SAUDI ARAMCO INSPECTION CHECKLIST
Fill Placement and Compaction Inspection SAIC-A-1004 24-Mar-16 CIVIL-
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
No.
SAES-A-114
A1 Fill material shall be placed in lifts not exceeding 200mm in loose depth.
Sec. 6.3..3.1
Fill material shall be placed in lifts not exceeding 100mm in loose depth SAES-A-114
A2
for hand-operated compaction. Sec. 6.3.3.3
Fill and backfill adjacent to any type of structure shall not be compacted
SAES-A-114
A4 with heavy equipment; Hand operated equipment shall be used within
Sec. 6.3.5.1
1.2 meters of any structures.
Compacted surfaces of fill and backfill shall be finish graded to the cross SAES-A-114
A6
sections, lines, grades and elevations as indicated on the drawings. Sec. 6.3.7
B Compaction Inspection
Compaction shall begin only after the fill or backfill has been properly
placed and the material to be compacted is at the proper moisture SAES-A-114
B1
content. +/- 3% of the optimum moisture content per ASTM D1557 or Sec. 6.3.4
ASTM D698, whichever is applicable. (PIP-CVS02100, Sec. 4.3.7.7.3)
SAES-A-114
B2 Compaction shall be performed with equipment compatible with soil type.
Sec. 6.3.5