Professional Documents
Culture Documents
Programme Logements - Planning Travaux Level 3
Programme Logements - Planning Travaux Level 3
Programme Logements - Planning Travaux Level 3
Planning Level 3
Activity ID Activity Name Original Duration Start Finish WF-Lot tour 2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
262d 28/Dec/23 A 27/Dec/24
Master Planning
Master Schedule 262d 28/Dec/23 A 27/Dec/24
Remaining Level of Effort Actual Work Critical Remaining Work Date Revision Checked Approved
Page 1 of 7
17/Apr/24 Rebaseline version K BST
Actual Level of Effort Remaining Work Milestone
Tour Mohammed VI6 : Programme logements
Planning Level 3
Activity ID Activity Name Original Duration Start Finish WF-Lot tour 2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
Front of House 50d 23/Apr/24 01/Jul/24
Remaining Level of Effort Actual Work Critical Remaining Work Date Revision Checked Approved
Page 2 of 7
17/Apr/24 Rebaseline version K BST
Actual Level of Effort Remaining Work Milestone
Tour Mohammed VI6 : Programme logements
Planning Level 3
Activity ID Activity Name Original Duration Start Finish WF-Lot tour 2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
R+19 224d 28/Dec/23 A 05/Nov/24
Remaining Level of Effort Actual Work Critical Remaining Work Date Revision Checked Approved
Page 3 of 7
17/Apr/24 Rebaseline version K BST
Actual Level of Effort Remaining Work Milestone
Tour Mohammed VI6 : Programme logements
Planning Level 3
Activity ID Activity Name Original Duration Start Finish WF-Lot tour 2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
Revêtement sol 57d 10/Jan/24 A 06/May/24
Remaining Level of Effort Actual Work Critical Remaining Work Date Revision Checked Approved
Page 4 of 7
17/Apr/24 Rebaseline version K BST
Actual Level of Effort Remaining Work Milestone
Tour Mohammed VI6 : Programme logements
Planning Level 3
Activity ID Activity Name Original Duration Start Finish WF-Lot tour 2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
Front of House 167d 18/Jan/24 A 06/Sep/24
Remaining Level of Effort Actual Work Critical Remaining Work Date Revision Checked Approved
Page 5 of 7
17/Apr/24 Rebaseline version K BST
Actual Level of Effort Remaining Work Milestone
Tour Mohammed VI6 : Programme logements
Planning Level 3
Activity ID Activity Name Original Duration Start Finish WF-Lot tour 2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
Front of House 160d 03/Feb/24 A 13/Sep/24
Remaining Level of Effort Actual Work Critical Remaining Work Date Revision Checked Approved
Page 6 of 7
17/Apr/24 Rebaseline version K BST
Actual Level of Effort Remaining Work Milestone
Tour Mohammed VI6 : Programme logements
Planning Level 3
Activity ID Activity Name Original Duration Start Finish WF-Lot tour 2024 2025
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
Front of House 165d 12/Feb/24 A 27/Sep/24
Remaining Level of Effort Actual Work Critical Remaining Work Date Revision Checked Approved
Page 7 of 7
17/Apr/24 Rebaseline version K BST
Actual Level of Effort Remaining Work Milestone