APPL. N/A
Fill out chapter 1, 4, 5 and
Installation
“Installation and Acceptance Report”
Preventive Maintenance Fill out chapter 2, 3, 4 and 5
Corrective Maintenance Fill out chapter 3, 4 and 5
Safety Check Fill out chapter 4 and 5
or or
Safety Check with local report Fill out local Check List
Further documents attached
(The electrical safety test must be carried out in accordance with applicable local regulations and directives.)
Note:
For Model 5000/500 with any software version.
For Model 4000/400 with software version 6.0 and higher.
Note: Any section has to be filled in by marking "NA"(not applicable) or "OK" / "Not OK".
If you have to mark any check box "not OK", please explain in "Comments".
Basic: OK Not OK
Table Maximum / Minimum Travel Verification
Keyboard Installation
Mouse Installation
USB Wireless Network Adapter Installation
External Fixation Installation
Application Startup Checks Verification
Instrument Alignment Test
System Date & Time Verification
Optional:
Network Configuration N/A NA OK Not OK
Office Network Reconnected
DICOM Gateway Configuration
Connective Software (FORUM / EMR / Review Software)
Reconfigured
Each year
Basic: OK Not OK
All external cable and cord connections secured
Instrument powered from properly grounded AC outlet
Instrument cooling vents unobstructed
Chin Cup and Forehead Rest Clean
Front Window Lens (Ocular Lens) Clean
Instrument (Fan) Filter Clean
Chapter 3 (Comprehensive) Completed
PM Indicator Reset
Basic: NA BC AC
Nominal OCT SLD Power Verification (540-660 uW) 623
Condition A *
751
OCT SLD Shutoff Verification (675-825 uW)
Condition B *
Maximum OCT SLD Power Verification (640-775 uW)
Nominal LSLO SLD Power (900-1100 uW) 1230 1000
Maximum LSLO SLD Power (>900 uW) 2790
LSLO SLD Shutoff Verification (1200-1400 uW)
Note: For Model 4000 with LSLO SLD safety shutoff.
Comprehensive: NA BC AC
Nominal OCT SLD Power Verification (540-660 uW) 623
Condition A *
751
OCT SLD Shutoff Verification (675-825 uW)
Condition B *
Voltage Potentiometer (PD) Shutoff Verification
Condition B *
Voltage Potentiometer (PD) Adjustment (1.285 - 1.335 V)
Condition B *
Maximum OCT SLD Power Verification (640-775 uW)
Nominal LSLO SLD Power (900-1100 uW) 1230 1000
In addition follow your national regulations and if applicable all national standards!
CZ Service Customer*
The Safety test according to EN/IEC 62353 is performed by:
* In case the customer is responsible, no further action is required from FSE, but it is mandatory to
add this information to your service report.
Visual inspection
N/A OK Not OK
(EN/IEC 62353)
Function test
N/A OK Not OK
(EN/IEC 62353)
Further tested
functions/parameters:
________________________________________________________
Calibration
Test equipment used Type Serial number
valid until
Newport
Power Meter 0267L19R 2022-07-02
Field Master
LabMax
Power Meter Head OP-2 VIS 0207L19R 2022-07-02
6617 2022-07-06
Tool Kit CIRRUS
Calibration
Accessories used Type Serial number valid until
Calibration
Test equipment used Type Serial number
valid until
Calibration
Accessories used Type Serial number
valid until
Which:
Additional tested
Type Serial number Result
equipment
Accessories:
Rating:
6 12 24 36 19.07.2022
Next repeat check is due in months or not later than ____________________