Bldg. No:
Sr.
W.O Number Description Observations Photo Required Action Status Remarks
No Location:
Bldg.# BA24-
Maintenance Weekly Inspection of Emergency
9 Workshop & WO25746915 Generator(DOOSAN-500KVA@ PM tasks have been done PM Completed
Desalination 220/380V).
Plant
Inspected By
Yasir Safari