STATICAL CALCULATION

For
Slab Formwork System

Main Contractor
CANAR

Project

SMALL BOAT HARBOURS PROJECT

Prepared by

M.A.

Page 1 of 19
GENERAL REMARKS

1. Permissible Loads
Plywood:

Permissible Moment = 0.456 kNm/m

Permissible Shear force = 6.340 kN/m

Permissible deflection = span / 270

Secondary Beam

H20 TIMBER BEAM

Permissible Moment = 5.00 kNm

Permissible Shear force = 11.00 kN

Permissible deflection = span / 550

Primary Beam

DOUBLE H 20 TIMBER BEAM

Permissible Moment = 10.00 kNm

Permissible Shear force = 22.00 kN

Permissible deflection = span / 550

TG60 Tower AR-TG-C-02-0 :


- one frame 0.71 m
- Two frames 1.00m

Tower capacity for 30 cm jacks extension under the beam = 53.2 kN


Tower capacity for 65 cm jacks extension under the slab = 36.6 kN

Page 2 of 19
2.LOADS
Static calculation for bending moment, shear force and deflection are done using TIPOS Beam.

Loads

-Concrete Load, b 26 kN/m3

-Formwork Load, g 0.40 kN/m2

i) 4 Lm of H20 beam/sqm = 4*6kg = 24 kg/ sqm2, Supplied by site

ii) 13kg of plywood/sqm(Assumed wt of ply, supplied by site

-Live Load, p 0.20 x b, 1.5 ≤ p ≤ 5.0kN/m2

Supporting scaffolding according to DIN 4421 generallay 20% of the fresh concrete dead load at

least 1.5 kN/m2, but not more than 5.0 kN/m2

-Dynamic Load, d = 25% of Live load

Total Load, q = b + g + p + d

Page 3 of 19
STATIC CALCULATION

Page 4 of 19
3.Slab bottom formwork - 275 mm slab
Load Calculation- Slab Depth = 0.275 m

- Formwork load,g = 0.4 kN/m2

- Concrete load,b = 26kN/m3 x d(m)

=26 X 0.275

=7.15 kN/m2

- Live load = 20%of concrete load (b), 1.5 ≤ p ≤ 5.0kN/m2

= 1.43 kN/m2

- Dynamic Load,d = 25% of live load

= 0.36 kN/m2

Total Load, q = 7.15+ 1.43+ .36

= 8.95 kN/m2

Page 5 of 19
3.a. Plywood 18mm
Distributed load on the plywood (w) = 8.95 kN/m2

Spacing between the secondary (L) = 488 mm

Maximum bending moment = 0.1 x q x L2

= 0.1 x 8.95 x (0.488)2

= 0.21 kNm/m

Permissible bending moment = 0.456 kNm/m


O.K.

Maximum shear force = [0.525(L-b-t)/L] W x L

= [0.525(0.488 -0.08-0.018)/0.488] x8.95 x 0.488

Permissible shear force = 3.78 kN/m

O.K.

Maximum deflection =0.0068(wl4) / EI

=0.0068((8.95 x 0.4884)/3.26)

= 1.06 mm

Permissible deflection = Span / 270 = 488 /270

= 1.807 mm

O.K.

Page 6 of 19
3.b.a - H20-2.90M SECONDARY-TIMBER BEAM
Distributed load = 8.95 kN/m2

Spacing between the secondary beams = 488 mm

Total load on secondary beam = 8.95 x 0.488

= 4.37 kN/m

From the analysis:


-Maximum bending moment = 0.67 kNm

Permissible bending moment = 5.00 kNm

Maximum bending moment less than permissible. Hence safe

-Maximum shear force = 3.13 kN

Permissible shear force = 11.00 kN

Maximum shear less than permissible. Hence safe

-Maximum deflection = 0.3 mm


Permissible deflection = 1250/ 550 = 2.27 mm
Maximum deflection less than permissible. Hence safe

Page 7 of 19
3.c.b - H20-5.90M PRIMARY-TIMBER BEAM
Max reaction on the primary =5.97 kN

Spacing between the secondary beams =488 mm

-Max load on primary beam = 5.97 / 0.488


= 12.24 kN/m

From the analysis:

- Maximum bending moment = 4.51 kNm

Permissible bending moment = 10.00 kNm

Maximum bending moment less than permissible. Hence safe

- Maximum shear force = 14.7 kN

Permissible shear force = 22.00 kN

Maximum shear less than permissible. Hence safe


- Maximum deflection = 1.5 mm

Permissible deflection = span / 550


= 2.07 / 550
= 3.77 mm
Maximum deflection less than permissible. Hence safe

Page 11 of 19
3.d.Layher TG60 Tower AR-TG-C-02-0
- Maximum reaction on the tubes = 28.3 kN

Permissible load on the tubes = 36.6 kN

Maximum reaction is less than permissible. Hence safe

Page 12 of 19
4.Beam bottom formwork – 600X600 mm Beam
Load Calculation

- Formwork load,g = 0.4 kN/m2

- Concrete load,b = 26kN/m3 x d(m)


=26 x600

= 15.6 kN/m2

- Live load = 20%of concrete load (b), 1.5 ≤ p ≤ 5.0kN/m2

= 3.12 kN/m2

- Dynamic Load,d = 25% of live load


=0.78 kN/m2

Total Load, q = 0.4 + 15.6 + 3.12 + 0.78

= 19.9 kN/m2 from the beam.

Page 13 of 19
Plywood 18mm

Distributed load on the plywood (w) = 19.9 kN/m2

Spacing between the secondary (L) = 0.35 mm

Maximum bending moment = 0.1 x q x L2

= 0.1 x 19.9 x (0.35)2

= 0.244 kNm/m
Permissible bending moment = 0.456
O.K.
kNm/m
Maximum shear force = [0.525(L-b-t)/L] W x L

= [0.525(0.35 -0.08-0.018)/0.350] x19.9 x 0.35


= 2.633 kN/m
Permissible shear force = 6.340 kN/m
O.K.

Maximum deflection =0.0068(wl4) / EI

=0.0068((19.9 x 0.354)/3.26)

= 0.63 mm
Permissible deflection = Span / 270
= 350 /270
= 1.30 mm
O.K.

Page 14 of 19
4.a.H20- 1.5 M SECONDARY BEAM
Distributed load from the beam = 19.9 kN/m2

Spacing between the secondary beams = 350 mm

Total load from the beam 600x600 mm = 19.9 x 0.35 =6.97 kN/m
Total load from the Slab 275 mm = 8.95 x 0.35 =3.13 kN/m

-Maximum bending moment = 0.73kNm

Permissible bending moment = 5.00 kNm

Maximum bending moment less than permissible. Hence safe

-Maximum shear force = 2.55 kN

Permissible shear force = 11.00 kN

Maximum shear less than permissible. Hence safe

-Maximum deflection = 0.2 mm

Permissible deflection = 109 / 550 = 1.96 mm


Maximum deflection less than permissible. Hence safe

Page 15 of 19
4.b.Primary beam – DOUBLE H 20 TIMBER BEAM
Max reaction on the primary 3.20= kN Spacing

between the secondary beams = 350mm

-Max load on primary beam = 3.20/0.35


= 9.15 kN/m

From the analysis:

- Maximum bending moment = 3.20 kNm

Permissible bending moment = 5.0 kNm

Maximum bending moment less than permissible. Hence safe

- Maximum shear force = 10.67 kN

Permissible shear force = 22.00 kN

Maximum shear less than permissible. Hence safe

- Maximum deflection = 1.1mm

Permissible deflection = 2070 / 550

= 3.77

Maximum deflection less than permissible. Hence safe

Page 16 of 19
5.d.Layher TG60 Towers
- Maximum reaction on the Supports = 15.86 kN

Permissible load on the Supports = 53.2 kN

Maximum deflection less than permissible. Hence safe

No. of Towers needed for one floor = (47 x4 +5) for Slab shoring + (16X42)/3
= 417 Tower

Page 17 of 19
APPENDIX - 1

Page 18 of 19
Page 19 of 19