ID Task Name Duration Start

August September
1/8 8/8 15/8 22/8 29/8
1 MAIS-eFaraid CR 17 days Mon 9/8/21
2 Change Request (CR) 14 days Mon 9/8/21
3 Requirement Study 4 days Mon 9/8/21
4 User Requiment 1 day Mon 9/8/21
5 URS Document 2 days Tue 10/8/21
6 Sign off 1 day Thu 12/8/21
7 Development 4 days Fri 13/8/21
8 Tawaran 4 days Fri 13/8/21
9 Terima Tawaran 2 days Fri 13/8/21
10 Tolak Tawaran 2 days Tue 17/8/21
11 Notis 4 days Fri 13/8/21
12 Bayaran Lumpsum 2 days Fri 13/8/21
13 Bayaran Ansuran 2 days Tue 17/8/21
14 Maklumat Kontrak 2 days Thu 19/8/21
15 Daftar Maklumat Contract 2 days Thu 19/8/21
16 Integration Dengan Saga 4 days Mon 23/8/21
17 Upload dan Proses Rekod Bayaran 4 days Mon 23/8/21
18 laporan/Pertanyaan 4 days Thu 19/8/21
19 Tawaran 1 day Thu 19/8/21

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: eFaraid CR
Summary Manual Summary Rollup Progress
Date: Wed 4/8/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Name Duration Start
August September
1/8 8/8 15/8 22/8 29/8
20 Notis 1 day Fri 20/8/21
21 Kontrak 1 day Mon 23/8/21
22 Bayaran 2 days Mon 23/8/21
23 User Acceptance Test (UAT). 5 days Fri 13/8/21
24 Test Script Preparation 2 days Fri 13/8/21
25 Submit TestScript 1 day Tue 17/8/21
26 UAT 2 days Wed 18/8/21
27 Modify Code and Retest 3 days Fri 20/8/21
28 Modify Code and Retest 3 days Fri 20/8/21
29 Final Acceptance Test (FAT) 5 days Fri 20/8/21
30 Update Test Script 3 days Fri 20/8/21
31 Submit TestScript 1 day Wed 25/8/21
32 FAT 2 days Wed 25/8/21
33 Training 16 days Mon 9/8/21
34 Training Document Preparation 13 days Mon 9/8/21
35 Training (System Administrator) 1 day Fri 27/8/21
36 Training (User) 1 day Mon 30/8/21
37 GO LIVE 1 day Tue 31/8/21

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: eFaraid CR
Summary Manual Summary Rollup Progress
Date: Wed 4/8/21
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only