Tour Mohammed VI6 : Programme logements

Planning Level 3

Activity ID Activity Name Original Duration Start Finish WF-Lot tour 2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
262d 28/Dec/23 A 27/Dec/24
Master Planning
Master Schedule 262d 28/Dec/23 A 27/Dec/24

Execution 262d 28/Dec/23 A 27/Dec/24

Tour 262d 28/Dec/23 A 27/Dec/24

Logements (R+14 à R+28) 262d 28/Dec/23 A 27/Dec/24

R+16 51d 01/Feb/24 A 27/May/24

Front of House 44d 01/Feb/24 A 16/May/24

Agencement 30d 01/Feb/24 A 26/Apr/24

Terminaux 23d 25/Mar/24 27/Apr/24

Peinture 15d 22/Apr/24 09/May/24

Revêtement souple 15d 29/Apr/24 16/May/24

CHC 55d 01/Feb/24 A 27/May/24

Faux-plafond 10d 04/May/24 15/May/24

Revêtement sol 10d 16/Mar/24 27/Mar/24

Agencement 18d 01/Feb/24 A 30/Apr/24

Terminaux 6d 26/Apr/24 03/May/24

Peinture 10d 09/May/24 20/May/24

Revêtement souple 10d 16/May/24 27/May/24

R+14 200d 20/Feb/24 A 23/Oct/24

Front of House 72d 18/Mar/24 25/Jun/24

Agencement 46d 18/Mar/24 20/May/24

Terminaux 17d 14/May/24 01/Jun/24

Peinture 16d 27/May/24 13/Jun/24

Revêtement souple 10d 07/Jun/24 25/Jun/24

CHC 222d 20/Feb/24 A 23/Oct/24

Faux-plafond 10d 19/Sep/24 30/Sep/24

Revêtement sol 69d 20/Feb/24 A 06/Apr/24

Agencement 19d 10/Aug/24 04/Sep/24

Terminaux 11d 05/Sep/24 18/Sep/24

Peinture 10d 01/Oct/24 11/Oct/24

Revêtement souple 10d 12/Oct/24 23/Oct/24

R+17 150d 16/Mar/24 12/Oct/24

Remaining Level of Effort Actual Work Critical Remaining Work Date Revision Checked Approved
Page 1 of 7
17/Apr/24 Rebaseline version K BST
Actual Level of Effort Remaining Work Milestone
Tour Mohammed VI6 : Programme logements
Planning Level 3

Activity ID Activity Name Original Duration Start Finish WF-Lot tour 2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
Front of House 50d 23/Apr/24 01/Jul/24

Agencement 15d 23/Apr/24 13/May/24

Terminaux 16d 14/May/24 31/May/24

Peinture 15d 27/May/24 12/Jun/24

Revêtement souple 15d 07/Jun/24 01/Jul/24

CHC 163d 16/Mar/24 12/Oct/24

R+15 151d 28/Mar/24 24/Oct/24

Front of House 68d 29/Apr/24 31/Jul/24

Agencement 41d 29/Apr/24 24/Jun/24

Terminaux 21d 06/Jun/24 06/Jul/24

Peinture 20d 26/Jun/24 18/Jul/24

Revêtement souple 20d 08/Jul/24 31/Jul/24

CHC 163d 28/Mar/24 24/Oct/24

Faux-plafond 10d 20/Sep/24 01/Oct/24

Revêtement sol 10d 28/Mar/24 15/Apr/24

Agencement 20d 10/Aug/24 05/Sep/24

Terminaux 11d 06/Sep/24 19/Sep/24

Peinture 10d 02/Oct/24 12/Oct/24

Revêtement souple 10d 14/Oct/24 24/Oct/24

R+18 146d 15/Apr/24 04/Nov/24

Front of House 75d 18/Apr/24 31/Jul/24

Agencement 48d 18/Apr/24 24/Jun/24

Terminaux 21d 06/Jun/24 06/Jul/24

Peinture 20d 26/Jun/24 18/Jul/24

Revêtement souple 20d 08/Jul/24 31/Jul/24

CHC 163d 15/Apr/24 04/Nov/24

Faux-plafond 10d 01/Oct/24 11/Oct/24

Revêtement sol 10d 15/Apr/24 25/Apr/24

Agencement 19d 26/Aug/24 17/Sep/24

Terminaux 11d 18/Sep/24 30/Sep/24

Peinture 10d 12/Oct/24 23/Oct/24

Revêtement souple 10d 24/Oct/24 04/Nov/24

Remaining Level of Effort Actual Work Critical Remaining Work Date Revision Checked Approved
Page 2 of 7
17/Apr/24 Rebaseline version K BST
Actual Level of Effort Remaining Work Milestone
Tour Mohammed VI6 : Programme logements
Planning Level 3

Activity ID Activity Name Original Duration Start Finish WF-Lot tour 2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
R+19 224d 28/Dec/23 A 05/Nov/24

Front of House 163d 28/Dec/23 A 12/Aug/24

Revêtement sol 12d 14/Feb/24 A 26/Apr/24

Revêtement mur 14d 28/Dec/23 A 27/Mar/24

Agencement 31d 24/May/24 05/Jul/24

Terminaux 31d 06/Jun/24 18/Jul/24

Peinture 30d 26/Jun/24 31/Jul/24

Revêtement souple 30d 08/Jul/24 12/Aug/24

CHC 153d 27/Apr/24 05/Nov/24

Faux-plafond 10d 02/Oct/24 12/Oct/24

Revêtement sol 10d 27/Apr/24 09/May/24

Agencement 20d 26/Aug/24 18/Sep/24

Terminaux 11d 19/Sep/24 01/Oct/24

Peinture 10d 14/Oct/24 24/Oct/24

Revêtement souple 10d 25/Oct/24 05/Nov/24

R+20 227d 04/Jan/24 A 16/Nov/24

Front of House 162d 04/Jan/24 A 16/Aug/24

Revêtement sol 54d 04/Jan/24 A 26/Apr/24

Revêtement mur 22d 04/Jan/24 A 27/Mar/24

Agencement 80d 16/Mar/24 05/Jul/24

Terminaux 16d 04/Jul/24 22/Jul/24

Peinture 15d 17/Jul/24 03/Aug/24

Revêtement souple 15d 29/Jul/24 16/Aug/24

CHC 162d 27/Apr/24 16/Nov/24

Faux-plafond 10d 12/Oct/24 23/Oct/24

Revêtement sol 10d 27/Apr/24 09/May/24

Agencement 19d 06/Sep/24 28/Sep/24

Terminaux 11d 30/Sep/24 11/Oct/24

Peinture 10d 24/Oct/24 04/Nov/24

Revêtement souple 10d 05/Nov/24 16/Nov/24

R+21 204d 10/Jan/24 A 21/Oct/24

Front of House 147d 10/Jan/24 A 01/Aug/24

Remaining Level of Effort Actual Work Critical Remaining Work Date Revision Checked Approved
Page 3 of 7
17/Apr/24 Rebaseline version K BST
Actual Level of Effort Remaining Work Milestone
Tour Mohammed VI6 : Programme logements
Planning Level 3

Activity ID Activity Name Original Duration Start Finish WF-Lot tour 2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
Revêtement sol 57d 10/Jan/24 A 06/May/24

Revêtement mur 19d 10/Jan/24 A 20/Apr/24

Agencement 72d 16/Mar/24 25/Jun/24

Terminaux 22d 25/Jun/24 19/Jul/24

Peinture 26d 02/Jul/24 01/Aug/24

Revêtement souple 15d 13/Jul/24 31/Jul/24

CHC 133d 06/May/24 21/Oct/24

Faux-plafond 10d 17/Sep/24 27/Sep/24

Revêtement sol 10d 06/May/24 17/May/24

Agencement 17d 10/Aug/24 02/Sep/24

Terminaux 11d 03/Sep/24 14/Sep/24

Peinture 10d 28/Sep/24 09/Oct/24

Revêtement souple 10d 10/Oct/24 21/Oct/24

R+22 229d 15/Jan/24 A 28/Nov/24

Front of House 165d 15/Jan/24 A 30/Aug/24

Chape 53d 15/Jan/24 A 16/Apr/24

Revêtement sol 104d 20/Jan/24 A 28/May/24

Revêtement mur 14d 27/Apr/24 14/May/24

Agencement 63d 22/Apr/24 17/Jul/24

Terminaux 16d 16/Jul/24 03/Aug/24

Peinture 15d 29/Jul/24 16/Aug/24

Revêtement souple 15d 10/Aug/24 30/Aug/24

CHC 146d 29/May/24 28/Nov/24

Faux-plafond 10d 24/Oct/24 04/Nov/24

Revêtement sol 10d 29/May/24 08/Jun/24

Agencement 19d 19/Sep/24 10/Oct/24

Terminaux 11d 11/Oct/24 23/Oct/24

Peinture 10d 05/Nov/24 16/Nov/24

Revêtement souple 10d 18/Nov/24 28/Nov/24

Back of House 60d 28/Feb/24 A 16/May/24

No WF-Lot tour 60d 28/Feb/24 A 16/May/24

R+23 218d 18/Jan/24 A 18/Nov/24

Remaining Level of Effort Actual Work Critical Remaining Work Date Revision Checked Approved
Page 4 of 7
17/Apr/24 Rebaseline version K BST
Actual Level of Effort Remaining Work Milestone
Tour Mohammed VI6 : Programme logements
Planning Level 3

Activity ID Activity Name Original Duration Start Finish WF-Lot tour 2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
Front of House 167d 18/Jan/24 A 06/Sep/24

Chape 50d 18/Jan/24 A 16/Apr/24

Revêtement sol 88d 08/Feb/24 A 28/May/24

Revêtement mur 14d 27/Apr/24 14/May/24

Agencement 79d 03/Apr/24 22/Jul/24

Terminaux 16d 23/Jul/24 10/Aug/24

Peinture 15d 06/Aug/24 26/Aug/24

Revêtement souple 15d 19/Aug/24 06/Sep/24

CHC 137d 29/May/24 18/Nov/24

Faux-plafond 10d 14/Oct/24 24/Oct/24

Revêtement sol 10d 29/May/24 08/Jun/24

Agencement 20d 06/Sep/24 30/Sep/24

Terminaux 11d 01/Oct/24 12/Oct/24

Peinture 10d 25/Oct/24 05/Nov/24

Revêtement souple 10d 07/Nov/24 18/Nov/24

R+24 226d 30/Jan/24 A 10/Dec/24

Front of House 162d 30/Jan/24 A 11/Sep/24

Chape 40d 30/Jan/24 A 16/Apr/24

Revêtement sol 61d 01/Mar/24 A 04/Jul/24

Revêtement mur 14d 29/May/24 13/Jun/24

Agencement 41d 03/Jun/24 29/Jul/24

Terminaux 16d 27/Jul/24 16/Aug/24

Peinture 15d 10/Aug/24 30/Aug/24

Revêtement souple 15d 26/Aug/24 11/Sep/24

CHC 130d 05/Jul/24 10/Dec/24

Faux-plafond 10d 05/Nov/24 16/Nov/24

Revêtement sol 10d 05/Jul/24 16/Jul/24

Agencement 19d 01/Oct/24 22/Oct/24

Terminaux 11d 23/Oct/24 04/Nov/24

Peinture 10d 18/Nov/24 28/Nov/24

Revêtement souple 10d 29/Nov/24 10/Dec/24

R+25 210d 03/Feb/24 A 23/Nov/24

Remaining Level of Effort Actual Work Critical Remaining Work Date Revision Checked Approved
Page 5 of 7
17/Apr/24 Rebaseline version K BST
Actual Level of Effort Remaining Work Milestone
Tour Mohammed VI6 : Programme logements
Planning Level 3

Activity ID Activity Name Original Duration Start Finish WF-Lot tour 2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
Front of House 160d 03/Feb/24 A 13/Sep/24

Chape 36d 03/Feb/24 A 16/Apr/24

Revêtement sol 115d 09/Feb/24 A 06/Jul/24

Revêtement mur 14d 29/May/24 13/Jun/24

Agencement 57d 16/May/24 03/Aug/24

Terminaux 28d 05/Aug/24 09/Sep/24

Peinture 21d 19/Aug/24 13/Sep/24

Revêtement souple 10d 02/Sep/24 12/Sep/24

CHC 114d 08/Jul/24 23/Nov/24

Faux-plafond 10d 19/Oct/24 30/Oct/24

Revêtement sol 10d 08/Jul/24 18/Jul/24

Agencement 20d 19/Sep/24 11/Oct/24

Terminaux 6d 12/Oct/24 18/Oct/24

Peinture 10d 31/Oct/24 12/Nov/24

Revêtement souple 10d 13/Nov/24 23/Nov/24

R+26 228d 07/Feb/24 A 21/Dec/24

Front of House 161d 07/Feb/24 A 18/Sep/24

Chape 28d 13/Feb/24 A 16/Apr/24

Revêtement sol 143d 07/Feb/24 A 07/Aug/24

Revêtement mur 14d 05/Jul/24 20/Jul/24

Agencement 15d 22/Jul/24 10/Aug/24

Terminaux 16d 09/Aug/24 30/Aug/24

Peinture 18d 26/Aug/24 14/Sep/24

Revêtement souple 10d 06/Sep/24 18/Sep/24

CHC 249d 14/Feb/24 A 21/Dec/24

Faux-plafond 229d 14/Feb/24 A 28/Nov/24

Revêtement sol 90d 27/Apr/24 22/Aug/24

Agencement 19d 12/Oct/24 02/Nov/24

Terminaux 11d 04/Nov/24 16/Nov/24

Peinture 10d 29/Nov/24 10/Dec/24

Revêtement souple 10d 11/Dec/24 21/Dec/24

R+27 217d 07/Feb/24 A 05/Dec/24

Remaining Level of Effort Actual Work Critical Remaining Work Date Revision Checked Approved
Page 6 of 7
17/Apr/24 Rebaseline version K BST
Actual Level of Effort Remaining Work Milestone
Tour Mohammed VI6 : Programme logements
Planning Level 3

Activity ID Activity Name Original Duration Start Finish WF-Lot tour 2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
Front of House 165d 12/Feb/24 A 27/Sep/24

Chape 19d 23/Feb/24 A 16/Apr/24

Revêtement sol 140d 12/Feb/24 A 08/Aug/24

Revêtement mur 13d 08/Jul/24 22/Jul/24

Agencement 26d 23/Jul/24 27/Aug/24

Terminaux 18d 17/Aug/24 09/Sep/24

Peinture 17d 02/Sep/24 21/Sep/24

Revêtement souple 12d 13/Sep/24 27/Sep/24

CHC 241d 07/Feb/24 A 05/Dec/24

Faux-plafond 221d 07/Feb/24 A 12/Nov/24

Revêtement sol 61d 03/Jun/24 23/Aug/24

Agencement 20d 01/Oct/24 23/Oct/24

Terminaux 6d 24/Oct/24 30/Oct/24

Peinture 10d 13/Nov/24 23/Nov/24

Revêtement souple 10d 25/Nov/24 05/Dec/24

R+28 247d 18/Jan/24 A 27/Dec/24

Front of House 205d 18/Jan/24 A 30/Oct/24

Chape 22d 03/Jun/24 04/Jul/24

Faux-plafond 50d 18/Jan/24 A 01/Jun/24

Revêtement sol 107d 27/Apr/24 11/Sep/24

Revêtement mur 13d 08/Aug/24 26/Aug/24

Agencement 12d 04/Sep/24 19/Sep/24

Terminaux 26d 19/Sep/24 18/Oct/24

Peinture 25d 02/Oct/24 30/Oct/24

Revêtement souple 10d 14/Oct/24 24/Oct/24

CHC 167d 03/Jun/24 27/Dec/24

Faux-plafond 147d 03/Jun/24 04/Dec/24

Revêtement sol 57d 15/Jul/24 24/Sep/24

Agencement 19d 24/Oct/24 15/Nov/24

Terminaux 6d 16/Nov/24 22/Nov/24

Peinture 10d 05/Dec/24 16/Dec/24

Revêtement souple 10d 17/Dec/24 27/Dec/24

Remaining Level of Effort Actual Work Critical Remaining Work Date Revision Checked Approved
Page 7 of 7
17/Apr/24 Rebaseline version K BST
Actual Level of Effort Remaining Work Milestone