Professional Documents
Culture Documents
PMP Session Day 2
PMP Session Day 2
PMP Session Day 2
Define Activities
Process of
Identifying the specific actions to be performed
to produce project deliverables at the lowest
level in WBS (work packages).
Therefore we decompose work packages into
activities needed to complete them!
32
0
Project Time Management
Activities
32
3
Project Time Management
32
8
Project Time Management “Define Activities”
TEMPLATES
33
2
Define Activities process: Outputs
ACTIVITY LIST
Consists of all the schedule activities to be
performed to complete the project.
Activity attributes
Extend the description of each activity by
identifying multiple components associated with
each activity.
Please note: components for each activity evolve
over time. During initial stages of the project they
include: activity ID, WBS ID, and activity name.
33
4
Define Activities process: Outputs
Activity attributes
When completed they may include:
1) activity codes, activity descriptions,
2) predecessor, successor, logical relationships,
3) leads and lags,
4) resource requirements,
5) imposed dates,
6) Constraints, and assumptions.
33
5
Project Time Management
Sequence Activities
Sequence Activities
Sequence Activities
34
3
Project Time Management
PDM
precedence relationships
Finish to Start
Finish to start
The successor activity
A B can begin only when
predecessor activity
Furniture Employee completes.
move-in move-in This is the most
commonly used
35 relationship.
0
Project Time Management
PDM
Finish to Finish precedence relationships
Finish to finish
A B The successor activity can
complete only when
predecessor completes.
Lay asphalt Paint
parking
35 lines
1
Project Time Management
PDM
Start to Finish precedence relationships
A B Start to finish
The successor can
finish only when
Test new Phase-out predecessor starts.
System Old system This relationship is
35 rarely used.
3
Project Time Management
PDM
dependencies such as Start
to start, finish to finish, and
start to finish have not been
implemented consistently.
Schedule Network
TOOLS &
templates
TECHNIQUES SIMILAR networks from your past
Precedence projects can be used to expedite
diagramming preparing current project’s network
method (PDM)
Schedule network
MAY use it for the entire project or
templates for a portion of it. The companies
Dependency doing same type of projects over the
determination years have standardized the
Applying leads and
lags
networks based on their experience.
Portions of the such schedule
network diagrams are called
35 FRAGMENT NETWORK or
5 SUBNETWORK.
Project Time Management
1) Mandatory dependencies
TOOLS & (hard logic)
TECHNIQUES
determined by the type of work being
Precedence performed.
diagramming
method (PDM) offer physical limitations as the nature of
Schedule network work itself dictates the order of activities.
templates
Dependency
determination
In the Century Cotton Mills example,
Applying leads and
you can’t prime the walls until
lags scraping is done before.
In ECE Industries example, you can
not make control board until printed
35 circuit boards are populated and wave-
7 soldered.
Project Time Management
3) External dependencies
TOOLS & are external to the project and
TECHNIQUES
depend on relationship between
Precedence
diagramming project activities and non-
method (PDM) project activities.
Schedule network
templates Examples
Dependency
determination 1) Testing schedule activity on a
Applying leads and
lags software project may depend
on delivery of hardware from
35 an outside source
9
Project Time Management
3) External dependencies
TOOLS & are external to the project and
TECHNIQUES
depend on relationship between
Precedence
diagramming project activities and non-
method (PDM) project activities.
Schedule network
templates Examples
Dependency
determination 2) Governmental environmental
Applying leads and
lags forecasts may need to be
held before site preparation
36 on a construction project.
0
Project Time Management
PROJECT Schedule
OUTPUTS NETWORK DIAGRAMS
Project Network Schematically show project
Diagrams activities along with their
Project documents dependencies
updates
May be drawn manually or on
computer, using PDM or ADM
Sequence Activities
PROJECT NETWORK DIAGRAMS
OUTPUTS A summary description of
Project Network sequencing approach accompanies
Diagrams them
Project documents
updates
Unusual sequences, if any, are
properly narrated
A network diagram is traditionally
known as PERT Chart, however
PERT (program evaluation and
review technique was a particular
type of network diagram using
36 weighted average.
5
Project Time Management
Sequence Activities
Project document ACTIVITY LIST UPDATES
updated: While preparing network diagrams,
1) Activity list updates we may discover some instances
2) Activity attributes where certain activities must be
divided or refined in order to show
updates
3) Risk register correct logical dependencies.
updates
This leads to activity list updates to
36 include approved changes.
6
Project Time Management
36
8
Project Time Management
WHAT TYPE
FOR EACH ELEMENT AT LOWEST LEVEL OF WBS OF PHYSICAL
RESOURCES
ARE
REQUIRED?
WHEN
ARE THEY
REQUIRED?
Estimate Activity Resources
IN WHAT
QUANTITIES?
TO PERFORM PROJECT ACTIVITIES
36
9 Closely coordinated with cost estimating!
Project Time Management
Management of resources is as
important as managing
37 time, cost, quality and scope
0
Project Time Management
ESTIMATING FUNDAMENTALS?
You should have properly defined scope (WBS).
Estimate Activity
Durations
ESTIMATING FUNDAMENTALS?
ESTIMATING FUNDAMENTALS?
You must be aware of all the potential risks that may
have negative or positive impact on your estimates. This
is a grey area in many organizations.
We seem to have enough time to do rework than to do it
right the first time. Risks are not fully identified in the
39 beginning. They are taken to be a way of life.
0
Project Time Management
ESTIMATING FUNDAMENTALS?
Who should provide inputs for estimates of
duration? In many organizations everybody seem to
offer them!
It is highly risky to accept them from just anybody.
They should be provided only by those people or the
group who are well conversant with the nature of the
39 concerned schedule activity.
2
Project Time Management
ESTIMATING FUNDAMENTALS?
ESTIMATING FUNDAMENTALS?
DURATION is the time required for completing an
activity. Estimating this duration is actually
approximating how many work periods (hours, days,
weeks, months), it will take.
In real life, while performing an activity, you have non-
work periods also, like Sundays and other holidays.
Your estimation should not ignore them. You need to
39 use both Project calendar and Schedule activity
5 resource calendar!
Project Time Management
ESTIMATING FUNDAMENTALS?
39
6
Project Time Management
39
9
Estimate
Activity
Durations
Project Time Management
Expert judgment
team members rely on their knowledge and
experience, but these estimates can be very
risky:
1) Many factors influence activity durations,
such as resource capability, resource
levels required/assigned, etc., that need to
be carefully considered.
2) May be subject to bias, not based on
scientific means.
40 3) Not based on documented data but simply
7 on recall.
“Estimate Activity Durations”
TOOLS & TECHNIQUES
Expert judgment
Therefore, expert judgment must be combined
with historical information and use as many
experts as possible.
Expert judgment, guided by historical information,
can provide:
1) Duration estimate or recommended maximum
activity durations from similar past projects.
2) Knowledge whether to combine methods of
40 estimating and how to reconcile differences.
8
“Estimate Activity Durations”
TOOLS & TECHNIQUES
Analogous estimating
THE actual duration of a similar activity completed on
a previous project to determine the duration of same
type of activity on the current project.
USED only in early phases of the project (initiation)
when we don not have detailed information about the
project. Uses historical info and expert judgment!
When analogous estimating is most reliable?
• When previous projects activities are really similar, not
just apparently similar
• The people making this kind of estimate have
40 necessary expertise
9
“Estimate Activity Durations”
TOOLS & TECHNIQUES
parametric estimating
Uses a statistical relationship between historical
data and other variables (square footage in
construction) to calculate an estimate for activity
parameters like cost, budget, and duration.
on a Design Project:
1) number of drawings X labor
hours per drawing
41 2) cable installation in meters X
1 labor hours per meter
“Estimate Activity Durations”
TOOLS & TECHNIQUES
Three-point estimates
Estimate Activity 1) Most likely: duration considering
Durations all resources with their
TOOLS & productivity, availability,
TECHNIQUES dependencies on their
participants, and interruptions.
2) Optimistic: best case of most
likely.
3) Pessimistic: worst case of most
41
likely.
5
“Estimate Activity Durations”
TOOLS & TECHNIQUES
Three-point estimates
The concept originated with the Program Evaluation
and Review technique (PERT). PERT uses three
estimates to define an approximate range for activity
duration: Most Likely, Optimistic, and Pessimistic.
Then, calculates an EXPECTED (tE) activity
duration using a weighted average of three
estimates:
t E = tO + 4 tM + tP
41
6
6
Project Time Management
Reserve analysis
Estimate Activity
an additional time (known as time
Durations buffer, reserve, or contingency)
TOOLS & added to the activity duration or
TECHNIQUES elsewhere in the schedule as
recognition of schedule risk:
1. A percentage of estimated activity
duration, a fixed number of work
periods, or
41 2. As developed by quantitative
7 schedule risk analysis (good)
Project Time Management
Reserve analysis
Please remember!
Estimate
Activity A contingency reserve can be used
Durations completely or PARTIALLY , OR
LATER REDUCED OR
ELIMINATED as you progress and
get more precise information
about the project. Contingency
reserve is also documented with
41 other related data and
8 assumptions!!!
Project Time Management
2. Student syndrome
Work is attended only when the deadline
41
dangles like Damocles’ sword over our
9 head.
Project Time Management
42
2
Project Time Management
Develop Schedule
“THE KEY WORDS ARE START AND
FINISH DATES!”
Schedules show the timing for work elements
start and finish dates – and denote when events
and milestones take place.
Therefore, schedule development is the process
42 of determining start and finish dates for project
6 activities.
Project Time Management
Schedule Development
Develop Schedule
1
Project Time Management
4 8 5 7 8
D E G H C
Start 6 7 5 End
A F B
D, E, G, H, C = 32 Weeks
A, F, B = 18 Weeks
Paths
44 D, F, B = 16 Weeks
D, F, G, H, C = 31 Weeks
6 A, F, G, H, C = 33 Weeks
Project Time Management
PERT
Such projects are contracted as new developments unfold
and before problems in technology, materials, and processes
are identified and resolved.
= O + 4M + P / 6
2. STANDARD DEVIATION of an activity duration (SD)
= (P – O) / 6
3. VARIABILITY IN THE ACTIVITY COMPLETION TIME (Activity Variance, V)
45 V = (P – O / 6 )^2
7
Project Time Management
KEY:
PERT: THREE TIME ESTIMATES (0, M, P)
Exp. Time, V
2 6
( 6, 15, 30 )
1 7 8
( 1, 4, 7 )
45 3 ( 3, 12, 21) 4 ( 3, 4, 5 ) 5
8
Project Time Management
KEY:
PERT: THREE TIME ESTIMATES (0, M, P)
Exp. Time, V
( 6, 15, 30 )
16, 16.00
1 7 8
( 1, 4, 7 )
4, 1.00
45 3 ( 3, 12, 21) 4 ( 3, 4, 5 ) 5
9 12, 9.00 4, 0.11
Project Time Management
46
9
Project Time Management
47 Slide 2
3
“Develop Schedule”- Tools & Techniques
Resource leveling
WE have a schedule of activities.
Now, it’s time to plug in resources
because :
Techniques like CPM and PERT did
not consider resource availability
and produced a preliminary early-
start schedule that needs more
resources during certain times than
available, or needs unmanageable
47 alterations in resource levels.
6
“Develop Schedule”- Tools & Techniques
Resource leveling
WE have a schedule of activities.
Now, it’s time to plug in resources
because :
We will also have to adjust our
schedule if we find any resource
constraints to our schedule of
activities made so far using
mathematical analysis techniques.
47
7
“Develop Schedule”- Tools & Techniques
Resource leveling
process of adjusting resource
utilization on your project to match
with real resource availability.
OFTEN INVOLVES:
Allocate scarce resources to critical
path activities first.
Move an activity in time to take
advantage of a period of under-
allocation elsewhere in the project.
47
8
“Develop Schedule”- Tools & Techniques
Resource leveling
process of adjusting resource
utilization on your project to match
with real resource availability.
OFTEN INVOLVES:
Replace the resources that are not
over-allocated during the same
timeframe.
Increase the duration of an activity
while applying the same total effort.
47 Resource leveling generally extends
9 schedule. It can change CP.
“Develop Schedule”- Tools & Techniques
Resource leveling
Other techniques in an event of
critical or limited resource
availability:
Utilization of extended hours
Productivity increase of resources
Fast tracking
Reverse resource allocation
Critical chain method modifies project
schedule to account for limited
48 resources.
0
“Develop Schedule”- Tools & Techniques
Resource leveling
Some projects have can have a finite and critical
resource. In such cases, the resource is scheduled in
reverse from the project ending date. It is called
REVERSE RESOURCE ALLOCATION
SCHEDULING!
It may not result in an optimal project schedule.
48
1
“Develop Schedule”- Tools & Techniques
Resource leveling
Resource leveling produces a
RESOURCE-LIMITED SCHEDULE, or
RESOURCE-CONSTRAINED SCHEDULE!
48
2
“Develop Schedule”- Tools & Techniques
48
3
“Develop Schedule”- Tools & Techniques
48
5
“Develop Schedule”- Tools & Techniques
Scheduling Tool
Schedule data and information is
compiled into the schedule model
for the project.
We may use the schedule model
tool and its supporting data along
with manual methods or project
management software:
to perform schedule network
analysis for generating the project
48 schedule.
6
“Develop Schedule”- OUTPUTS
Project schedule
MAY be displayed in summary form for the whole project,
or in detailed form for various levels of WBS.
SCHEDULE FORMATS
1. Project network diagrams (display project
logic and critical path activities).
2. Bar charts or Gantt charts (depict activity
start and finish dates, estimated durations,
and occasionally dependencies).
48 3. Milestone charts (show start or finish of
7 major deliverables or key external interfaces).
“Develop Schedule”- OUTPUTS
48 WRITE
MANUAL
8
“Develop Schedule”- OUTPUTS
Activity A
Activity B
Activity C
Activity D
0
“Develop Schedule”- OUTPUTS
Data date
49
1
“Develop Schedule”- OUTPUTS
Data date
49
2
“Develop Schedule”- OUTPUTS
Schedule data
Supporting data for the project
schedule
Includes (at least)
Schedule milestones
Schedule activities
Activity attributes
All constraints and assumptions
49 Amount of additional data varies by
3 application area.
“Develop Schedule”- OUTPUTS
Schedule data
Supporting data for the project
schedule
Frequently supplied supporting
details:
Resource requirements by time period
as “Resource Histogram”
Alternative schedules (best case, worst
case, resource not leveled, resource
49 leveled, with/without imposed dates)
4 Schedule contingency reserves
Project Human Resource Management
HR HR
HR
HR
HR HR
49
8
HR
THE CHALLENGES
Most project managers have considerably more
responsibility than authority, so they need different
skills and approaches than traditional managers.
Stakeholders often have different needs and
perspectives, but project manager has to balance
them, and yet achieve project objectives.
Generally, project staff comes from various
functional areas and do not report to the project
49 manager, but he has to get work done by them.
9
HR
THE CHALLENGES
Project manger’s role is so central that without it
there would be no such thing as project
management. But he/she has to wear lot of different
hats, many at the same time. He/she has to be an
integrator, communicator, decision maker, motivator,
entrepreneur, and change agent.
The Project Manager has to make most effective use
of all project stakeholders- sponsor, customer,
functional managers, individual contributors, etc.
50 Look at his task!
0
HR
THE CHALLENGES
Managing people on projects involves:
Key General Management Skills, like leading,
communicating, negotiating, problem solving, and
influencing organization.
Dealing with individuals- delegating, motivating,
coaching, mentoring, etc.
Dealing with groups- team building, solving conflicts,
etc.
Administering the human resource function. May
also have the responsibility of HR redeployment and
50 release (depends on where they belong).
1
HR
THE CHALLENGES
Consists of:
processes needed to organize and manage the project
team, the people who are assigned roles and
responsibilities for completing the project.
Apart from assigning roles, we must involve the team
members in planning and decision making. WHY?
Early involvement of team members ADDS
EXPERTISE DURING PLANNING PROCESSES
AND ALSO ENSURES COMMITMENENT!
50
4
HR
50
7
HR
Project HR Management
Develop Human
Enterprise environmental
Resource Plan
INPUTS
factors
Definition of roles and responsibilities on the
project is evolved with an understanding of :
1) The ways that existing
organizations will be involved
2) How the technical disciplines will
interact with each other
3) How people currently will interact
50 with one another
8
HR
Project HR Management
Project HR Management
Project HR Management
Project interfaces
REAL LIFE SCENARIO
Project HR Management
Project HR Management
Develop Human
Technical interfaces
Resource Plan
INPUTS 3) Whether transitions from one
life cycle phase to another
pose unique challenges
TECHNICAL INTERFACES
EXIST BETWEEN
PHASES AS WELL AS WITHIN
PHASES
51
3
HR
Project HR Management
Project interfaces
REAL LIFE SCENARIO
Project HR Management
Project HR Management
Project HR Management
Project HR Management
51
8
HR
Develop Human
Project HR Management Resource Plan
Organization structure
ORGANIZATION STRUCTURE CONSTRAINTS
• If you work in a functional organization, you will face lot
of difficulties in acquiring resources from iron walls of
various functional departments.
• Here, the authority over resources lies with functional
managers. You are called project manager, but in fact
you just and an expeditor.
• You are more comfortable in strong matrix because you
Project HR Management
Develop Human
Resource Plan Collective bargaining
INPUTS
agreements
entered between the organizations and
labor/other employee groups detail
require certain roles and reporting
relationships.
Project HR Management
Develop Human
Resource Plan
INPUTS
Economic conditions
Hiring, freezes, reduced training
funds, or lack of travel budget
are examples that can limit
staffing options. entered
between the organizations and
52
1
HR
Project HR Management
Project HR Management
Project HR Management
Project HR Management
Project HR Management
Project HR Management
Organization chart
Project reporting relationships are
graphically displayed.
Depending on the project needs,
you can make it formal or
informal; broadly-detailed or
highly-detailed.
INR 2 billion Reliance Power Dadri
Project, has mind-boggling
organization chart for about 7000
people.
52
7
HR
Develop Human
Project HR Management Resource Plan
OBS
Organization breakdown
Structure (OBS)
WBS shows how project deliverables
are broken down into work packages
and becomes one way to depict high-level
areas of responsibility. OBS looks similar
but arranged according to departments,
units, or teams: the project activities or
work packages listed under each
52 Department. This helps each operational
8 department to see its portion of OBS.
HR
Develop Human
Project HR Management Resource Plan
Project HR Management
Text-oriented format
Text-oriented format
Role Team member responsibilities that
require detailed descriptions can be
written here in outline form:
Responsibilities
Responsibilities, authority,
Competencies, qualifications
This format is also called:
Position Descriptions and Role-
Authority Responsibility-Authority forms.
Make great templates if updated throughout
53 current project!
2
HR
Project HR Management
Develop Human
Resource Plan
Other sections of project
INPUTS management plan
We consider team member
responsibilities detailed in other sections
of the project management plan:
1) Risk register lists risk owners
2) Communication management plan lists
people responsible for communication
activities
3) Quality plan lists people responsible for
quality assurance and quality control
53 activities
3
HR
Project HR Management
Develop Human
Resource Plan
Networking
For effectiveness of staffing management
INPUTS plan options, we must understand
political and interpersonal factors that
may impact them. So, we need to use
networking, such as:
1) Proactive correspondence
2) Luncheon meetings
3) Informal conversations
4) Trade conferences
Networking pays from start of the project till
53 its completion!
4
HR
Project HR Management
Develop Human
Resource Plan Organization theory (OB)
INPUTS Informs us on the ways people,
teams and organizations behave.
We must use proven principles to
shorten the time needed to arrive
at outputs of HR planning.
It makes planning more effective.
1) Goal-setting
2) Group Dynamics
53
5
HR
53
8
HR
54
0
HR
90
80
Staff hours
70
60
50
40
30
20
10
0
1st Qtr 2nd Qtr 3rd Qtr 4th Qtr
54
Resource Usage Staff hours
5
HR
54
7
HR
Project
Procurement Management
55
1
Project Procurement Management
CONTRACT
CONTRACT
CONTRACT
CONTRACT
CONTRACT
Determines
Plan Procurements
Considers
1. “whether to procure?” (make or buy!)
2. “how to procure?” (procurement methods)
3. “what to procure?” (description of products)
4. “how much to procure?” (quantity)
5. “when to procure?” (procurement schedule)
6. potential subcontractors (prospective sellers)
57
(Consideration of potential sellers gives some degree of
0 influence/ control to the buyer over contracting decisions)
Plan Procurements: PROCESS OVERVIEW
58
2
Project Procurement Management
Plan procurements
Make-or-buy analysis
TOOLS & General management technique
TECHNIQUES used to decide whether a particular
Make-or-buy product/service can be produced
Analysis (COST EFFECTIVELY) by the project
Expert Judgment
Contract Type
team or need to be purchased
Selection
Budget constraints are factored in
Considers both direct and indirect
costs
58 example
3
Project Procurement Management
Plan procurements
Make-or-buy analysis
TOOLS & example
TECHNIQUES Buy-side of analysis includes actual
Make-or-buy
Analysis 1) Direct out-of-pocket costs to
Expert Judgment
Contract Type procure the product, and
Selection 2) Indirect costs of managing the
purchasing process.
58
4
Project Procurement Management
Plan procurements
Make-or-buy analysis
TOOLS &
TECHNIQUES
Reflects
Make-or-buy 1) Perspective of the performing
Analysis organization, and
Expert Judgment 2) Immediate project needs
Contract Type
Selection
3) Long range strategy
58 examples
5
Project Procurement Management
Make-or-buy analysis
example
TOOLS & Buying an item (say material
TECHNIQUES
handling equipments or computers)
Make-or-buy
or leasing it may or may be cost
Analysis
Expert Judgment effective on the current project.
Contract Type
Selection
But, if performing organization
Requires it on regular basis and
buys the item, then the part of the
purchase cost apportioned to the
58 project may be less than the leasing
6 cost. (Margin Analysis helps allocate
such costs)
Project Procurement Management
Expert judgement
TOOLS & What expert judgment is needed?
TECHNIQUES 1) Expert technical judgment to access
Make-or-buy inputs and outputs from this process.
Analysis
2) Expert purchasing judgment to develop
Expert
Judgment or modify evaluation criteria.
Contract Type 3) Expert legal judgment to make terms and
Selection conditions for non-standard procurement
items.
4) Such technical, business and legal
judgment can also be applied to other
58 aspects of procurement management
8 processes.
Project Procurement Management
Example
Contract INR 5,500,000
Incentive INR 50,000 for every month
59 for finishing contracted work early
2
Project Procurement Management
59
6
Project Procurement Management
59
9
Project Procurement Management
EXAMPLE
Contract = Costs + fee, say INR 500,000 + INR 50,000 (for
60 every month the project is earlier than agreed)
0
Project Procurement Management
HANDS-ON EXERCISE
60
1
Project Procurement Management
DATA
1) Estimate cost INR 630,000, fee INR 75,000
60
2
Project Procurement Management
SOLUTION
Step 1
Fee = INR 630,000 – INR 600,000
= INR 30,000 x 20%
= INR 6,000
Final fee = INR 75,000 target fee + INR 6,000
= INR 77,000
Step 2
Final price = INR 600,000 + 77,000
= INR 677,000
60
3
Project Procurement Management
60
5
Project Procurement Management
Procurement management
OUTPUTS
plan
Procurement Describes
Management Plan how the procurement processes shall
Procurement
Statements of work be managed from developing procurement
Make-or-buy decisions documents through contract closure
Procurement
documents Includes
Source Selection
1) Contract types for use
Criteria
Change requests 2) Who will make independent estimates
and if they are required as evaluation
60 criteria
7
Project Procurement Management
Make-or-buy decisions
Are obvious output.
May also include: Decisions to buy
insurance policies, performance
bond contracts! WHY? Answer: To
address some of the identified risks.
May be simple (short justification)
May be complex (iterative as subsequent
procurement activities may require a
61 different approach)
8
Project Procurement Management
Procurement documents
used to request proposals from
prospective sellers
Evaluation criteria
Source Developed and used to rate or
score Proposals
selection
1) FOR THE ITEMS READILY
criteria AVAILABLE FROM MANY
SELLERS
Evaluation Criteria limited to
purchase price. Purchase Price
means landed cost
62 ( cost of the item and ancillary
4 expenses, such as freight)
Project Procurement Management
Evaluation criteria
Developed and used to rate or score
Source Proposals
2) FOR A MORE COMPLEX PRODUCT
selection OR SERVICE
1) Understanding of need
criteria 2) Overall life cycle cost
3) Technical capability
4) Management approach
5) Financial capacity
6) Production capacity and interest
7) Business size and type
8) References
62 9) Intellectual property rights
10) Proprietary rights
5
Project Quality Management
62
7
Project Quality Management
63
0
Project Quality Management
THE CONCEPT
Quality is “the totality of characteristics of an entity
that bear on its ability to satisfy stated or implied
needs”.
IN OTHER WORDS, it is the degree to which a set
of inherent characteristics fulfill requirements.
Stated or implied needs, therefore, needs guide us
in developing project requirements.
63
6
Project Quality Management
THE CONCEPT
In project context, the key issue is converting
IMPLIED NEEDS INTO REQUIREMENTS- through
project scope management.
Quality therefore is conformance to requirements and
fitness for use.
This means you must produce what you promised to
63 produce and the product must be fit for use for which it
is meant.
7
Project Quality Management
THE CONCEPT
64
9
Project Quality Management
THE CONCEPT
PREVENTION OVER INSPECTION
THE COST OF PREVENTING MISTAKES IS
NORMALLY “MUCH LESS” THAN THE COST
OF CORRECTING THEM (DEMONSTRATED BY
INSPECTION)
65
0
Project Quality Management
THE CONCEPT
MANAGEMENT RESPONSIBILITY
success needs participation of all team members, but
it stays with the management to provide resources
required to succeed.
Deming suggested: as much as 85% of the cost of
65 quality is management problem
1
Project Quality Management
THE CONCEPT
MANAGEMENT RESPONSIBILITY
Deming suggested: once the quality issue has hit the
floor, or the worker level, the workers have little control
65
2
Project Quality Management
THE CONCEPT REAL LIFE SCENARIO
MANAGEMENT RESPONSIBILITY
A company had bid on the an Express Highway Project
and won it.
To earn more profits, management decided to use
inferior-grade asphalt. The workers laying the asphalt
65 have little control over its quality.
3
Project Quality Management
THE CONCEPT
CONTINUOUS IMPROVEMENT
PDCA (plan-do-check-act) Cycle, defined by Shewhart
and modified by Deming, forms the basis for quality
improvement
65
4
Project Quality Management
THE CONCEPT
CONTINUOUS IMPROVEMENT
Quality improvement initiatives (TQM, SIX SIGMA)
can contribute in improving the quality of both:
1) Project management, and
2) The project’s product
65 Process improvement models (Malcolm Baldrige,
5 CMM, CMMI) also provide useful guidance.
Project Quality Management
THE CONCEPT
Key difference project team MUST know:
Projects are too temporary to reap the rewards of
investments in product quality improvement (mainly
defection prevention, appraisal), hence performing
organization must bear these investments!
65
6
Plan Quality process overview
65
8
Plan Quality - INPUTS
65
9
Plan Quality - INPUTS
3. Scope Baseline.
- A. Scope statement: contains the product
description, major project deliverables, and
acceptance criteria. The product description contains
details of technical issues and other concerns that
can affect quality planning. The definition of
acceptance criteria can significantly increase or
decrease project costs and quality costs. Satisfying
acceptance criteria means the needs of the customer
have been met.
- B. WBS: identifies the deliverables, the work
66 packages and the control accounts used to measure
project performance.
1
Plan Quality - INPUTS
Scope Baseline.
- C. WBS dictionary: defines technical information for
WBS elements and must be considered during quality
planning.
4. Cost Performance baseline
documents the accepted time phase used to measure
cost performance. Quality must be achieved within
this time-phased budget.
5. Risk Register
provides threats and opportunities that may impact
66 quality requirements
2
Plan Quality - INPUTS
6. Schedule Baseline
accepted schedule within which quality parameters
should be achieved.
7. Stakeholder Register
identifies stakeholders with a particular interest , or
impact on quality.
66
3
Plan Quality – Tools & Techniques
1. Cost/Benefit analysis
analyze cost-benefits tradeoffs
Primary benefit of meeting Quality
Requirements:
BENEFITS
1. LESS REWORK
2. HIGHER PRODUCTIVITY
3. LOWER COSTS
4. INCREASED STAKEHOLDER
66 SATISFACTION
4
Plan Quality – Tools & Techniques
COSTS
TRAINING
SURVEYS
STUDIES
APPRAISAL
DESIGN REVIEW
66
5
Plan Quality – Tools & Techniques
2. Benchmarking
Purpose: To generate ideas for improvements and
offer standards to measure performance.
Method: We compare the actual or planned project’s
practices to those of other projects.
Sources: These projects can be:
a) within performing organization or outside
b) Within same application area or in another
66 Application area
6
Plan Quality – Tools & Techniques
4. Cost of quality
Consists of all our costs on efforts to:
Achieve product / service quality
Ensure conformance to requirements
Work resulting from nonconformance to requirements
66
8
Plan Quality – Tools & TechniquesPlan Quality
Cost of quality
66
9
Plan Quality – Tools & TechniquesPlan Quality
Cost of quality
Prevention costs
Prevention means keeping defects
out of the hands of the customer.
These costs are associated with
producing a product/service without
defects in order to satisfy Customer
Requirements.
Example: quality planning, training,
design review, contractor and
supplier costs
67
0
Plan Quality – Tools & TechniquesPlan Quality
Cost of quality
Appraisal costs
Expended to examine the product or
process and make certain that the
Requirements are being met.
67
1
Plan Quality – Tools & TechniquesPlan Quality
Cost of quality
Failure costs
Are the costs incurred when things
don’t happen according to the plan:
1) Internal failure costs
result when customer requirements
are not satisfied and the product
is still in the control of the
performing organization
Example: corrective action, rework,
scraping, and downtime
67
2
Plan Quality – Tools & TechniquesPlan Quality
Cost of quality
Failure costs
Are the costs incurred when things
don’t happen according to the plan:
2) External failure costs
result when the product has
reached the customer and they
determine that their requirements
have not been met.
Example: inspections at customer’s site
returns, and customer service
costs
67
3 COST OF POOR QUALITY: FAILURE COSTS!
Plan Quality – Tools & Techniques
5. Flow charting
It is any diagram that shows logical steps that must be
performed to accomplish an objective.
It displays how individual elements of a System
interrelate.
In the case of quality management,two types of flow
charts are used:
Cause-and-effect diagrams (Ishikawa diagrams,
67 fishbone diagrams) show relationship between various
4 factors (causes) to potential problems/effects.
Plan Quality – Tools & Techniques
5. Flow charting
Cause-and-effect diagrams (Ishikawa
diagrams, fishbone diagrams) show
relationship between various factors (causes)
to potential problems/effects.
Process flow diagram
67
5
Plan Quality – Tools & Techniques
EXAMPLE:CAUSE-AND-EFFECT DIAGRAM
MAJOR
DEFECT
PROJECT
ENERGY ENVIRONMENT MEASUREMENT
TEAM
67
6
Plan Quality – Tools & Techniques
N = No 1. Project Request
Y = Yes
2. Compliance Copy
3. Develop Artwork
4. Artwork Approved N
6. Control Charts
Used to determine whether or not process is stable
or has predictable performance.
Upper and lower specification i are set based on the
requirements, reflecting minimum and maximum
values allowed.
There may be penalties for crossing these limits.
For repeatable processes are generally +/- 3 sigma!
67
9
Plan Quality – Tools & Techniques
6. Control Charts
A process is out of control when data points cross
the limits or seven consecutive points are above or
below the mean, although inside the control limits.
Control charts are used to monitor various types of
variable outputs.
68
0
Plan Quality – Tools & Techniques
6. Control Charts
68
1
Plan Quality – Tools & Techniques
7. Statistical Sampling:-
It involves choosing part of a population of
interest for inspection.
Sample frequency and sizes should be
determined during the plan quality process
so the cost of quality will include the no. of
tests, expected scrap, etc.
68
2
Plan Quality – Tools & Techniques
68
4
Plan Quality – OUTPUTS
68
7
Plan Quality - OUTPUTS
Quality Checklists
It is a component specific, structured tool used to
verify a set of required steps has been performed.
A ‘do this’ list, or ‘have you done this’ monitor!
These lists ascertain consistency in frequently
performed tasks.
Most organizations have it, or you can get one from
commercial service providers or professional
associations.
69
1
Plan Quality – OUTPUTS
COMMUNICATIONS
69
3
Communication
THE CONCEPT
1. Proper communication is one of the critical success factors.
2. There should be a structured approach to it.
3. Communication needs of all project stakeholders must be
identified in advance:
What they need to be communicated
How they are going to be communicated
When they will to be communicated
69
4
Communication
THE CONCEPT
4. This is a very proactive approach and must be adopted on all
projects to ensure smooth working, amicable relations, and
project success.
5. This is particularly more important due the fact that most
project managers do not know what this is, nor do they
realize that individual needs of each stakeholder must be
69 addressed.
5
Communication
69
8
Communication
Writing style:
- active or passive voice
- sentence structure
70 - word choice
1
Communication
2
Communication
Plan Communications
the process of
Determining the project stakeholders
information needs and defining a communication
approach.
Identifying information needs of stakeholders
and deciding suitable means of meeting them
70 are key factors for project success!
4
Communication
Plan Communications
70
6
Communication
THROUGH
Status reports
Progress reports
Trend report
Forecasting report
Variance report
Earned value analysis reports
Compliance to regulations, and so on
71
2
Communication
Communication channels
The project manager needs to consider the number of potential
communication channels to grasp the complexity of a project’s
Communications: ( 20 PEOPLE, 190 CHANNEL! )
2 PEOPLE, 1 CHANNEL
4 PEOPLE, 6 CHANNEL
5 PEOPLE, 10 CHANNEL