3m SN bolt in 3m SN bolt in slope

Date Location Top surface

26-Apr

km 153+900-154+100
27-Apr RHS 14

km 153+900-154+100
28-Apr RHS 29

km 153+900-154+100
29-Apr RHS 27

km 153+900-154+100
30-Apr RHS

km 153+900-154+100
01-May RHS
6m SN bolt in slope
surface Chain Link mesh HSBN with Hang HSBN

1875

1250
Remarks
Fastners
Approach road making & vegetaion
clerance at km 153+900- 154+100 RHS.
7 labour
Approach road making & vegetaion
clerance at km 153+900- 154+100 RHS.
7 labour
Approach road making & vegetaion
clerance at km 153+800- 154+100 RHS.
7 labour
Approach road making & vegetaion
clerance at km 153+800- 154+100 RHS.
7 labour . 9 local
Approach road making & vegetaion
clerance at km 153+800- 154+100 RHS.
7 labour , 9 local
Approach road making & vegetaion
clerance at km 153+800- 154+100 RHS.
7 labour , 13 local