Our Ref : HIF/IIS/L/2211/02

Dated : 30th November 2022

MACHLAB SCIENTIFIC SDN. BHD.


No. 1-1, Jalan BS5/26A,
Taman Bukit Serdang, 43300,
Seri Kembangan. Selangor.
ATTN : MR. AMBROSE TEY/ MR. EDMUND LIM

RE : INVICTUS INTERNATIONAL SCHOOL – Letter for Non-compliance of construction works

We refer to your email dated 30th November 2022,

As per our site discussion on 23th November 2022 with Mr. Mike (HIFSB), Ms. Summer (HIFSB), Mr.
Edmund Lim (Machlab) and myself. We found that the Phenolic Top supply by Machlab Scientific Sdn.
Bhd. do not comply as per your shop drawings submitted and not as per our drawing provided to you.
We totally not accepting the incorrect Phenolic Top delivered to site, which do not comply to the
requirement as per contract.

Therefore, with immediate effect you are require to replace your materials in accordance to your shop
drawings without any further delay. We wish to remind you that your works delay will affect our
progress on site and others.

We trust the above are in order

Yours faithfully,

HOMLUX INTERIOR FURNISHING SDN BHD

………………………………………………………………..
TAN WG
Project Manager
SUMMARY OF NON-COMPLIANCE Homlux Interior Furnishing Sdn. Bhd.

Items Drawings/ Details by Homlux Shop Drawings/ Details by Machlab Materials On-Site Status/Action

Water tap opening position


1 Reject & Re-Do

Sink opening edge


2 Reject & Re-Do