Progres Week 41
Progres Week 41
Progres Week 41
Contract No 088/E-CTR//BNY/COI/2022
BUNYUT BARGE LOADING UPGRADE 3700/4000
Sign
Safety Record
Conveyor Belt Maintenance and Vulcanizing Power Transmission Conveyor Accessories Wear & Corrosion Protection Engineering
WEEKLY Project Bunyut Barge Loader Upgrade 3700/4000 TPH
Contract No 088/E-CTR//COI/2022
Period, 15 April 2024 – 21 April 2024
MAN POWER
No Labour Cominco
1 PJO -
2 HSE -
3 QA/QC 1
4 Admin Site -
6 Foreman 1
7 Welder -
8 Fitter 1
9 Driver -
10 Project Control -
12 Mechanical Supervisor -
13 Operator Crane 1
14 Rigger 1
15 Scaffolder -
16 Civil -
17 Carpenter -
18 Drafter -
19 Engineering -
21 Helper 2
21 Store Man -
22 Electrical -
23 Programmer -
24 Technician -
25 Planner -
26 Total 7
SAFETY RECORD
QUANTITY
NO CATEGORY
LAST WEEK THIS WEEK
1 Fatality 0 0
2 Major Injuries 0 0
3 Lost Time Injuries 0 0
4 Medical Aid Injuries 0 0
5 First Aid Injuries 0 0
6 Near Miss 0 0
7 Hazardous Condition 0 0
8 Hazardous Action 0 0
9 Traffic Accident 0 0
10 Working Hours With Out Injuries 0 336
Total Man Hours Last Week 79153 336
Total Man Hours Until This Week 79489
HAZARD RECORD
2. PROJECT OVERVIEW
www.cominco.co.id
WEEKLY Project Bunyut Barge Loader Upgrade 3700/4000 TPH
Contract No 088/E-CTR//COI/2022
Period, 15 April 2024 – 21 April 2024
Description Remark
- Work scheme, In the morning at 08:00 Tool Box Meeting work and Safety Plan
- Work scheme, 08:30 Work scheme, 08:30 Restore Carry Rollers from New to Existing BC 04 &
05, Closing Punchlist BC 04 & 05, Install Seam Plate for Carry Roller Frame BC 04, Modify Tail
Feed Chute BC 03 Tunnel 1, Modify Tail Feed Chute BC 03 Tunnel 1, Welding Modified Tail
Feed Chute BC 03 Tunnel 1, Install Additional Sliding Gate Rail Bracing BC 03 Tunnel 1, Install &
Welding Additional Hat for Hopper Liner Plate BC 03 Tunnel 1, Concrete Casting for Drive Unit
Reinforcement BC 05, Test Running Open-close Sliding Gate BC 03 Tunnel 1, Repair
Termination MV Transformer MCC 2
www.cominco.co.id
WEEKLY Project Bunyut Barge Loader Upgrade 3700/4000 TPH
Contract No 088/E-CTR//COI/2022
Period, 15 April 2024 – 21 April 2024
DOCUMENTATION
3.Painting
Material
Steel Sliding
Gate Tunnel
2-6
4. Install
Gate Roller
BC 05
5.Fabrikasi
Support
Perkuatan
Support Base
Drive Unit BC
05
www.cominco.co.id
WEEKLY Project Bunyut Barge Loader Upgrade 3700/4000 TPH
Contract No 088/E-CTR//COI/2022
Period, 15 April 2024 – 21 April 2024
3.Painting
Material
Steel Sliding
Gate Tunnel
2-6
4. Install
Gate Roller
BC 05
5.Install
Support
Perkuatan
Support Base
Drive Unit BC
05
3.Change
Carry Roller
BC 05
4.Reposisi
Miss
Aligment BC
04 Area
Tunnel 1
www.cominco.co.id
WEEKLY Project Bunyut Barge Loader Upgrade 3700/4000 TPH
Contract No 088/E-CTR//COI/2022
Period, 15 April 2024 – 21 April 2024
3.Install Roff
MCC 2
4. Install
Roof MCC
2.1
5. Welding
Penambahan
Support Base
Drive Unit BC
05
3.Install Add
Support
Cable Ladder
BC 04 TO
MCC 2.2
4. Install
Roof MCC
2.1
5. Welding
Penambahan
Support Base
Drive Unit BC
05
www.cominco.co.id
WEEKLY Project Bunyut Barge Loader Upgrade 3700/4000 TPH
Contract No 088/E-CTR//COI/2022
Period, 15 April 2024 – 21 April 2024
3.Install Add
Support
Cable Ladder
BC 04 TO
MCC 2.2
4.Continue
Install Roof
MCC 2.1
5. Welding
Penambahan
Support Base
Drive Unit BC
05
6. Fabrikasi
Box Metal
Magnet
Saparator BC
05
7 Sunday 1.Toolbox
Meeting
21/04/24
2. Continue
DismantleRel
l Hoist
Existing
Tunnel 5 & 6
3.Install Add
Support
Cable Ladder
BC 04 TO
MCC 2.2
4.Continue
Install Roof
MCC 2.1
5. Painting
Penambahan
Support Base
Drive Unit BC
05
www.cominco.co.id