PROVIDENT HOUSING LIMITED

CHECKLIST FOR FOOTING Anupama Constructions


ACTIVITY : REINFORCEMENT

Project : Checklist No:CL-QA-07A


Rev. No:01
Location : Date:
Contractor : Dwg No:
Note : Please appropriate box as per requirements
Sl No DESCRIPTION YES NA REMARKS
1 Checked and ensured the availability of GFC drawing with Name,date and [ ] [ ]
no.?
PRE-EXECUTION CHECKS

2 Ensured QA & PE approved work method statement is available with the [ ] [ ]


team
3 Checked and ensured the area is prepared for starting reinforcement [ ] [ ]
(PCC complete)
4 Checked and ensured the steel bars are tested and approved as per ITP. [ ] [ ]

5 Checked and ensured necessary barricading and safety measures are [ ] [ ]


taken.
6 Checked and ensured required tools are available at the site. [ ] [ ]

7 Checked and ensured reinforcement is free from oil, mud, crease and other [ ] [ ]
forms of contamination.
CHECKS DURING EXECUTION

8 Checked and ensured the reinforcement placing is done as per drawing. [ ] [ ]

9 Ensured the column bars are placed as per GFC drawings with provision for [ ] [ ]
alternate lap zone.
10 Checked and ensured the spacing between the stirupps and the total [ ] [ ]
number of strirrups are as per design.
11 Ensured the anchors are provided as per drawings at the edges of the [ ] [ ]
footing
12 Ensured the chairs are provided at appropriate locations and as per design. [ ] [ ]

13 Ensured the cover blocks are of correct sizes and at correct spacing. [ ] [ ]

14 Ensured the development lengths and anchorage lengths provided are as [ ] [ ]


per drawings.
15 Ensured the dowels that are provided for future concreting are as per [ ] [ ]
drawings.
POST-EXECUTION CHECKS

16 Ensured the reinforcements are clean and free from any unwanted [ ] [ ]
materials.
17 Ensured the reinforcements are tied properly with binding wire of [ ] [ ]
necessary gauge.
18 Ensured no bars are twisted or deformed in any manner. [ ] [ ]

19 Ensured the position of reinforcement and chairs are not disturbed. [ ] [ ]

Note: Please record NA where not applicable


Contractor PL/PHL

Site In Charge QC Engineer PMC Site In Charge QA & PE

Name:

Signature:

Date: