Professional Documents
Culture Documents
Samb Case File
Samb Case File
Counsel:
For the plaintiff: M/s Bell & Lee
For the defendant: M/s Chee Siah Le Kee & Partners
JUDGMENT
Introduction
Syarikat Air Melaka Berhad
pg 2 v. Sunpower Malaysia Manufacturing Sdn Bhd [2020] MLRHU 57
[1] In encl 7 (the Application) the Defendant applied to strike out the Plaintiff's
Writ of Summons and Statement of Claim under O 18 r 19(1) Rules of Court
2012 ("ROC 2012") anchored on what the Defendant strenuously argued a
claim that is barred by limitation and ultra vires the relevant statute. The
Plaintiff as is expected assiduously resisted the Application.
Cause Papers/Affidavits
[2] The parties wasted no efforts in fling rival affidavits. By way of preliminary
observation, it could be stated that the Application herein involves complex set
of facts, in the sense that there are no common grounds; that almost all the
facts are interpreted differently by the respective party and there are multitude
of documents.
[3] For convenience the cause papers relevant to the Application are as follows
but I must also state for clarification that the Plaintiff, in response to one of the
affidavits filed by the Defendant, had files another application, in encl 20,
dated 16 October 2018, essentially to strike out certain part of the averments in
the Defendant's affidavit dated 7 May 2018 on the basis that the averments
contained hearsay evidence. That application was made under O 41 r 5 ROC
2012. Enclosure 20 was allowed in part and I had dealt with that separately
and given my reasons for arriving at the decision.
(d) the Defendant's Notice of Application dated 7 May 2018 for the
striking out (hereinafter referred to as the "Defendant's Striking Out
Application or the Application");
Background Fact.
Valley. For the purposes of its factory, the Defendant needed a supply of both
raw water and treated water.
[6] The Plaintiff has pleaded that the State Government of Melaka had agreed
on 21 January 2008 to provide raw water and treated water at "special water
tariff" to the Defendant. Those rates were to be applicable for 10 years.
Permission was also given for the Defendant to carry out its own drilling
within the factory area to procure raw water.
[7] Central to the Application are the questions (1) whether the Plaintiff is
entitled in law to charge the costs of building of certain infrastructure to 5 the
Defendant and (2) whether the claim are barred by limitation.
Defendant's Submission
[8] The Plaintiff pleads that it claims is for "Payment for the Plaintiff's
Services" in para 16 as a claim under Enactment 20/1971 (repealed on 1 July
2006), Enactment 10/2002 and Water Services Industry Act 2006 (WASIA),
as well as is Enactment 9/2014. As regards to the last Enactment of 9/2014 it
would appear that it has no relevance to the claim as first, the Enactment came
into force well after the Plaintiff had agreed to supply both treated and raw
water to the Defendant in December 2007. Secondly, the requirement for
supply of water was initiated and agreed in December 2007. At that time, the
applicable legislation was only Enactment 10/2002. Enactment 20/1971 is
also irrelevant as it was repealed on 1 July 2006. This case relates to events
that commenced in 2007.
[9] The Defendant submits that the Plaintiff's claim for each part of the works
are barred by limitation pursuant to s 6(1)(d) of the Limitation Act 1953, ie
actions to recover any sum recoverable by virtue of any written law other than
a penalty or forfeiture or of a sum by way of penalty or forfeiture shall not be
brought after the expiration of 6 years from the date on which the cause of
action accrued. Even if the Plaintiff is entitled to bring its alternative claims
against the Defendant, those alternative claims, are also barred by limitation
pursuant to s 6(1)(a) of the Limitation Act 1953, ie actions founded on a
contract or on tort shall not be brought after the expiration of 6 years on which
the cause of action accrued. Where a suit is brought outside the limitation
period, it can be struck out on the ground that it is frivolous and vexatious
(limb (b) of O 18 r 19(1)) and an abuse of process (limb (d) of O 18 r 19(1)).
[10] The Defendant also contended that that Plaintiff's pleaded alternative
claims against the Defendant, namely is not sustainable for the following
reasons:-
Plaintiff's Submission
[11] The Defendant's contention that the Minister does not have any power to
make regulations that allow for the imposition of capital contribution based on
water demand as provided under the 2014 Regulations but instead must only
be in relation to connection to public mains and consequently the 2014
Regulations in this context ultra vires WASIA was totally an ultra vires
argument.
[12] On issue of limitation, the Plaintiff right may have had arisen before the
infrastructure works were awarded to contractors because the costs would
have been fixed by that time. Defendant further contends in para 60 of
Defendant's Submissions that since Plaintiff's position is that each request
constituted fresh request, then Plaintiff's own pleading shows that each alleged
request was separate and distinct. It is submitted that the above statement by
Defendant is a clear example of misapplication and misapprehension of the
established principles of law. The Plaintiff will demonstrate that each time
Defendant had substantially changed its positions and stands, it would amount
Syarikat Air Melaka Berhad
pg 6 v. Sunpower Malaysia Manufacturing Sdn Bhd [2020] MLRHU 57
to a new request. Consequently, the change would then reset the limitation
period. Therefore, this Civil Suit is filed well within the limitation period.
[13] On issue of unjust enrichment, the Plaintiff has also brought the claim of
unjust enrichment against Defendant. It is submitted that all the works that
were carried out are essentially done pursuant to statutory duties imposed by
statutes, enactments and/or subsidiary legislations.
[14] On the issue of s 71 of the Contracts Act, the Plaintiff submitted that s 71
ought to be construed widely and should therefore be applied in this case.
With respect to the first requirement that the acts 'must be lawful', all the
works that were carried out are essentially done pursuant to statutory duties
imposed by statutes, enactments and/or subsidiary legislations. Besides,
claims pursuant to s 71 of Contracts Act 1950 fall within the scope of s 6(1)(d)
of the Limitation Act. As such, the limitation period applicable is 6 years.
Therefore, the accrual of action pursuant to statutory claims within s 6(1)(d) of
the Limitation Act 1950.
Finding Of Court
[16] I had in the preceding paragraphs outlined what in essence is the claim as
well as the underlying defence in resisting the claim. The application before
me is one of a striking out application only where the role of the court in
determining the application is rather trite. The principles of law in relation to
striking out application are clear that only in plain and obvious cases should
recourse be had to the summary process under O 18 r 19. As long as the
statement of claim on the particulars discloses some cause of action, or raise
some question fit to be decided by a judge, the mere fact that the case is weak
and is not likely to succeed is no ground for striking it out (see Bandar Builder
Sdn Bhd & 2 Ors v. United Malayan Banking Corporation Bhd [1993] 1 MLRA
611; [1993] 3 MLJ 36; [1993] 4 CLJ 7; [1993] 2 AMR 1969, Pertamina v.
Kartika Ratna Thahir & Ors [1982] 1 MLRH 669; [1983] 1 MLJ 136). In
Seruan Gemilang Makmur Sdn Bhd v. Kerajaan Negeri Pahang Darul Makmur &
Anor [2016] 2 MLRA 263; [2016] 3 MLJ 1; [2016] 3 CLJ 1; [2016] 2 AMR
795 the relevant principles are that thus:
[26] The tests for striking out application under O 18 r 19 of the ROC,
as adopted by the Supreme Court in Bandar Builder are, inter alia, as
follows:
[27] The Court of Appeal, in Sivarasa Rasiah & Ors v. Che Hamzah
Che Ismail & Ors [2012] 1 MLRA 255; [2012] 1 MLJ 473; [2012] 1
CLJ 75, had adopted the well settled principle of striking out in the
following passage:
[28] The basic test for striking out as laid down by the Supreme Court
in Bandar Builder is that the claim on the face of it must be 'obviously
unsustainable'. The stress is not only on the word 'unsustainable' but
also on the word 'obviously' ie the degree of unsustainability must
appear on the face of the claim without having to go into lengthy and
mature consideration in detail. If one has to go into lengthy and
mature consideration in detail of the issues of law and/or fact, then
the matter is not appropriate to be struck out summarily. It must be
determined at trial.
[29] The established rule on this point is that the court should not
examine the evidence in this summary proceedings in such a way as to
amount to conducting a trial on the conflicting affidavit evidence. As
rightly said by Lord Diplock in the House of Lords in American
Cyanamid Co v. Ethicon Ltd [1975] AC 396 at p 407:
... The court no doubt must be satisfied that the claim is not
frivolous or vexatious; in other words, that there is a serious
question to be tried.
[30] This passage was cited with approval by the Privy Council in a
Malaysian case of Eng Mee Yong & Ors v. Letchumanan [1979] 1
MLRA 143; [1979] 2 MLJ 212.
[17] I have given anxious consideration to the issues raised by the parties
which include:-
[18] At this juncture it is my considered opinion and I so hold that the legal
issues are connected and intertwine with the facts that are hotly contested and
thus this is not a suitable case for this Court to exercise its power to strike out
the claim. In short, this is not straightforward case where the Court could be
satisfied to hold that the claim is obviously unsustainable. The Plaintiff thus
should not be prevented from having its day in court to prove its case.
[19] The Defendant had raised a pertinent issue of the claim being ultra vires
the statutes. This argument at first blush appears to be a straightforward
argument but having studied the affidavits, this issue cannot be decided in
vacuum. It is again connected to the facts and that it is complex legal issue
where a decision could be taken upon a mature argument after finding of facts
are made. It will involve a study of the developments in the various
Enactments and Regulations and the interplay between the Enactments and
WASIA and the regulations made thereunder.
[20] I should perhaps add that the alternative claims though contended by the
Defendant as being barred by limitation period, had however raised to certain
issue in relation to one's duty and liability where the evidence of the witness
through full trial should be heard and decided by this Court. Furthermore,
there are many other issues raised by the Plaintiff that warrant a full trial
through calling of the witness to decide on the Defendant's' duties and
liabilities. The example can be seen in several paragraphs stated in the
Plaintiff's Statement of Claims as follows:
[21] On this issue of implied contract, I find that the question whether there is
an implied contract should be determined in full trial - see Kondisi Utama Sdn
Bhd v. Baltic Agencies Pte Ltd and another appeal [2019] 1 MLRA 1; [2019] 1
MLJ 181; [2018] 9 CLJ 561 where the following passages are instructive:-
[74] The Court of Appeal held that 'these contracts are contracts
implied in fact. A contract implied in fact is not expressed by the
parties, but rather suggested from the facts and circumstances that
indicate a mutual intention to contract. Circumstances exist that,
according to the ordinary course of dealing and common
understanding, demonstrate such an intent that is sufficient to support
a finding of implied contract. We found this to be the case based on
the evidence before the court'. The Court of Appeal quoted the
following passage from Chitty's on Contract:
[75] Was the Court of Appeal correct in making the finding that
implied contracts subsisted between the parties? Unfortunately in their
broad grounds the Court of Appeal did not explain the reasons for
their finding. Therefore, we need to examine the relevant oral and
documentary evidence, in particular the conduct of the parties, in
order to answer that question.
...
...
[128] Based on our analysis above, we are unanimous in our view that
a contract had come into existence between EPIC and the informal
joint venture partnership of Kondisi and Baltic. That joint venture
clearly existed and EPIC and Kondisi had clearly admitted its
existence by the actions taken by Ramli and Amarjeet.
[129] We also find that the evidence shows that EPIC had breached
that contract by offering Kondisi the contract by the letter dated 16
October 2011 and Kondisi had breached its joint venture agreement
with Baltic by accepting that offer on 17 October 2011 and
Syarikat Air Melaka Berhad
[2020] MLRHU 57 v. Sunpower Malaysia Manufacturing Sdn Bhd pg 11
[22] On quantum meruit, the cases of Mega Mayang M & E Sdn Bhd v. Utama
Lodge Sdn Bhd and another appeal [2018] MLRAU 506, Tanjung Teras Sdn Bhd
v. Kerajaan Malaysia [2015] MLRAU 468; [2015] 9 CLJ 1002 and Syarikat
Binaan Utara Jaya (a firm) v. Koperasi Serbaguna Sungai Glugor Bhd [2008] 2
MLRA 809; [2009] 2 MLJ 546; [2009] 1 CLJ 786 are relevant and in the latter
case the foilIwing observation is pertinent:-
[41]... A claim in quantum meruit would be made on the basis that the
respondent employer had derived a benefit from the work done by the
appellant contractor and; if this is so, a reasonable remuneration has to
be paid to the contractor...
[23] In Crystal Realty Sdn Bhd v. Wary Holdings Sdn Bhd [2000] 5 MLRH 745
the Court held
So, the question is not when the valuation reports were made but
when the cause of action arose and that was when the Plaintiff had
performed the works upon which he claimed quantum meruit.
[24] It can also be seen from one of the defences mounted by the Defendant is
that there is purported representation that no payment will be due from the
Defendant.
[26] These questions remained unanswered at this stage and the proper place
for unraveling these issues will be the trial.
Conclusion
[27] In conclusion this Court holds that the Plaintiff's claim as disclosed in the
Writ and Statement of Claim is not 'on the face of it obviously unsustainable'
or that this is a case where on the face of it is suitable to be struck out under O
18 r 19 of the ROC 2012.
[28] I also hold that there are issues of facts or law and mixed of facts and law
that could be resolved upon a full trial.
[30] I so order.