OFFICE FIT OUT/ GENERAL CONSTRUCTION

16F, World Plaza BGC

WEEKLY ACCOMPLISHMENT REPORT


as of August 1-5, 2023
PROJECT HIGHLIGHTS :
1. CEILING REPAINT
2. INSTALLATION OF WIRE FOR TABLES/DESK
3. INSTALLATION OF DRY WALL WITH INSULATION
4. REMOVAL OF SLATTED WALLS
AVERAGE MANPOWER
PROJECT ENGINEER - 1
FOREMAN – 1
PAINTER – 4
INSTALLER – 2
ELECTRICIAN - 3
LABOR / HOUSEKEEPING– 1
TOTAL - 12
1. CEILING REPAINT WORK PROGRESS
4

1 2 3
5
8 7 6
PROGRESS PHOTO REPORT
1 2

3 4
PROGRESS PHOTO REPORT
5 6

7 8
2. INSTALLATION OF WIRE FOR TABLES / DESK

1 2 3

4
PROGRESS PHOTO REPORT
1 2

3 4
3. INSTALLATION OF DRY WALL
PROGRESS PHOTO REPORT
4. REMOVAL OF SLATTED WALLS

1 2

4
PROGRESS PHOTO REPORT
1 2

3 4
LOOKAHEAD OF ACTIVITIES
• MOCK UP OF FLOORING REPAIR AT BREAKOUT AREA 1 & 2
• PREPARATION OF WALL AND COLUMN PAINTING (NOVEMBER STORM & DOVE WHITE)
• INSTALLATION OF OUTLETS
• REPLACEMENT OF LAMINATE
• REPLACEMENT OF FAUCET (TOILET & KITCHEN)
• PREPARATION FOR GLASS WALL INSTALLATION
• PREPARATION FOR STUCCO GRAY-SCALE PAINT
• MOVING OF EXISTING LIGHTS
DELIVERED MATERIALS
1. WALL STUDS
2. WALL TRACKS
3. ROCKWOOL INSULATION
4. WALL ANGLE
5. BLUE SACK
6. GYPSUM BOARD 9MM 4X8 FT
7. DURAFLEX WIRE
8. BOYSEN FLAT LATEX
9. ALUMINUM LADDER
10. BORAL COMPOUND
SITE CONCERNS

• FINAL ELEVATION OF DRY WALL AT PRIVATE OFFICE 4


• FINAL COLOR OF VARNISH FOR WOOD SLATS
• CONFIRMATION OF INSTALLATION OF OUTLETS AT OPEN WORKSPACE / TRAINING AREA