.00 (AH)
K0130+624.00 - K0130+770.00 146.00 l.m. 50.00
TOTAL 383.00 l.m. 134.00

AT CENTER LINE
STATION Length Quantity
K0130+210.00 - K0130+568.00 358.00 l.m. 61.00
K0130+770.00 - K0130+827.00 57.00 l.m. 11.00
TOTAL 415.00 l.m. 72.00

AT BIKE LANE
Quantity
STATION Length (Both Sides)
K0129+1006.00 - K0129+1033.00(BK)
27.00 l.m. 12.00
K0130+000.00 (AH)
K0129+1033.00(BK) - K0130+553.00
553.00 l.m. 186.00
K0130+000.00 (AH)
TOTAL 580.00 l.m. 198.00

Qty.= 404.00 ea.

612(1) Reflectorized Thermoplastic Pavement Markings White

STATION Length
K0129+1006.00 - K0129+1033.00(BK)
27.00 l.m.
K0130+000.00 (AH)
K0129+1033.00(BK) - K0130+210.00
210.00 l.m.
K0130+000.00 (AH)
K0130+624.00 - K0130+770.00 146.00 l.m.
TOTAL 383.00 l.m.

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

EDGE LINE (NEAR BARRIER)


Length = 383.00 l.m.
Length x 2= 766.00 l.m.
Width = 0.10 l.m.
Area = 76.60 sq.m.

STATION Length
K0130+210.00 - K0130+568.00 358.00 l.m.
K0130+770.00 - K0130+827.00 57.00 l.m.
TOTAL 415.00 l.m.

CENTER LINE
Length = 415.00 l.m.
Width = 0.20 l.m.
Area = 83.00 sq.m.

STATION Length
K0129+1006.00 - K0129+1033.00(BK)
27.00 l.m.
K0130+000.00 (AH)
K0129+1033.00(BK) - K0130+568.00
568.00 l.m.
K0130+000.00 (AH)
K0130+624.00 - K0130+827.00 203.00 l.m.
TOTAL 798.00 l.m.

EDGE LINE
Length = 798.00 l.m.
Length x 2= 1,596.00 l.m.
Width = 0.10 l.m.
Area = 159.60 sq.m.
BROKEN LINE
Length = 798.00 l.m.
Length (broken) x 4= 1,064.00 l.m.
Width = 0.15 l.m.
Area = 159.60 sq.m.

BICYCLE LANE
Length = 798.00 l.m.
Length x 2= 1,596.00 l.m.
Width = 0.10 l.m.
Area = 159.60 sq.m.

BICYCLE LANE SYMBOL, BLUE (for every 50m)


Description Area Quantity Total Area
Area of Symbol 0.41 sq.m. 32 13.12 sq.m.
Area of Directioanal Arrow 0.45 sq.m. 32 14.40 sq.m.
TOTAL 27.52 sq.m.

Area = 27.52 sq.m.

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

PEDESTRIAN LANE
CARRIAGEWAY
STATION NO. OF STRIPS
WIDTH
K0130+156.00 26.20 m. 44.00 pcs.
K0130+359.00 26.20 m. 44.00 pcs.
K0130+699.00 26.20 m. 44.00 pcs.
TOTAL 78.60 m. 132.00 pcs.

Total Width Length = 78.60 m.


Total No. of Strips = 132.00 pcs.
Length = 4.00 l.m.
Width = 0.30 m.
Area = 158.40 sq.m.

STOP LINE @ PEDESTRIAN LANE


Total Width Length = 78.60 m.
Width = 0.40 m.
Area = 31.44 sq.m.

Total Qty= 855.76 sq.m.

618(1) Reflectorized Thermoplastic Rumble Strips

RUMBLE STRIPS
STATION NO. OF SECTION
K0130+023.00 LS 1.00
K0130+197.00 RS 1.00
K0130+247.00 LS 1.00
K0130+247.00 RS 1.00
K0130+432.00 LS 1.00
K0130+482.00 LS 1.00
K0130+518.00 RS 1.00

Total No. of Section = 7.00


Length = 13.10 l.m.
Total No. of Strips = 30.00 pcs.
Width 1 = 0.15 m.
Area 1 = 412.65 sq.m.

Width 2 = 0.10 m.
Area 2 = 275.10 sq.m.

Total Qty = 687.75 sq.m.

Prepared by:

RAINIER D. PALAGANAS
Engineer II

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

BACK UP COMPUTATION

Project : CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239,
Preventive Maintenance - Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827

Location : Lucena City, Quezon


Item No. : 310(1)b & 310(2)b
Description Bituminous Concrete Surface Wearing Course, Hot-Laid (40mm) & Bituminous Concrete Surface Binder Course, Hot-Laid (40mm)
:

WIDTH AREA (sq.m)


STATION DIST.(m)
LEFT RIGHT LEFT RIGHT
SECTION I
K0129+1006.00 13.1500 3.4600
8.00 105.200 27.680
K0129+1014.00 A 13.1500 3.4600

K0129+1014.00 B 13.1500 6.7800


14.00 184.100 94.920
K0129+1028.00 A 13.1500 6.7800

K0129+1028.00 B 13.1500 13.0000


5.00 65.750 65.000
K0129+1033.00 (BK) 13.1500 13.0000
K0130+000.00 (AH)
20.00 263.300 260.300
K0130+020.00 13.1800 13.0300
20.00 263.900 260.800
K0130+040.00 13.2100 13.0500
20.00 264.500 261.300
K0130+060.00 13.2400 13.0800
20.00 264.600 261.800
K0130+080.00 13.2200 13.1000
20.00 262.200 262.300
K0130+100.00 13.0000 13.1300
20.00 259.800 262.800
K0130+120.00 12.9800 13.1500
20.00 260.000 263.300
K0130+140.00 13.0200 13.1800
20.00 260.700 263.700
K0130+160.00 13.0500 13.1900
20.00 261.200 263.600
K0130+180.00 13.0700 13.1700
20.00 261.500 263.300
K0130+200.00 13.0800 13.1600
20.00 261.800 263.000
K0130+220.00 13.1000 13.1400
20.00 262.200 262.600
K0130+240.00 13.1200 13.1200
20.00 262.400 262.300
K0130+260.00 13.1200 13.1100
20.00 262.000 262.500
K0130+280.00 13.0800 13.1400
20.00 261.200 263.000

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

K0130+300.00 13.0400 13.1600


20.00 260.800 263.000
K0130+320.00 13.0400 13.1400
20.00 261.000 262.500
K0130+340.00 13.0600 13.1100
20.00 261.500 261.800
K0130+360.00 13.0900 13.0700
20.00 262.100 261.100
K0130+380.00 13.1200 13.0400
20.00 262.300 260.900
K0130+400.00 13.1100 13.0500
20.00 261.900 261.500
K0130+420.00 13.0800 13.1000
20.00 261.300 262.500
K0130+440.00 13.0500 13.1500
20.00 260.700 263.500
K0130+460.00 13.0200 13.2000
20.00 261.700 263.800
K0130+480.00 13.1500 13.1800
20.00 264.500 263.300
K0130+500.00 13.3000 13.1500
20.00 267.500 262.700
K0130+520.00 13.4500 13.1200
18.76 248.945 239.753
K0129+538.76 A 13.0900 12.4400

K0129+538.76 B 13.0900 6.9000


1.24 16.232 8.556
K0130+540.00 13.0900 6.9000
4.34 56.811 28.991
K0130+544.34 13.0900 6.4600
15.66 209.922 79.788
K0130+560.00 13.7200 3.7300
8.00 109.760 29.840
K0130+568.00 13.7200 3.7300

SECTION II
K0130+624.00 14.1800 4.8300
9.50 134.710 53.723
K0129+633.50 A 14.1800 6.4800

K0129+633.50 B 13.8900 13.0900


6.50 90.285 85.085
K0130+640.00 13.8900 13.0900
20.00 275.000 261.800
K0130+660.00 13.6100 13.0900
20.00 269.400 261.800
K0130+680.00 13.3300 13.0900
20.00 265.300 262.000
K0130+700.00 13.2000 13.1100
20.00 263.500 262.200
K0130+720.00 13.1500 13.1100
20.00 262.400 262.200
K0130+740.00 13.0900 13.1100

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

20.00 262.000 261.800


K0130+760.00 13.1100 13.0700
20.00 262.800 260.800
K0130+780.00 13.1700 13.0100
20.00 264.100 259.600
K0130+800.00 13.2400 12.9500
20.00 265.200 258.600
K0130+820.00 13.2800 12.9100
7.00 92.855 90.440
K0130+827.00 13.2500 12.9300

TOTAL : 798.00 10,520.87 9,977.78

TOTAL AREA
LEFT 10,520.87 sq.m.
RIGHT 9,977.78 sq.m.

Transitions at MSR Diversion Road (Left Side)


STATION LENGTH (m) WIDTH (m) AREA (sq.m.) x 0.5

SUB-TOTAL 0.00 0.00 0.00

Transitions at MSR Diversion Road (Right Side)


STATION LENGTH (m) WIDTH (m) AREA (sq.m.) x 0.5
K0130+297.00 - K0130+326.00 5.00 29.00 72.50
K0130+333.00 - K0130+343.00 5.00 10.00 25.00
K0130+356.00 - K0130+382.00 5.00 26.00 65.00
K0130+812.00 - K0130+822.00 5.00 10.00 25.00
SUB-TOTAL 20.00 75.00 187.50

TOTAL AREA (TRANSITIONS)= 187.50 sq.m.

310(1)b Bituminous Concrete Surface Wearing Course, Hot-Laid (40mm)

Area (40 mm thk. ) = 10520.87 sq.m. + 9977.78 sq.m. + 187.5 sq.m.

= 20,686.15 sq.m.

310(2)b Bituminous Concrete Surface Binder Course, Hot-Laid (40mm) `

Area (40 mm thk.) = 10520.87 sq.m. + 9977.78 sq.m. + 187.5 sq.m.

= 20,686.15 sq.m.

Prepared by:

RAINIER D. PALAGANAS
Engineer II

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

COMPUTATION OF ESTIMATED PROJECT DURATION


(BASED ON DEPARTMENT ORDER 44, SERIES OF 2012)

PROJECT : CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle
User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance - Primary Roads, MSR
Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827

LOCATION : Lucena City, Quezon

AMOUNT: P 83,840,000.00

PROJECT CATEGORY : Roads

106 Calendar Days as per D.O. 44 series of 2012 --- P 100


X Calendar Days as per D.O. 44 series of 2012 --- P 83.8
81 Calendar Days as per D.O. 44 series of 2012 --- P 50
By interpolation:
106 C.D. - 81 C.D. X CD - 81 CD
=
100 M - 50 M 83.84 M - 50M
X = 97.92 calendar days

WORKING DAYS : 98.00 calendar days


UNWORKABLE DAYS : 51.00 calendar days

PROJECT DURATION : 149.00 calendar days

Prepared by:

RAINIER D. PALAGANAS
Engineer II

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

Project : CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239,
Preventive Maintenance - Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827

Location : Lucena City, Quezon

COMPUTATION OF NET WORKING DAYS

DESCRIPTION FEB MAR APR MAY JUN JUL AUG SEP TOTAL
CALENDAR DAY 28 31 30 31 29 149
SUNDAYS 4 4 4 5 4 21
NATIONAL HOLIDAYS 0 0 2 1 1 4
RAINY DAYS 5 2 6 5 8 26
TOTAL NON-WORKING DAYS 9 6 12 11 13 51
NET WORKING DAYS 19 25 18 20 16 98

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance - Primary Roads, MSR Diversion Rd -
K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : A.1.1 (3) Construction of Field Office for the Engineer
Unit of Measurement : lump sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of
Designation No. of Hour/s Hourly Rate Amount (Php)
Person/s
A.1 Labor
a. Foreman 1 40 102.73 4,109.20
b. Skilled Laborer 3 40 74.22 8,906.40
c. Unskilled Laborer 5 40 57.17 11,434.00

Sub - Total for A.1 - As Submitted 24,449.60


A.2 Labor
a. Foreman 1 40 102.73 4,109.20
b. Skilled Laborer 3 40 74.22 8,906.40
c. Unskilled Laborer 5 40 57.17 11,434.00

Sub - Total for A.2 - As Evaluated 24,449.60


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (Php)
B.1 Equipment

Sub - Total for B.1 - As Submitted 0.00


B.2 Equipment

Sub - Total for B.2 - As Evaluated 0.00


C.1 Total (A.1 + B.1) - As Submitted 24,449.60
C.2 Total (A.2 + B.2) - As Evaluated 24,449.60
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 24,449.60
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 24,449.60
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

a. 1/4 x 4 x 8 Plywood Marine pc. 11.00 500.00 5,500.00


b. Good Lumber bd.ft. 459.37 60.00 27,562.20
c. Corrugated Roofing, Gauge 26 sq.m. 36.00 255.00 9,180.00
d. 2" x 4" Door Hinges pc. 4.00 70.00 280.00
e. 2" x 3" Window Hinges pc. 8.00 41.00 328.00
f. Porland Cement bag 43.00 250.00 10,750.00
g. Gravel, 3/4 cu.m. 4.00 1,307.36 5,229.44
h. Sand cu.m. 2.00 1,307.36 2,614.72
i. Reinforcing Steel Bar Grade 40 kg. 153.14 37.50 5,742.75
j. CHB Ordinary 4" pc. 163.00 15.00 2,445.00
k. Fascia Board (1/2 x 12" Marine Plywood) l.m. 23.60 93.75 2,212.50
l. Ridge Roll l.m. 7.20 100.00 720.00
m. 20 watts Flourescent LF set 3.00 255.00 765.00
n. Duplex Convenience Outlet set 2.00 130.00 260.00
o. One Gang Switch set 1.00 95.00 95.00
p. Panel Board & Cabinet set 1.00 1,320.00 1,320.00
q. #16 G.I Tie Wires kg. 3.00 80.00 240.00
r. Miscellaneous (Forms, CWN, Bolts, Electrical Wires, etc.) lot 1.00 2,733.98 2,733.98

Sub - Total for F.1 - As Submitted 77,978.59


F.2 Materials

a. 1/4 x 4 x 8 Plywood Marine pc. 11.00 500.00 5,500.00


b. Good Lumber bd.ft. 459.37 60.00 27,562.20
c. Corrugated Roofing, Gauge 26 sq.m. 36.00 255.00 9,180.00
d. 2" x 4" Door Hinges pc. 4.00 70.00 280.00
e. 2" x 3" Window Hinges pc. 8.00 41.00 328.00
f. Porland Cement bag 43.00 250.00 10,750.00
g. Gravel, 3/4 cu.m. 4.00 1,307.36 5,229.44
h. Sand cu.m. 2.00 1,307.36 2,614.72
i. Reinforcing Steel Bar Grade 40 kg. 153.14 37.50 5,742.75
j. CHB Ordinary 4" pc. 163.00 15.00 2,445.00
k. Fascia Board (1/2 x 12" Marine Plywood) l.m. 23.60 93.75 2,212.50
l. Ridge Roll l.m. 7.20 100.00 720.00
m. 20 watts Flourescent LF set 3.00 255.00 765.00
n. Duplex Convenience Outlet set 2.00 130.00 260.00
o. One Gang Switch set 1.00 95.00 95.00
p. Panel Board & Cabinet set 1.00 1,320.00 1,320.00
q. #16 G.I Tie Wires kg. 3.00 80.00 240.00
r. Miscellaneous (Forms, CWN, Bolts, Electrical Wires, etc.) lot 1.00 2,733.98 2,733.98

Sub - Total for F.2 - As Evaluated 77,978.59


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 102,428.19
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 102,428.19
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 8,194.26
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 8,194.26
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 5,531.12
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 5,531.12
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 116,153.57
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 116,153.57

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

DETAILED CALCULATIONS OF FIELD OFFICE


Structural Concrete:
Volume:
L W H Q
Footing 0.6 0.6 0.2 6 0.432 Cement 43 bags
Column 0.2 0.2 1.6 6 0.384 Sand 2 cu.m.
WF 0.35 10.4 0.15 1 0.546 Gravel 4 cu.m.
Slab 6 3 0.1 1 1.8
CHB Mortar Cement 10.00 Sand 0.57
CHB Plaster Cement 4.00 Sand 0.21
3.162
Reinforcing Steel Bar:
w/m
Footing x 10 mmØ 0.6165 0.6 4 6 8.88
Footing y 10 mmØ 0.6165 0.6 4 6 8.88
Column 12 mmØ 0.8878 2 4 6 42.62
Stirrups 10 mmØ 0.6165 0.58 9 6 19.31
WF 10 mmØ 0.6165 10.4 1 1 6.41
Slab 10 mmØ 0.6165 10 3 1 18.50
10 mmØ 0.6165 5 6 1 18.50
Hor. Vert.
For CHB 10 mmØ 0.6165 27.95 20.8 30.06
153.14 kgs.
100mm Thk. Concrete Hollow Blocks
Ht. L
Area: 1.25 10.4 13 sq.m.
163 pcs.

Corrugated Roofing Sheet #26 Ridge Roll:


Wdth L Length: 7.2 m.
Area: 5 7.2 36 sq.m.

Fascia Board (1/2 x 12" HardiFlex)


Length: 23.6 m.

1/4" x 4 x 8 Marine Plywood


Door Openings:
Area: 0.9 2.1 1 1.89 sq.m. Door = 1.1 x 0.9 = 0.99
Window = W1 + W2 = 3.6
Window 4.59 sq.m.
Area: 1.2 1.2 2 2.88 sq.m. Hinge
1.2 0.6 1 0.72 sq.m. 2 x 4 Door Hinge 4 pcs.
2 x 3 Window Hinge 8 pcs.
Wall (Double) Ht L
Area: 1.8 12 21.6 sq.m.
0.3 6 1.8 sq.m.
23.4
Less openings: 18.81 sq.m. Size: 1.2 2.4
Total Area: 24.3 sq.m. Wastage (30%) 31.59
Quantity: 11.00 pcs.
Good Lumber
L cu.in. bd.ft.
2x2 2 2 3996.06 144 111.00
2x3 2 3 2267.72 144 94.49
2x4 2 4 1381.89 144 76.77
2x5 2 5 1161.42 144 80.65
3x5 3 5 472.44 144 49.21
4x4 4 4 425.20 144 47.24
459.37 bd.ft.

1 x 20 watts FLF
Quantity: 3 set

Duplex Convenience Outlet


Quantity: 2 set

One Gang Switch


Quantity: 1 set

Panel Board & Cabinet


Quantity: 1 set

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : A.1.1 (11) Provision of Furnitures/Fixtures, Equipment & Applicances for the Field
Office for the Engineer
Unit of Measurement : lump sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor

Sub - Total for A.1 - As Submitted 0.00


A.2 Labor

Sub - Total for A.2 - As Evaluated 0.00


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment

Sub - Total for B.1 - As Submitted 0.00


B.2 Equipment

Sub - Total for B.2 - As Evaluated 0.00


C.1 Total (A.1 + B.1) - As Submitted 0.00
C.2 Total (A.2 + B.2) - As Evaluated 0.00
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 0.00
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 0.00
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

a. Office Table Tanguile Varnish pc. 2 5,000.00 10,000.00


b. Monoblock Chair pc. 6 450.00 2,700.00
c. Bulletin/Cork Board pc. 2 320.00 640.00
d. Record Book pc. 4 50.00 200.00
e. Water Dispenser pc. 1 8,300.00 8,300.00
f. Miscellaneous Office Supplies l.s 1 20,099.11 20,099.11

Sub - Total for F.1 - As Submitted 41,939.11


F.2 Materials

a. Office Table Tanguile Varnish pc. 2 5,000.00 10,000.00


b. Monoblock Chair pc. 6 450.00 2,700.00
c. Bulletin/Cork Board pc. 2 320.00 640.00
d. Record Book pc. 4 50.00 200.00
e. Water Dispenser pc. 1 8,300.00 8,300.00
f. Miscellaneous Office Supplies l.s 1 20,099.11 20,099.11

Sub - Total for F.2 - As Evaluated 41,939.11


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 41,939.11
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 41,939.11
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 3,355.13
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 3,355.13
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 2,264.71
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 2,264.71
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 47,558.95
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 47,558.95

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : A.1.2(6) Operation and Maintenance of 4x2 Pick Up Type Service Vehicle for the
Engineer
Unit of Measurement : month
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor
a. Driver 1 160 74.22 11,875.20

Sub - Total for A.1 - As Submitted 11,875.20


A.2 Labor
a. Driver 1 160 74.22 11,875.20

Sub - Total for A.2 - As Evaluated 11,875.20


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment

Sub - Total for B.1 - As Submitted 0.00


B.2 Equipment

Sub - Total for B.2 - As Evaluated 0.00


C.1 Total (A.1 + B.1) - As Submitted 11,875.20
C.2 Total (A.2 + B.2) - As Evaluated 11,875.20
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 11,875.20
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 11,875.20
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

a. Fuel Diesel ltr. 182 39.45 7,179.90


b. Diesel Gear Oil ltr. 15 220.00 3,300.00
c. Break Fluid ltr. 15 165.00 2,475.00

Sub - Total for F.1 - As Submitted 12,954.90


F.2 Materials

a. Fuel Diesel ltr. 182 39.45 7,179.90


b. Diesel Gear Oil ltr. 15 220.00 3,300.00
c. Break Fluid ltr. 15 165.00 2,475.00

Sub - Total for F.2 - As Evaluated 12,954.90


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 24,830.10
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 24,830.10
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 0% of G.1 0.00
I.2 Contractor's Profit (CP) - As Evaluated 0% of G.2 0.00
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 1,241.51
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 1,241.51
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 26,071.61
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 26,071.61

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : A.1.4(1) Provision of Progress Photographs


Unit of Measurement : each
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor

Sub - Total for A.1 - As Submitted 0.00


A.2 Labor

Sub - Total for A.2 - As Evaluated 0.00


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment

Sub - Total for B.1 - As Submitted 0.00


B.2 Equipment

Sub - Total for B.2 - As Evaluated 0.00


C.1 Total (A.1 + B.1) - As Submitted 0.00
C.2 Total (A.2 + B.2) - As Evaluated 0.00
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 0.00
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 0.00
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

a. Developing each 1 15.00 15.00

Sub - Total for F.1 - As Submitted 15.00


F.2 Materials

a. Developing each 1 15.00 15.00

Sub - Total for F.2 - As Evaluated 15.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 15.00
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 15.00
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 1.20
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 1.20
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 0.81
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 0.81
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 17.01
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 17.01

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : B.5 Project Billboard / Signboard


Unit of Measurement : each
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor
a. Foreman 1 4 102.73 410.92
b. Skilled Laborer 1 4 74.22 296.88
c. Unskilled Laborer 2 4 57.17 457.36

Sub - Total for A.1 - As Submitted 1,165.16


A.2 Labor
a. Foreman 1 4 102.73 410.92
b. Skilled Laborer 1 4 74.22 296.88
c. Unskilled Laborer 2 4 57.17 457.36

Sub - Total for A.2 - As Evaluated 1,165.16


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment

Sub - Total for B.1 - As Submitted 0.00


B.2 Equipment

Sub - Total for B.2 - As Evaluated 0.00


C.1 Total (A.1 + B.1) - As Submitted 1,165.16
C.2 Total (A.2 + B.2) - As Evaluated 1,165.16
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 1,165.16
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 1,165.16
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

a. 1/2 x 4 x 8' marine plywood pc. 1 900.00 900.00


b. Good Lumber bd.ft. 41 60.00 2,460.00
c. Project Sign (Tarpaulin) sq.ft. 32 25.00 800.00
d. Miscelleaneous Items (CWN) lot 1 500.00 500.00

Sub - Total for F.1 - As Submitted 4,660.00


F.2 Materials

a. 1/2 x 4 x 8' marine plywood pc. 1 900.00 900.00


b. Good Lumber bd.ft. 41 60.00 2,460.00
c. Project Sign (Tarpaulin) sq.ft. 32 25.00 800.00
d. Miscelleaneous Items (CWN) lot 1 500.00 500.00

Sub - Total for F.2 - As Evaluated 4,660.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 5,825.16
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 5,825.16
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% of G.1 582.52
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% of G.2 582.52
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 466.01
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 466.01
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 343.68
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 343.68
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 7,217.37
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 7,217.37

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : B.7(2) Occupational Safety and Health Program


Unit of Measurement : lump sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor
a. Safety Practitioner/Officer (Part Time) 1 1192 62.50 74,500.00
b. Health Officer (Full Time) 1 1192 35.00 41,720.00
c. Sanitation Aide 2 1192 35.00 83,440.00

Sub - Total for A.1 - As Submitted 199,660.00


A.2 Labor
a. Safety Practitioner/Officer (Part Time) 1 1192 62.50 74,500.00
b. Health Officer (Full Time) 1 1192 35.00 41,720.00
c. Sanitation Aide 2 1192 35.00 83,440.00

Sub - Total for A.2 - As Evaluated 199,660.00


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment
a. Portable Mist-Based Sanitation Tent 1 1192 9.79 11,669.68
b. Thermal Scanner (w/ rechargeable battery) 2 1192 1.03 2,455.52
c. Power Sprayer w/ complete accessories 1 1192 3.47 4,136.24

Sub - Total for B.1 - As Submitted 18,261.44


B.2 Equipment
a. Portable Mist-Based Sanitation Tent 1 1192 9.79 11,669.68
b. Thermal Scanner (w/ rechargeable battery) 2 1192 1.03 2,455.52
c. Power Sprayer w/ complete accessories 1 1192 3.47 4,136.24

Sub - Total for B.2 - As Evaluated 18,261.44


C.1 Total (A.1 + B.1) - As Submitted 217,921.44
C.2 Total (A.2 + B.2) - As Evaluated 217,921.44
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 217,921.44
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 217,921.44
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. Safety Helmet m-day 498.86 0.34 169.61
b. Safety Shoes m-day 484.75 4.11 1,992.32
c. Safety Vest m-day 498.86 2.22 1,107.47
d. Working Gloves m-day 498.86 7.67 3,826.26
e. Rubber Boots m-day 14.11 1.39 19.61
f. Eye Goggles m-day 498.86 5.00 2,494.30
g. Face Mask m-day 498.86 2.00 997.72
h. Face Shield m-day 498.86 8.33 4,155.50

Optional (if Necessary)


i. Rain Coats (30% of the Duration) m-day 498.86 0.34 169.61

COVID 19 Rapid Antibody Test each 6 1,000.00 6,000.00


Antiseptics and Disinfectants
j. Sanitizing Solution lit 42 100.00 4,200.00
k. Ethyl Alcohol lit 14 185.00 2,590.00
l. Disinfectant Spray can 7 1,000.00 7,000.00
m. Liquid Hand Soap lit 14 200.00 2,800.00

Sub - Total for F.1 - As Submitted 37,522.40


F.2 Materials
a. Safety Helmet m-day 498.86 0.34 169.61
b. Safety Shoes m-day 484.75 4.11 1,992.32
c. Safety Vest m-day 498.86 2.22 1,107.47
d. Working Gloves m-day 498.86 7.67 3,826.26
e. Rubber Boots m-day 14.11 1.39 19.61
f. Eye Goggles m-day 498.86 5.00 2,494.30
g. Face Mask m-day 498.86 2.00 997.72
h. Face Shield m-day 498.86 8.33 4,155.50

Optional (if Necessary)


i. Rain Coats (30% of the Duration) m-day 498.86 0.34 169.61

COVID 19 Rapid Antibody Test each 6 1,000.00 6,000.00


Antiseptics and Disinfectants
j. Sanitizing Solution lit 42 100.00 4,200.00
k. Ethyl Alcohol lit 14 185.00 2,590.00
l. Disinfectant Spray can 7 1,000.00 7,000.00
m. Liquid Hand Soap lit 14 200.00 2,800.00

Sub - Total for F.2 - As Evaluated 37,522.40


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 255,443.84
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 255,443.84
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 20,435.51
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 20,435.51
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 13,793.97
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 13,793.97
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 289,673.32
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 289,673.32

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

DETAILED CALCULATIONS ON COST OF CONSTRUCTION SAFETY AND HEALTH

ITEM NO./DESCRPTION OUTPUT NO. OF SAFETY SAFETY SAFETY WORKING RAIN DUST/GAS BODY RUBBER EYE FACE
QUANTITY WORKERS DAYS MAN-DAYS EAR MUFF LANYARD FACE MASK TOTAL COST
PER HOUR PERSONNEL HELMET SHOES VEST GLOVES COATS MASK HARNESS BOOTS GOOGLES SHIELD
Foreman - 26.73 - - - - - - - - -
Removal of Actual Structures/Obstruction
101(3)c1 5,346.60 25.00 Skilled Laborer - 26.73 - - - - - - - - -
(0.05m thick, ACP)
Unskilled Laborer - 26.73 - - - - - - - - -
Foreman 1 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25 0.25
Removal of Actual Structures/Obstruction
101(3)b5 60.30 30.00 Skilled Laborer - 0.25 - - - - - - - - -
(0.28m thick, PCCP (Unreinforced))
Unskilled Laborer 2 0.25 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50
Foreman 1 0.64 0.64 0.64 0.64 0.64 0.64 0.64 0.64 0.64 0.64
102(2) Surplus Common Excavation 306.83 60.00 Skilled Laborer - 0.64 - - - - - - - - -
Unskilled Laborer 2 0.64 1.28 1.28 1.28 1.28 1.28 1.28 1.28 1.28 1.28
Foreman 1 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15
Subgrade Preparation (Common
105(1)a 357.99 300.00 Skilled Laborer - 0.15 - - - - - - - - -
Material)
Unskilled Laborer 2 0.15 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30
Foreman 1 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16 0.16
200(1) Aggregate Subbase Course 65.70 50.00 Skilled Laborer - 0.16 - - - - - - - - -
Unskilled Laborer 2 0.16 0.32 0.32 0.32 0.32 0.32 0.32 0.32 0.32 0.32
Foreman 1 12.04 12.04 12.04 12.04 12.04 12.04 12.04 12.04 12.04 12.04
Bituminous Tack Coat (Emulsified
302(2) 41,372.30 429.51 Skilled Laborer - 12.04 - - - - - - - - -
Asphalt)
Unskilled Laborer 3 12.04 36.12 36.12 36.12 36.12 36.12 36.12 36.12 36.12 36.12
Foreman 1 12.08 12.08 12.08 12.08 12.08 12.08 12.08 12.08 12.08 12.08
Bituminous Tack Coat (Emulsified
310(1)b 20,686.15 214.13 Skilled Laborer 4 12.08 48.32 48.32 48.32 48.32 48.32 48.32 48.32 48.32 48.32
Asphalt)
Unskilled Laborer 8 12.08 96.64 96.64 96.64 96.64 96.64 96.64 96.64 96.64 96.64
Foreman 1 12.08 12.08 12.08 12.08 12.08 12.08 12.08 12.08 12.08 12.08
Bituminous Concrete Surface Binder
310(2)b 20,686.15 214.13 Skilled Laborer 4 12.08 48.32 48.32 48.32 48.32 48.32 48.32 48.32 48.32 48.32
Course, Hot-Laid (40mm)
Unskilled Laborer 8 12.08 96.64 96.64 96.64 96.64 96.64 96.64 96.64 96.64 96.64
Foreman 1 0.83 0.83 0.83 0.83 0.83 0.83 0.83 0.83 0.83 0.83
Portland Cement Concrete Pavement
311(1)f1 357.99 53.67 Skilled Laborer 4 0.83 3.32 3.32 3.32 3.32 3.32 3.32 3.32 3.32 3.32
(Unreinforced) (0.30 m thick, 14 days)
Unskilled Laborer 12 0.83 9.96 9.96 9.96 9.96 9.96 9.96 9.96 9.96 9.96
Foreman 1 0.53 0.53 0.53 0.53 0.53 0.53 0.53 0.53 0.53 0.53
600(4) Curb and Gutter (Cast in Place) 63.00 15.00 Skilled Laborer 4 0.53 2.12 2.12 2.12 2.12 2.12 2.12 2.12 2.12 2.12
Unskilled Laborer 8 0.53 4.24 4.24 4.24 4.24 4.24 4.24 4.24 4.24 4.24
Foreman 1 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47 0.47
601(1) Sidewalk (100mm thk.) 75.60 20.00 Skilled Laborer 4 0.47 1.88 1.88 1.88 1.88 1.88 1.88 1.88 1.88 1.88
Unskilled Laborer 12 0.47 5.64 5.64 5.64 5.64 5.64 5.64 5.64 5.64 5.64
Regulatory Signs (600mm, R6-8B, Foreman 1 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75
605(2)ai2 Miscellaneous Signs Pedestrian 6.00 1.00 Skilled Laborer 1 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75
Crossing) Unskilled Laborer 2 0.75 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50 1.50
Foreman 1 6.31 6.31 6.31 6.31 6.31 6.31 6.31 6.31 6.31 6.31
Internally Illuminated (Solar) Pavement
607(3)b 404.00 8.00 Skilled Laborer 2 6.31 12.62 12.62 12.62 12.62 12.62 12.62 12.62 12.62 12.62
Levelled Marker/Stud Flush Type
Unskilled Laborer 2 6.31 12.62 12.62 12.62 12.62 12.62 12.62 12.62 12.62 12.62
Foreman 1 4.28 4.28 4.28 4.28 4.28 4.28 4.28 4.28 4.28 4.28
Reflectorized Thermoplastic Pavement
612(1) 855.76 25.00 Skilled Laborer 2 4.28 8.56 8.56 8.56 8.56 8.56 8.56 8.56 8.56 8.56
Markings White
Unskilled Laborer 6 4.28 25.68 25.68 25.68 25.68 25.68 25.68 25.68 25.68 25.68
Foreman 1 3.44 3.44 3.44 3.44 3.44 3.44 3.44 3.44 3.44 3.44
Reflectorized Thermoplastic Rumble
618(1) 687.75 25.00 Skilled Laborer 2 3.44 6.88 6.88 6.88 6.88 6.88 6.88 6.88 6.88 6.88
Strips
Unskilled Laborer 6 3.44 20.64 20.64 20.64 20.64 20.64 20.64 20.64 20.64 20.64
A. TOTAL PERSONNEL/MAN-DAYS 116 498.86 498.86 484.75 498.86 498.86 498.86 - - - - 14.11 498.86 498.86 498.86
B. SERVICE LIFE, DAYS 730.00 365.00 180.00 3.00 730.00 1.00 730.00 730.00 730.00 365.00 60.00 5.00 60.00
C. PURCHASE COST, PPh 250.00 1,500.00 400.00 23.00 245.00 63.25 602.50 1,263.85 1,083.30 506.00 300.00 10.00 500.00
D. UNIT COST/MAN-DAY(C/B) 0.34 4.11 2.22 7.67 0.34 63.25 0.83 1.73 1.48 1.39 5.00 2.00 8.33
E. DIRECT COST FOR PPE's (D*A(Man-days)) 170.84 1,992.12 1,108.58 3,824.59 167.43 - - - - 19.56 2,494.30 997.72 4,157.17 14,932.31
F. SAFETY OFFICER/PRACTITIONER(PART TIME) @ P15,000.00/MONTH (AS PER D.O. 56,S2005, consider at least 4hours per week) -
G. HEALTH PERSONNEL ( FULL TIME) @ P8,400.00/MONTH (AS PER D.O. 56,s2005) -
H. TOTAL DIRECT COSTM(E+F+G) 14,932.31
I. OCM (0% of E) -
J. PROFIT (8% of H) 1,194.58
K. VAT (5% of (H+I+J)) 806.34
L. TOTAL COST (H+I+J+K) 16,933.23

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : B.8(2) Traffic Management


Unit of Measurement : lump sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor
a. Construction Foreman 1 30 102.73 3,081.90
b. Skilled Laborer 2 30 74.22 4,453.20
c. Unskilled Laborer 3 30 57.17 5,145.30

Sub - Total for A.1 - As Submitted 12,680.40


A.2 Labor
a. Construction Foreman 1 30 102.73 3,081.90
b. Skilled Laborer 2 30 74.22 4,453.20
c. Unskilled Laborer 3 30 57.17 5,145.30

Sub - Total for A.2 - As Evaluated 12,680.40


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment

a. Barricade Flasher Light (3 Volts, Battery Operated, 32 888 0.65 18,470.40


Amber Color w/ lifespan consideration of 6 months)

Sub - Total for B.1 - As Submitted 18,470.40


B.2 Equipment

a. Barricade Flasher Light (3 Volts, Battery Operated, 32 888 0.65 18,470.40


Amber Color w/ lifespan consideration of 6 months)

Sub - Total for B.2 - As Evaluated 18,470.40


C.1 Total (A.1 + B.1) - As Submitted 31,150.80
C.2 Total (A.2 + B.2) - As Evaluated 31,150.80
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 31,150.80
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 31,150.80
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. Water Filled Road Barrier pc. 75 3,500.00 262,500.00
b. High Intensity Prismatic White Reflectorized Sticker sq.m. 93.375 2,750.00 256,781.25
c. Temporary Bollards (@ 5 meters apart) each 14.00 350.00 4,900.00
d. Misc. Items (CWN, Spray Paint, etc.) lot 1 5,000.00 5,000.00

Rental Basis (Based on D.O 13 series of 2018)


a. Roadwork 1 km Ahead each 2.00 1,631.76 3,263.52
b. Lane Status each 4.00 1,929.46 7,717.84
c. Road Work each 2.00 576.68 1,153.36
d. Speed Restriction each 2.00 704.18 1,408.36
e.Workmen Ahead each 2.00 840.26 1,680.52
f. Temporary Hazard Maker (Chervon) each 4.00 1193.30 4,773.20
g. End Speed Restriction each 2.00 827.47 1,654.94
h. End RoadWork each 2.00 1,631.76 3,263.52

Sub - Total for F.1 - As Submitted 554,096.51


F.2 Materials
a. Water Filled Road Barrier pc. 75 3,500.00 262,500.00
b. High Intensity Prismatic White Reflectorized Sticker sq.m. 93.375 2,750.00 256,781.25
c. Temporary Bollards (@ 5 meters apart) each 14.00 350.00 4,900.00
d. Misc. Items (CWN, Spray Paint, etc.) lot 1 5,000.00 5,000.00

Rental Basis (Based on D.O 13 series of 2018)


a. Roadwork 1 km Ahead each 2.00 1,631.76 3,263.52
b. Lane Status each 4.00 1,929.46 7,717.84
c. Road Work each 2.00 576.68 1,153.36
d. Speed Restriction each 2.00 704.18 1,408.36
e.Workmen Ahead each 2.00 840.26 1,680.52
f. Temporary Hazard Maker (Chervon) each 4.00 1,193.30 4,773.20
g. End Speed Restriction each 2.00 827.47 1,654.94
h. End RoadWork each 2.00 1,631.76 3,263.52

Sub - Total for F.2 - As Evaluated 554,096.51


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 585,247.31
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 585,247.31
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 46,819.78
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 46,819.78
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 31,603.35
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 31,603.35
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 663,670.44
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 663,670.44

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

DETAILED CALCULATIONS ON COST OF TRAFFIC MANAGEMENT

Materials (Rental Basis Based on


Price For 3 years span Unit Cost per day Calendar Days Total Unit Cost
DO13)
Roadwork 1 km Ahead 11,991.80 10.95 149.00 1,631.76
Lane Status 14,179.56 12.95 149.00 1,929.46
Road Work 4,238.04 3.87 149.00 576.68
Speed Restriction 5,175.04 4.73 149.00 704.18
Workmen Ahead 6,175.04 5.64 149.00 840.26
Temporary Hazard Maker
8,769.56 8.01 149.00 1,193.30
(Chervon)
End Speed Restriction 6,081.04 5.55 149.00 827.47
End RoadWork 11,991.80 10.95 149.00 1,631.76

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : B.9 Mobilization / Demobilization


Unit of Measurement : lump sum
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor

Sub - Total for A.1 - As Submitted 0.00


A.2 Labor

Sub - Total for A.2 - As Evaluated 0.00


No of No. of
Name and Capacity Rate per trip Amount (Php)
Unit/s Trips
B.1 Equipment

a. Low Bed Trailer 1 6 20,000.00 120,000.00

Sub - Total for B.1 - As Submitted 120,000.00


B.2 Equipment

a. Low Bed Trailer 1 6 20,000.00 120,000.00

Sub - Total for B.2 - As Evaluated 120,000.00


C.1 Total (A.1 + B.1) - As Submitted 120,000.00
C.2 Total (A.2 + B.2) - As Evaluated 120,000.00
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 120,000.00
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 120,000.00
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

Sub - Total for F.1 - As Submitted 0.00


F.2 Materials

Sub - Total for F.2 - As Evaluated 0.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 120,000.00
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 120,000.00
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 0% of G.1 0.00
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 0% of G.2 0.00
I.1 Contractor's Profit (CP) - As Submitted 0% of G.1 0.00
I.2 Contractor's Profit (CP) - As Evaluated 0% of G.2 0.00
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 6,000.00
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 6,000.00
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 126,000.00
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 126,000.00

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 101(3)c1 Removal of Actual Structures/Obstruction (0.05m thick, ACP)

Unit of Measurement : sq.m.


Output per hour - As Submitted : 25.00
Output per hour - As Evaluated : 25.00

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor

Sub - Total for A.1 - As Submitted -


A.2 Labor

Sub - Total for A.2 - As Evaluated -


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment
a. WIRTGEN (SF1900C 1920 mm milling width / 150 mm
1 1 5,145.00 5,145.00
max depth)
b. Pay Loader (1.50 cu.m.) 1 1 1,733.00 1,733.00
c. Dump Truck (10 cu.m.) 2 1 1,420.00 2,840.00
Minor Tools (10% of Labor) lot 0.00 0.00

Sub - Total for B.1 - As Submitted 9,718.00


B.2 Equipment
a. WIRTGEN (SF1900C 1920 mm milling width / 150 mm
1 1 5,145.00 5,145.00
max depth)
b. Pay Loader (1.50 cu.m.) 1 1 1,733.00 1,733.00
c. Dump Truck (10 cu.m.) 2 1 1,420.00 2,840.00
Minor Tools (10% of Labor) lot 0.00 0.00

Sub - Total for B.2 - As Evaluated 9,718.00


C.1 Total (A.1 + B.1) - As Submitted 9,718.00
C.2 Total (A.2 + B.2) - As Evaluated 9,718.00
D.1 Output per hour - As Submitted 25.00
D.2 Output per hour - As Evaluated 25.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 388.72
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 388.72
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

Sub - Total for F.1 - As Submitted 0.00


F.2 Materials

Sub - Total for F.2 - As Evaluated 0.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 388.72
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 388.72
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% of G.1 38.87
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% of G.2 38.87
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 31.10
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 31.10
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 22.93
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 22.93
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 481.62
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 481.62

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 101(3)b5 Removal of Actual Structures/Obstruction (0.28m thick, PCCP


(Unreinforced))
Unit of Measurement : sq.m.
Output per hour - As Submitted : 30.00
Output per hour - As Evaluated : 30.00

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor

a. Foreman 1 1 102.73 102.73


b. Unskilled Laborers 2 1 57.17 114.34

Sub - Total for A.1 - As Submitted 217.07


A.2 Labor

a. Foreman 1 1 102.73 102.73


b. Unskilled Laborers 2 1 57.17 114.34

Sub - Total for A.2 - As Evaluated 217.07


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment
a. Backhoe with Pavement Breaker (0.80 cu.m.) 1 1 2,724.80 2,724.80
b. Payloader (1.50 cu.m.) , LX80-2C 1 1 1,733.00 1,733.00
c. Dump Truck (10 cu.m.) 1 0.5 1,420.00 710.00
d. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 0.5 32.64 16.32
Minor Tools (10% of Labor Cost) 21.71 21.71

Sub - Total for B.1 - As Submitted 5,205.83


B.2 Equipment
a. Backhoe with Pavement Breaker (0.80 cu.m.) 1 1 2,724.80 2,724.80
b. Payloader (1.50 cu.m.) , LX80-2C 1 1 1,733.00 1,733.00
c. Dump Truck (10 cu.m.) 1 0.5 1,420.00 710.00
d. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 0.5 32.64 16.32
Minor Tools (10% of Labor Cost) 21.71 21.71

Sub - Total for B.2 - As Evaluated 5,205.83


C.1 Total (A.1 + B.1) - As Submitted 5,422.90
C.2 Total (A.2 + B.2) - As Evaluated 5,422.90
D.1 Output per hour - As Submitted 30.00
D.2 Output per hour - As Evaluated 30.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 180.76
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 180.76
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20

Sub - Total for F.1 - As Submitted 1.20


F.2 Materials
a. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20

Sub - Total for F.2 - As Evaluated 1.20


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 181.96
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 181.96
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% of G.1 18.20
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% of G.2 18.20
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 14.56
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 14.56
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 10.74
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 10.74
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 225.46
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 225.46

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 102(2) Surplus Common Excavation


Unit of Measurement : cu.m.
Output per hour - As Submitted : 60.00
Output per hour - As Evaluated : 60.00

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor

a. Foreman 1 1 102.73 102.73


b. Unskilled Laborers 2 1 57.17 114.34

Sub - Total for A.1 - As Submitted 217.07


A.2 Labor

a. Foreman 1 1 102.73 102.73


b. Unskilled Laborers 2 1 57.17 114.34

Sub - Total for A.2 - As Evaluated 217.07


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment
a. Backhoe (0.80 cu.m.) 1 1 2,096.00 2,096.00
b. Payloader (1.50 cu.m.) 1 1 1,733.00 1,733.00
c. Payloader (1.50 cu.m.) at disposal site 1 0.25 1,733.00 433.25
d. Dump Truck (10 cu.m.) 2 1 1,420.00 2,840.00
Minor Tools (10% of Labor Cost) 21.71 21.71

Sub - Total for B.1 - As Submitted 7,123.96


B.2 Equipment
a. Backhoe (0.80 cu.m.) 1 1 2,096.00 2,096.00
b. Payloader (1.50 cu.m.) 1 1 1,733.00 1,733.00
c. Payloader (1.50 cu.m.) at disposal site 1 0.25 1,733.00 433.25
d. Dump Truck (10 cu.m.) 2 1 1,420.00 2,840.00
Minor Tools (10% of Labor Cost) 21.71 21.71

Sub - Total for B.2 - As Evaluated 7,123.96


C.1 Total (A.1 + B.1) - As Submitted 7,341.03
C.2 Total (A.2 + B.2) - As Evaluated 7,341.03
D.1 Output per hour - As Submitted 60.00
D.2 Output per hour - As Evaluated 60.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 122.35
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 122.35
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

Sub - Total for F.1 - As Submitted 0.00


F.2 Materials

Sub - Total for F.2 - As Evaluated 0.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 122.35
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 122.35
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% of G.1 12.24
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% of G.2 12.24
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 9.79
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 9.79
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 7.22
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 7.22
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 151.60
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 151.60

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 105(1)a Subgrade Preparation (Common Material)


Unit of Measurement : sq.m.
Output per hour - As Submitted : 300.00
Output per hour - As Evaluated : 300.00

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor

a. Foreman 1 1 102.73 102.73


b. Unskilled Laborer 2 1 57.17 114.34

Sub - Total for A.1 - As Submitted 217.07


A.2 Labor

a. Foreman 1 1 102.73 102.73


b. Unskilled Laborer 2 1 57.17 114.34

Sub - Total for A.2 - As Evaluated 217.07


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,846.00 1,846.00
c. Water Truck (16,000 lit.) 1 0.25 2,450.00 612.50

Sub - Total for B.1 - As Submitted 4,631.50


B.2 Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,846.00 1,846.00
c. Water Truck (16,000 lit.) 1 0.25 2,450.00 612.50

Sub - Total for B.2 - As Evaluated 4,631.50


C.1 Total (A.1 + B.1) - As Submitted 4,848.57
C.2 Total (A.2 + B.2) - As Evaluated 4,848.57
D.1 Output per hour - As Submitted 300.00
D.2 Output per hour - As Evaluated 300.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 16.16
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 16.16
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials

Sub - Total for F.1 - As Submitted 0.00


F.2 Materials

Sub - Total for F.2 - As Evaluated 0.00


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 16.16
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 16.16
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% of G.1 1.62
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% of G.2 1.62
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 1.29
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 1.29
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 0.95
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 0.95
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 20.02
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 20.02

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 200(1) Aggregate Subbase Course


Unit of Measurement : cu.m.
Output per hour - As Submitted : 50.00
Output per hour - As Evaluated : 50.00

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor

a. Foreman 1 1 102.73 102.73


b. Unskilled Laborer 2 1 57.17 114.34

Sub - Total for A.1 - As Submitted 217.07


A.2 Labor

a. Foreman 1 1 102.73 102.73


b. Unskilled Laborer 2 1 57.17 114.34

Sub - Total for A.2 - As Evaluated 217.07


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,846.00 1,846.00
c. Water Truck (16,000 lit.) 1 0.25 2,450.00 612.50

Sub - Total for B.1 - As Submitted 4,631.50


B.2 Equipment

a. Motorized Road Grader, G710A 1 1 2,173.00 2,173.00


b. Vibratory Roller (10 m.t.), SP56 1 1 1,846.00 1,846.00
c. Water Truck (16,000 lit.) 1 0.25 2,450.00 612.50

Sub - Total for B.2 - As Evaluated 4,631.50


C.1 Total (A.1 + B.1) - As Submitted 4,848.57
C.2 Total (A.2 + B.2) - As Evaluated 4,848.57
D.1 Output per hour - As Submitted 50.00
D.2 Output per hour - As Evaluated 50.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 96.97
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 96.97
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. Aggregate Subbase Course cu.m. 1.15 707.36 813.46
(w/ 15% Shrinkage Factor)

Sub - Total for F.1 - As Submitted 813.46


F.2 Materials
a. Aggregate Subbase Course cu.m. 1.15 707.36 813.46
(w/ 15% Shrinkage Factor)

Sub - Total for F.2 - As Evaluated 813.46


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 910.43
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 910.43
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% of G.1 91.04
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% of G.2 91.04
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 72.83
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 72.83
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 53.72
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 53.72
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 1,128.02
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 1,128.02

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 302(2) Bituminous Tack Coat (Emulsified Asphalt)


Unit of Measurement : sq.m.
Output per hour - As Submitted : 429.51
Output per hour - As Evaluated : 429.51

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor

a. Foreman 1 1 102.73 102.73


b. Unskilled Laborer 3 1 57.17 171.51

Sub - Total for A.1 - As Submitted 274.24


A.2 Labor

a. Foreman 1 1 102.73 102.73


b. Unskilled Laborer 3 1 57.17 171.51

Sub - Total for A.2 - As Evaluated 274.24


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B.1 - As Submitted 1,066.54


B.2 Equipment

a. Asphalt Distributor, 10 ft. wide (5 tons) 1 1 936.00 936.00


b. Power Broom (20 m. wide) 1 1 130.54 130.54

Sub - Total for B.2 - As Evaluated 1,066.54


C.1 Total (A.1 + B.1) - As Submitted 1,340.78
C.2 Total (A.2 + B.2) - As Evaluated 1,340.78
D.1 Output per hour - As Submitted 429.51
D.2 Output per hour - As Evaluated 429.51
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 3.12
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 3.12
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
Emulsified Asphalt SS-1 sq.m. 1 58.82 58.82

Sub - Total for F.1 - As Submitted 58.82


F.2 Materials
Emulsified Asphalt SS-1 sq.m. 1 58.82 58.82

Sub - Total for F.2 - As Evaluated 58.82


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 61.94
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 61.94
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% of G.1 6.19
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% of G.2 6.19
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 4.96
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 4.96
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 3.65
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 3.65
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 76.74
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 76.74

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 310(1)b Bituminous Concrete Surface Wearing Course, Hot-Laid (40mm)
Unit of Measurement : sq.m.
Output per hour - As Submitted : 214.13
Output per hour - As Evaluated : 214.13

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor

a. Foreman 1 1 102.73 102.73


b. Skilled Laborer 4 1 74.22 296.88
c. Unskilled Laborer 8 1 57.17 457.36

Sub - Total for A.1 - As Submitted 856.97


A.2 Labor

a. Foreman 1 1 102.73 102.73


b. Skilled Laborer 4 1 74.22 296.88
c. Unskilled Laborer 8 1 57.17 457.36

Sub - Total for A.2 - As Evaluated 856.97


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment

a. Asphalt Paver (80 Hp) 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
d. Water Truck (16000 L) 1 1 2,450.00 2,450.00
Minor Tools (10% of Labor) 1 1 85.70 85.70

Sub - Total for B.1 - As Submitted 6,581.70


B.2 Equipment

a. Asphalt Paver (80 Hp) 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
d. Water Truck (16000 L) 1 1 2,450.00 2,450.00
Minor Tools (10% of Labor) 1 1 85.70 85.70

Sub - Total for B.2 - As Evaluated 6,581.70


C.1 Total (A.1 + B.1) - As Submitted 7,438.67
C.2 Total (A.2 + B.2) - As Evaluated 7,438.67
D.1 Output per hour - As Submitted 214.13
D.2 Output per hour - As Evaluated 214.13
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 34.74
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 34.74
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. Bituminous Concrete Surface Course m.t. 0.0980 12,885.00 1,262.73

Sub - Total for F.1 - As Submitted 1,262.73


F.2 Materials
a. Bituminous Concrete Surface Course m.t. 0.0980 12,885.00 1,262.73

Sub - Total for F.2 - As Evaluated 1,262.73


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 1,297.47
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 1,297.47
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% of G.1 129.75
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% of G.2 129.75
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 103.80
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 103.80
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 76.55
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 76.55
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 1,607.57
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 1,607.57

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 310(2)b Bituminous Concrete Surface Binder Course, Hot-Laid (40mm)
Unit of Measurement : sq.m.
Output per hour - As Submitted : 214.13
Output per hour - As Evaluated : 214.13

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor

a. Foreman 1 1 102.73 102.73


b. Skilled Laborers 4 1 74.22 296.88
c. Unskilled Laborer 8 1 57.17 457.36

Sub - Total for A.1 - As Submitted 856.97


A.2 Labor

a. Foreman 1 1 102.73 102.73


b. Skilled Laborer 4 1 74.22 296.88
c. Unskilled Laborer 8 1 57.17 457.36

Sub - Total for A.2 - As Evaluated 856.97


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment

a. Asphalt Paver (80 Hp) 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
d. Water Truck (16000 L) 1 1 2,450.00 2,450.00
Minor Tools (10% of Labor) 1 1 85.70 85.70

Sub - Total for B.1 - As Submitted 6,581.70


B.2 Equipment

a. Asphalt Paver (80 Hp) 1 1 1,833.00 1,833.00


b. Pneumatic Tire Roller (10 m.t.) 1 1 561.00 561.00
c. Tandem Steel Roller (10.1 m.t.), CC421 1 1 1,652.00 1,652.00
d. Water Truck (16000 L) 1 1 2,450.00 2,450.00
Minor Tools (10% of Labor) 1 1 85.70 85.70

Sub - Total for B.2 - As Evaluated 6,581.70


C.1 Total (A.1 + B.1) - As Submitted 7,438.67
C.2 Total (A.2 + B.2) - As Evaluated 7,438.67
D.1 Output per hour - As Submitted 214.13
D.2 Output per hour - As Evaluated 214.13
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 34.74
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 34.74
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. Bituminous Concrete Surface Course m.t. 0.0980 12,885.00 1,262.73

Sub - Total for F.1 - As Submitted 1,262.73


F.2 Materials
a. Bituminous Concrete Surface Course m.t. 0.0980 12,885.00 1,262.73

Sub - Total for F.2 - As Evaluated 1,262.73


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 1,297.47
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 1,297.47
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% of G.1 129.75
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% of G.2 129.75
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 103.80
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 103.80
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 76.55
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 76.55
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 1,607.57
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 1,607.57

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 311(1)f1 Portland Cement Concrete Pavement (Unreinforced) (0.30 m thick, 14
days)
Unit of Measurement : sq.m.
Output per hour - As Submitted : 53.67
Output per hour - As Evaluated : 53.67

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor

a. Foreman 1 1 102.73 102.73


b. Skilled Laborer 4 1 74.22 296.88
c. Unskilled Laborer 12 1 57.17 686.04

Sub - Total for A.1 - As Submitted 1,085.65


A.2 Labor

a. Foreman 1 1 102.73 102.73


b. Skilled Laborer 4 1 74.22 296.88
c. Unskilled Laborer 12 1 57.17 686.04

Sub - Total for A.2 - As Evaluated 1,085.65


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment

a. Concrete Vibrator 2 1 57.17 114.34


b. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
c. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 32.64 32.64
d. Bar Cutter, Single Phase, 25 mm. 1 0.1 105.47 10.55
Minor Tools (5% of Labor) 1 1 54.28 54.28

Sub - Total for B.1 - As Submitted 756.81


B.2 Equipment

a. Concrete Vibrator 2 1 57.17 114.34


b. Concrete Screeder (5.5 Hp) 1 1 545.00 545.00
c. Concrete Saw, Blade Ø 14" (7.5 Hp) 1 1 32.64 32.64
d. Bar Cutter, Single Phase, 25 mm. 1 0.1 105.47 10.55
Minor Tools (5% of Labor) 1 1 54.28 54.28

Sub - Total for B.2 - As Evaluated 756.81


C.1 Total (A.1 + B.1) - As Submitted 1,842.46
C.2 Total (A.2 + B.2) - As Evaluated 1,842.46
D.1 Output per hour - As Submitted 53.67
D.2 Output per hour - As Evaluated 53.67
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 34.33
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 34.33
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. Reinforcing Steel Bar kg. 0.850 38.53 32.75
b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.17 44.00 7.48
d. Steel Forms, 300 mm width l.m. 0.46 160.00 73.60
e. Ready Mix Concrete (3500psi @ 14 days) cu.m. 0.30 6,050.00 1,815.00
f. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
g. Pipe Sleeve, 1/2" dia. l.m. 0.0094 225.00 2.12
h. Grease / Tar lit. 0.0094 112.00 1.05

Sub - Total for F.1 - As Submitted 1,941.32


F.2 Materials
a. Reinforcing Steel Bar kg. 0.850 38.53 32.75
b. Curing Compound lit. 0.29 28.00 8.12
c. Asphalt Sealant lit. 0.17 44.00 7.48
d. Steel Forms, 300 mm width l.m. 0.46 160.00 73.60
e. Ready Mix Concrete (3500psi @ 14 days) cu.m. 0.30 6,050.00 1,815.00
f. Concrete Saw (diamond blade 14") pc. 0.00015 8,000.00 1.20
g. Pipe Sleeve, 1/2" dia. l.m. 0.0094 225.00 2.12
h. Grease / Tar lit. 0.0094 112.00 1.05

Sub - Total for F.2 - As Evaluated 1,941.32


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 1,975.65
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 1,975.65
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% of G.1 197.57
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% of G.2 197.57
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 158.05
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 158.05
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 116.56
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 116.56
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 2,447.83
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 2,447.83

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 600(4) Curb and Gutter (Cast in Place)

Unit of Measurement : l.m.


Output per hour - As Submitted : 15.00
Output per hour - As Evaluated : 15.00

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor

a. Foreman 1 1 102.73 102.73


b. Skilled Laborer 4 1 74.22 296.88
c. Unskilled Laborer 8 1 57.17 457.36

Sub - Total for A.1 - As Submitted 856.97


A.2 Labor

a. Foreman 1 1 102.73 102.73


b. Skilled Laborer 4 1 74.22 296.88
c. Unskilled Laborer 8 1 57.17 457.36

Sub - Total for A.2 - As Evaluated 856.97


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Concrete Vibrator 1 1 57.17 57.17
c. Water Truck (16,000 L) 1 0.05 2,450.00 122.50
Minor Tools (10% of Labor) 1 1 85.70 85.70

Sub - Total for B.1 - As Submitted 437.37


B.2 Equipment

a. One Bagger Mixer 1 1 172.00 172.00


b. Concrete Vibrator 1 1 57.17 57.17
c. Water Truck (16,000 L) 1 0.05 2,450.00 122.50
Minor Tools (10% of Labor) 1 1 85.70 85.70

Sub - Total for B.2 - As Evaluated 437.37


C.1 Total (A.1 + B.1) - As Submitted 1,294.34
C.2 Total (A.2 + B.2) - As Evaluated 1,294.34
D.1 Output per hour - As Submitted 15.00
D.2 Output per hour - As Evaluated 15.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 86.29
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 86.29
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. Cement bag 1.080 250.00 270.00
b. Sand cu.m. 0.06 1,307.36 78.44
c. Gravel (3/4) cu.m. 0.12 1,307.36 156.88
d. Marine Plywood (1/2" x 4'x 8') - 4 uses pc 0.20 900.00 45.00
e. Good Lumber - 4 uses bd.ft. 10.42 60.00 156.30
f. Miscellaneous Materials (5% of Materials) l.s 1 35.33 35.33

Sub - Total for F.1 - As Submitted 741.95


F.2 Materials
a. Cement bag 1.080 250.00 270.00
b. Sand cu.m. 0.06 1,307.36 78.44
c. Gravel (3/4) cu.m. 0.12 1,307.36 156.88
d. Marine Plywood (1/2" x 4'x 8') - 4 uses pc 0.20 900.00 45.00
e. Good Lumber - 4 uses bd.ft. 10.42 60.00 156.30
f. Miscellaneous Materials (5% of Materials) l.s 1 35.33 35.33

Sub - Total for F.2 - As Evaluated 741.95


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 828.24
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 828.24
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% of G.1 82.82
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% of G.2 82.82
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 66.26
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 66.26
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 48.87
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 48.87
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 1,026.19
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 1,026.19

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 601(1) Sidewalk (100mm thk.)

Unit of Measurement : sq.m.


Output per hour - As Submitted : 20.00
Output per hour - As Evaluated : 20.00

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor

a. Foreman 1 1 102.73 102.73


b. Skilled Laborer 4 1 74.22 296.88
c. Unskilled Laborer 12 1 57.17 686.04

Sub - Total for A.1 - As Submitted 1,085.65


A.2 Labor

a. Foreman 1 1 102.73 102.73


b. Skilled Laborer 4 1 74.22 296.88
c. Unskilled Laborer 12 1 57.17 686.04

Sub - Total for A.2 - As Evaluated 1,085.65


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment

a. One bagger Mixer 1 1 172.00 172.00


b. Concrete Vibrator 2 1 57.17 114.34
c. Water Truck/Pump (16000 L) 1 0.125 2,450.00 306.25
d. Concrete Saw (7.5 hp), 14" Blade Ø 1 1 32.50 32.50
Minor Tools (5% of Labor) 1 1 54.28 54.28

Sub - Total for B.1 - As Submitted 679.37


B.2 Equipment

a. One bagger Mixer 1 1 172.00 172.00


b. Concrete Vibrator 2 1 57.17 114.34
c. Water Truck/Pump (16000 L) 1 0.125 2,450.00 306.25
d. Concrete Saw (7.5 hp), 14" Blade Ø 1 1 32.50 32.50
Minor Tools (5% of Labor) 1 1 54.28 54.28

Sub - Total for B.2 - As Evaluated 679.37


C.1 Total (A.1 + B.1) - As Submitted 1,765.02
C.2 Total (A.2 + B.2) - As Evaluated 1,765.02
D.1 Output per hour - As Submitted 20.00
D.2 Output per hour - As Evaluated 20.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 88.25
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 88.25
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. Reinforcing Steel Bar (Grade 40) kg. 3.530 37.50 132.38
b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Forms l.m. 0.46 80.00 36.80
e. Sand cu.m. 0.055 1,342.21 73.82
f. Gravel 3/4 cu.m. 0.1 1,342.21 134.22
g. Cement bag 0.95 250.00 237.50
Note: Bed Course exluded

Sub - Total for F.1 - As Submitted 628.12


F.2 Materials
a. Reinforcing Steel Bar (Grade 40) kg. 3.530 37.50 132.38
b. Curing Compound L 0.29 28.00 8.12
c. Asphalt Sealant L 0.12 44.00 5.28
d. Forms l.m. 0.46 80.00 36.80
e. Sand cu.m. 0.055 1,342.21 73.82
f. Gravel 3/4 cu.m. 0.1 1,342.21 134.22
g. Cement bag 0.95 250.00 237.50
Note: Bed Course exluded

Sub - Total for F.2 - As Evaluated 628.12


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 716.37
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 716.37
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% of G.1 71.64
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% of G.2 71.64
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 57.31
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 57.31
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 42.27
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 42.27
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 887.59
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 887.59

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 605(2)ai2 Regulatory Signs (600mm, R6-8B, Miscellaneous Signs Pedestrian
Crossing)
Unit of Measurement : each
Output per hour - As Submitted : 1.00
Output per hour - As Evaluated : 1.00

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor
a. Foreman 1 1 102.73 102.73
b. Skilled Laborer 1 1 74.22 74.22
c. Unskilled Laborer 2 1 57.17 114.34

Sub - Total for A.1 - As Submitted 291.29


A.2 Labor
a. Foreman 1 1 102.73 102.73
b. Skilled Laborer 1 1 74.22 74.22
c. Unskilled Laborer 2 1 57.17 114.34

Sub - Total for A.2 - As Evaluated 291.29


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment
a. Cargo Truck (5T) 1 0.25 783.00 195.75
Minor Tools (10% of Labor) 29.13 29.13

Sub - Total for B.1 - As Submitted 224.88


B.2 Equipment
a. Cargo Truck (5T) 1 0.25 783.00 195.75
Minor Tools (10% of Labor) 29.13 29.13

Sub - Total for B.2 - As Evaluated 224.88


C.1 Total (A.1 + B.1) - As Submitted 516.17
C.2 Total (A.2 + B.2) - As Evaluated 516.17
D.1 Output per hour - As Submitted 1.00
D.2 Output per hour - As Evaluated 1.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 516.17
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 516.17

Name and Specification Unit Quantity Unit Cost Amount

F.1 Materials
a. Portland Cement bag 0.480 250.00 120.00
b. Sand cu.m. 0.025 1,307.36 32.68
c. Gravel cu.m. 0.050 1,307.36 65.37
d. Form Lumber, Good - 4 uses bd.ft 8.000 60.00 120.00
e. 3"Ø G.I. Pipe m. 3.100 433.33 1,343.32
f. Plate kg. 2 60.00 120.00
g. Bolts, 5mm Ø pc. 12 15.00 180.00
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1 4,800.00 4,800.00
i. Assorted CWN (1 kg./100 bd.ft. Of Lumber) kg. 0.08 80.00 6.40

Sub - Total for F.1 - As Submitted 6,787.77


F.2 Materials
a. Portland Cement bag 0.480 250.00 120.00
b. Sand cu.m. 0.025 1,307.36 32.68
c. Gravel cu.m. 0.050 1,307.36 65.37
d. Form Lumber, Good - 4 uses bd.ft 8.000 60.00 120.00
e. 3"Ø G.I. Pipe m. 3.100 433.33 1,343.32
f. Plate kg. 2 60.00 120.00
g. Bolts, 5mm Ø pc. 12 15.00 180.00
h. Sign Face, 3mm thk. Aluminum Sheet pc. 1 4,800.00 4,800.00
i. Assorted CWN (1 kg./100 bd.ft. Of Lumber) kg. 0.08 80.00 6.40

Sub - Total for F.2 - As Evaluated 6,787.77


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 7,303.94
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 7,303.94
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% of G.1 730.39
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% of G.2 730.39
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 584.32
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 584.32
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 430.93
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 430.93
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 9,049.58
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 9,049.58

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 607(3)b Internally Illuminated (Solar) Pavement Levelled Marker/Stud Flush
Type
Unit of Measurement : ea.
Output per hour - As Submitted : 8.00
Output per hour - As Evaluated : 8.00

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor

a. Foreman 1 1 102.73 102.73


b. Skilled Laborer 2 1 74.22 148.44
c. Unskilled Laborers 2 1 57.17 114.34

Sub - Total for A.1 - As Submitted 365.51


A.2 Labor

a. Foreman 1 1 102.73 102.73


b. Skilled Laborer 2 1 74.22 148.44
c. Unskilled Laborers 2 1 57.17 114.34

Sub - Total for A.2 - As Evaluated 365.51


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment
a. Drilling Machine / Hammer, CP-55A 1 0.40 185.00 74.00
b. Demolition / Chipping Hammer (Breaker) TL700-AV 1 0.35 129.38 45.28
c. Portable Air Compressor (Diesel Engine), 15-35CF 1 0.25 246.00 61.50
d. Generator Set, 5 kVa 1 1.00 134.79 134.79
e. Cargo Truck (2-5 MT) 1 0.25 783.00 195.75
Minor Tools (10% of Labor Cost) 36.55 36.55

Sub - Total for B.1 - As Submitted 547.87


B.2 Equipment
a. Drilling Machine / Hammer, CP-55A 1 0.40 185.00 74.00
b. Demolition / Chipping Hammer (Breaker) TL700-AV 1 0.35 129.38 45.28
c. Portable Air Compressor (Diesel Engine), 15-35CF 1 0.25 246.00 61.50
d. Generator Set, 5 kVa 1 1.00 134.79 134.79
e. Cargo Truck (2-5 MT) 1 0.25 783.00 195.75
Minor Tools (10% of Labor Cost) 36.55 36.55

Sub - Total for B.2 - As Evaluated 547.87


C.1 Total (A.1 + B.1) - As Submitted 913.38
C.2 Total (A.2 + B.2) - As Evaluated 913.38
D.1 Output per hour - As Submitted 8.00
D.2 Output per hour - As Evaluated 8.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 114.17
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 114.17
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. Solar Pavement Leveled Marker/Stud, Model MS-127,
pc. 1.00 8,500.00 8,500.00
137mm dia. x 45mm depth
b. Freight and Handling Cost, LU pc. 1.00 100.00 100.00
c. Concrete Epoxy "A" & "B" gal. 0.07 2,500.00 177.50
d. Diamong Core Bit pc. 0.003 1,925.00 5.78
e. Demolition/Chipping Hammer pc. 0.002 2,750.00 5.50
Miscellaneous (5% Materials Cost) 1 439.44 439.44

Sub - Total for F.1 - As Submitted 9,228.22


F.2 Materials
a. Solar Pavement Leveled Marker/Stud, Model MS-127, pc. 1.00 8,500.00 8,500.00
b. Freight and Handling Cost, LU pc. 1.00 100.00 100.00
c. Concrete Epoxy "A" & "B" gal. 0.07 2,500.00 177.50
d. Diamong Core Bit pc. 0.003 1,925.00 5.78
e. Demolition/Chipping Hammer pc. 0.002 2,750.00 5.50
Miscellaneous (5% Materials Cost) 1 439.44 439.44

Sub - Total for F.2 - As Evaluated 9,228.22


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 9,342.39
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 9,342.39
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% of G.1 934.24
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% of G.2 934.24
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 747.39
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 747.39
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 551.20
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 551.20
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 11,575.22
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 11,575.22

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 612(1) Reflectorized Thermoplastic Pavement Markings White


Unit of Measurement : sq.m.
Output per hour - As Submitted : 25.00
Output per hour - As Evaluated : 25.00

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor

a. Foreman 1 1 102.73 102.73


b. Skilled Laborer 2 1 74.22 148.44
c. Unskilled Laborers 6 1 57.17 343.02

Sub - Total for A.1 - As Submitted 594.19


A.2 Labor

a. Foreman 1 1 102.73 102.73


b. Skilled Laborer 2 1 74.22 148.44
c. Unskilled Laborers 6 1 57.17 343.02

Sub - Total for A.2 - As Evaluated 594.19


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment
a. Cargo Truck/Delivery Truck (2-5 mt) 1 1 783.00 783.00
b. Application Machine 1 1 93.75 93.75
c. Kneading Machine 1 1 187.50 187.50
Minor Tools (10% of Labor Cost) 59.42 59.42

Sub - Total for B.1 - As Submitted 1,123.67


B.2 Equipment
a. Cargo Truck/Delivery Truck (2-5 mt) 1 1 783.00 783.00
b. Application Machine 1 1 93.75 93.75
c. Kneading Machine 1 1 187.50 187.50
Minor Tools (10% of Labor Cost) 59.42 59.42

Sub - Total for B.2 - As Evaluated 1,123.67


C.1 Total (A.1 + B.1) - As Submitted 1,717.86
C.2 Total (A.2 + B.2) - As Evaluated 1,717.86
D.1 Output per hour - As Submitted 25.00
D.2 Output per hour - As Evaluated 25.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 68.71
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 68.71
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. Thermoplastic Paint (White) bags 0.3250 1,565.00 508.63
b. Glass Beads bags 0.033 1,250.00 41.25
c. Primer L 0.12 330.00 39.60
d. LPG (50 kg) cyl 0.004 4,100.00 16.40
e. LPG (12 kg) cyl 0.002 984.00 1.97
f. Calsumine kg 0.125 100.00 12.50
Miscellaneous (5% Materials Cost) 1 31.02 31.02

Sub - Total for F.1 - As Submitted 651.37


F.2 Materials
a. Thermoplastic Paint (White) bags 0.3250 1,565.00 508.63
b. Glass Beads bags 0.033 1,250.00 41.25
c. Primer L 0.12 330.00 39.60
d. LPG (50 kg) cyl 0.004 4,100.00 16.40
e. LPG (12 kg) cyl 0.002 984.00 1.97
f. Calsumine kg 0.125 100.00 12.50
Miscellaneous (5% Materials Cost) 1 31.02 31.02

Sub - Total for F.2 - As Evaluated 651.37


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 720.08
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 720.08
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% of G.1 72.01
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% of G.2 72.01
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 57.61
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 57.61
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 42.49
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 42.49
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 892.19
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 892.19

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

CONVERGE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive Maintenance -
Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568, K0130+624 - K0130+827
Lucena City, Quezon

DETAILED UNIT PRICE ANALYSIS (DUPA)


FORM-POW-2015-01D-00

Item no./Description : 618(1) Reflectorized Thermoplastic Rumble Strips


Unit of Measurement : sq.m.
Output per hour - As Submitted : 25.00
Output per hour - As Evaluated : 25.00

No. of No. of
Designation Hourly Rate Amount (Php)
Person/s Hour/s
A.1 Labor

a. Foreman 1 1 102.73 102.73


b. Skilled Laborer 2 1 74.22 148.44
c. Unskilled Laborers 6 1 57.17 343.02

Sub - Total for A.1 - As Submitted 594.19


A.2 Labor

a. Foreman 1 1 102.73 102.73


b. Skilled Laborer 2 1 74.22 148.44
c. Unskilled Laborers 6 1 57.17 343.02

Sub - Total for A.2 - As Evaluated 594.19


No of No. of
Name and Capacity Hourly Rate Amount (Php)
Unit/s Hour/s
B.1 Equipment
a. Cargo Truck/Delivery Truck (2-5 mt) 1 1 783.00 783.00
b. Application Machine 1 1 93.75 93.75
c. Kneading Machine 1 1 187.50 187.50
Minor Tools (10% of Labor Cost) 1 59.42 59.42

Sub - Total for B.1 - As Submitted 1,123.67


B.2 Equipment
a. Cargo Truck/Delivery Truck (2-5 mt) 1 1 783.00 783.00
b. Application Machine 1 1 93.75 93.75
c. Kneading Machine 1 1 187.50 187.50
Minor Tools (10% of Labor Cost) 1 59.42 59.42

Sub - Total for B.2 - As Evaluated 1,123.67


C.1 Total (A.1 + B.1) - As Submitted 1,717.86
C.2 Total (A.2 + B.2) - As Evaluated 1,717.86
D.1 Output per hour - As Submitted 25.00
D.2 Output per hour - As Evaluated 25.00
E.1 Direct Unit Cost (C.1 ÷ D.1) - As Submitted 68.71
E.2 Direct Unit Cost (C.2 ÷ D.2) - As Evaluated 68.71
Name and Specification Unit Quantity Unit Cost Amount
F.1 Materials
a. Thermoplastic Paint (White) bags 0.3250 1,565.00 508.63
b. Glass Beads bags 0.033 1,250.00 41.25
c. Primer L 0.12 330.00 39.60
d. LPG (50 kg) cyl 0.004 4,100.00 16.40
e. LPG (12 kg) cyl 0.002 984.00 1.97
f. Calsumine kg 0.125 100.00 12.50
Miscellaneous (5% Materials Cost) 1 31.02 31.02

Sub - Total for F.1 - As Submitted 651.37


F.2 Materials
a. Thermoplastic Paint (White) bags 0.3250 1,565.00 508.63
b. Glass Beads bags 0.033 1,250.00 41.25
c. Primer L 0.12 330.00 39.60
d. LPG (50 kg) cyl 0.004 4,100.00 16.40
e. LPG (12 kg) cyl 0.002 984.00 1.97
f. Calsumine kg 0.125 100.00 12.50
Miscellaneous (5% Materials Cost) 1 31.02 31.02

Sub - Total for F.2 - As Evaluated 651.37


G.1 Direct Unit Cost (E.1 + F.1) - As Submitted 720.08
G.2 Direct Unit Cost (E.2 + F.2) - As Evaluated 720.08
H.1 Overhead, Contingencies & Miscellaneous (OCM) - As Submitted 10% of G.1 72.01
H.2 Overhead, Contingencies & Miscellaneous (OCM) - As Evaluated 10% of G.2 72.01
I.1 Contractor's Profit (CP) - As Submitted 8% of G.1 57.61
I.2 Contractor's Profit (CP) - As Evaluated 8% of G.2 57.61
J.1 Value Added Tax (VAT) - As Submitted 5% of (G.1+ H.1 + I.1) 42.49
J.2 Value Added Tax (VAT) - As Evaluated 5% of (G.2+ H.2 + I.2) 42.49
K.1 Total Unit Cost - As Submitted (G.1 + H.1 + I.1 + J.1) 892.19
K.2 Total Unit Cost - As Evaluated (G.2 + H.2 + I.2 + J.2) 892.19

Prepared by: Checked/Reviewed by:

RAINIER D. PALAGANAS JUMEL B. REYES


Engineer II Engineer II
Maintenance Section Construction Section

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

HAULING DISTANCE

Project Name : CONVERGENCE AND SPECIAL SUPPORT PROGRAM: Special Road Fund -
Motor Vehicle User's Charge (MVUC) as per R.A. 11239, Preventive
Maintenance - Primary Roads, MSR Diversion Rd - K0129+1006 - K0130+568,
K0130+624 - K0130+910
Location : Lucena City, Quezon

SARIAYA QUARRY
MAP SHOWING THE SOURCE OF MATERIAL TO THE POINT OF REFERENCE (PROJECT SITE), L= 14.80 KM

MAP SHOWING DPWH QUEZON II DEO OFFICE TO THE POINT OF REFERENCE (PROJECT SITE), L= 5.00 KM

Prepared by:

RAINIER D. PALAGANAS
Engineer II

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)


lOMoARcPSD|35623485

UNIT COST ANALYSIS FOR AGGREGATES

Item Description : Aggregates


Assumed Quantity : 100.00 cu.m.
Source : Sariaya Quarry

CONVERGENCE AND SPECIAL SUPPORT PROGRAM: Special Road Fund - Motor Vehicle User's
Project : Charge (MVUC) as per R.A. 11239, Preventive Maintenance - Primary Roads, MSR Diversion Rd -
K0129+1006 - K0130+568, K0130+624 - K0130+910

Lucena Sta. K132+000.00 (POBLACION)


A
Total Hauling Distance : 14.80 km
Terrain Condition : **With 5km free hauling distance
Flat/ Rolling, Paved : 9.80 km **From Source of Material to Point of Reference
Flat/ Rolling, Paved : 0.00 km **From Point of Reference to Project Site if Applicable
(Note: Distance established was based on Google Earth)
Working Hours : 8.00 hours

TIME MOTION ANALYSIS :

Flat/ Rolling, Paved :


Speed when Loaded = 32.5 kph
Speed when empty = 47.5 kph
9.80 km x 60 mins/hr
Time when loaded = = 18.09 mins
32.5 kph
9.80 km x 60 mins/hr
Time when empty = = 12.38 mins
47.5 kph

Flat/ Rolling, Paved :


Speed when Loaded = 32.5 kph
Speed when empty = 47.5 kph
0.00 km x 60 mins/hr
Time when loaded = = 0.00 mins
32.5 kph
0.00 km x 60 mins/hr
Time when empty = = 0.00 mins
47.5 kph

Loading Time = 3 mins


Unloading Time = 2 mins
Allowance for Delay:
10% of Total Time = 3.55 mins
TOTAL CYCLE TIME = 39.02 mins/trip

No. of Dumptrucks Used: 1 Dumptruck


Capacity of Dumptruck : 10 cu.m
No. of trips for DT per 8.00 hr/day x 60 mins/hr
= = 12.30 trips/day
day 39.02 mins/trip
Dumptruck Daily Output = 10 cu.m/trip x 12.30 trips/day = 123.00 cu.m./day
No. of Dump Trucks Used = 1 DT x 123.00 cu.m./day = 123.00 cu.m./day
No. of Days of 100 cu.m.
= = 0.81 days
Dumptruck 123.00 cu.m./day
Equipment Used
(Rates per Day) (Days)
1 Dumptruck = 11360 x 0.81 = 9,235.77 Php
Sub Total = 9,235.77 Php
Hauling Cost 9,235.77 Php
= = 92.36 Php/ cu.m.
per cu.m. 100 cu.m.

Baranggay Municipal Total Cost up to Project


ITEM Pick Up Price Hauling Cost
Passway Passway Site
3/4 1,200.00 5.00 10.00 92.36 1,307.36
G-1 1,150.00 5.00 10.00 92.36 1,257.36
Sand 1,200.00 5.00 10.00 92.36 1,307.36
Filler Materials 515.00 5.00 10.00 92.36 622.36
Boulder 830.00 5.00 10.00 92.36 937.36
Aggregates
Subbase 600.00 5.00 10.00 92.36 707.36
Course
Common
118.00 5.00 10.00 92.36 225.36
Borrow

Prepared by:

RAINIER D. PALAGANAS
Engineer II

Downloaded by Mark Louise Olandres (engrmark.official@gmail.com)

You might also like