Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

PROVIDENT HOUSING LIMITED

CHECKLIST FOR COLUMNS Anupama


ACTIVITY : REINFORCEMENT Constructions
Project : Checklist No:CL-QA-07B
Rev. No:01
Location : Date:
Contractor : Dwg No:
Note : Please appropriate box as per requirements
Sl No DESCRIPTION YES NA REMARKS
1 Checked and ensured the availability of GFC drawing with Name,date and [ ] [ ]
no.?
PRE-EXECUTION CHECKS
2 Ensured QA & PE approved work method statement is available with the team [ ] [ ]

3 Checked and ensured the area is prepared for starting reinforcement [ ] [ ]


(PCC complete/ slab concrete set)
4 Checked and ensured the steel bars are tested and approved as per ITP. [ ] [ ]

5 Checked and ensured availability of necessary scaffolding and safety [ ] [ ]


measures are taken.
6 Checked and ensured required tools are available at the site. [ ] [ ]

7 Checked and ensured reinforcement is free from oil, mud, crease and other [ ] [ ]
forms of contamination.
CHECKS DURING EXECUTION
8 Ensured the column bars are placed as per GFC drawings with provision for [ ] [ ]
alternate lap zone.
9 Checked and ensured the spacing between the stirupps and the total number [ ] [ ]
of strirrups are as per design.
10 Ensured stirrups are provided up to the bottom of the each footing and at the [ ] [ ]
beam -column junction.
11 Ensured that the reinforcement bars that are projecting out of the current [ ] [ ]
area of concreting are parallel.
12 Ensured the cover blocks are ofcorrect sizes and at correct spacing. [ ] [ ]

13 Ensured minimum three strirupps are done above the concrete finishing level [ ] [ ]
to maintain the shape of the reinfoircement .
14 Ensured adequate anchorge lengths are provided at the bottom of the column [ ] [ ]
reinforcement.
15 Ensured the provision of dowels for future extensions are done are as per the [ ] [ ]
drawings.
16 Ensured the ends of the dowels for future extension are covered properly [ ] [ ]
with polythene sheets.
POST-EXECUTION CHECKS
17 Ensured the reinforcements are clean and free from any unwanted materials. [ ] [ ]

18 Ensured the reinforcements are tied properly with binding wire of necessary gauge. [ ] [ ]

19 Ensured no bars are twisted or deformed in any manner. [ ] [ ]

20 Ensured the position of reinforcement and stirrups are not disturbed. [ ] [ ]

Note: Please record NA where not applicable


Contractor PL /PHL
Site In Charge QC Engineer PMC Site In Charge QA & PE
Name:
Signature:
Date:

You might also like