RESUME

WEEKLY REPORT
JOB PROGRESS
DAY : 3 (Days)
PT RAM LIFTING TECHNOLOGIES PTE LTD
DATE PERIODE : 25 - 28 March 2024
Lytech Industrial Park Block C3 No.
FABRICATION DUMMY FORK LOCATION :
5-6 Batam, Indonesia
CONTRACTOR : PT. LOUIS ALAIN CONTRACT NUMBER :
DATE OF CONTRACT :
Unit Total Weight Progress
No Volume UOM
JOB DESCRIPTION Price Price % 25 - 26 26 - 27 27 - 28 28 - 29 29 -30 30 - 31

A PREPARATION

1 ANALYZE 1 Ls 10.000.000 10.000.000 14,63 14,63%


2 MATERIAL 1 Ls 11.890.000 11.890.000 17,40 17,40%
3 CONSUMABLE 1 Ls 1.888.400 1.888.400 2,76 2,76%
4 EQUIPMENT AND TOOL 1 Ls 12.415.000 12.415.000 18,17 18,17%
B PRODUCTION
1 MACHINING 1 Ls 10.000.000 10.000.000 14,63 14,63%
2 FIT UP 1 Ls 6.068.000 6.068.000 8,88 4,44% 4,44%
3 WELDING 1 Ls 6.068.000 6.068.000 8,88 8,88%
C FINISHING
1 DOING INSPECTION AFTER ALL WORK IS DONE 1 Ls 10.000.000 10.000.000 14,63 14,63%

Total 68.329.400 100,00 52,96% 19,07% 27,95%


JUMLAH 8
Total Progress 100,0%
- CONTRACT / PO No. / IDR 68.329.400
- PROGRESS DAY 1 52,96%
- PROGRESS DAY 2 19,07%
- PROGRESS DAY 3 27,95%
- TOTAL PROGRESS 100,0%

Approved by : An Knowledge by Checked by : Prepared by:

RAM LIFTING TECH PT. LOUIS ALAIN PT. LOUIS ALAIN PT. LOUIS ALAIN

GARY VALENCIA GONZALES DENNY OSCAR MUS MULYADI DENNY OSCAR


GENERAL MANAGER GENERAL MANAGER ENGINEERING CORDINATOR PROJECT LEAD