Standard Rate Analysis for Site Specific Items of Schedule 1 of the BOQ

BOQ Item No. 1001

(Please also refer the procedure for estimation of rate for this item)

(based on item no. 013120 of USSOR - Analysis of Rates (IR) and suitably modified with use of carriage and labour rates of
CPWD)

S. No. Description Unit Quantity Rate Amount Remarks


Details of cost for 1 cum
MATERIALS &
A TRANSPORTATION:
This rate should include cost of earth
to be paid to the land owner and
royalty and any other levy/tax.
1 Good Earth cum 1 75.00 75.00 Prevailing rate of the project area to
be taken.

Hydraulic Excavator (3D) with This is based on item 2.6.1 of CPWD


2 day 0.004125 7000.00 28.88
driver and fuel Delhi DAR 2018
Rates based on item no. 1.1.2 of
Carriage of Materials rates (by
Transportation of earth by mechanical transport) of CPWD Delhi
mechanical means including DAR 2018. Contractor's profit &
3 loading and unloading for lead Cum 1.1 111.49 122.64 overhead @ 15% has been deducted
upto 1 km (10% extra qty taken from the CPWD rate.
for loose earth after excavation)

Fill in lead qty as per actuals. Rate is


based on item no. 1.1.2 of Carriage of
Materials rates by mechanical
transport of CPWD Delhi DAR 2018.
Deduct rate for 1 km lead from the
Extra for every km or part thereof rate for 5 km lead and divide by 4 for
4 for Lead beyond 1 km but upto 5 Km 0 16.90 0
km average rate per km. Contractor's
profit & overhead @ 15% has been
deducted from the CPWD rate. Rate
has been multiplied by 1.1 for
transposrt of loose soil ( 1 cum soil in
situ = 1.1 cum of loose earth).
Fill in lead qty as per actuals. Rates
based on item no. 1.1.2 of Carriage of
Materials rates by mechanical
transport of CPWD Delhi DAR 2018.
Contractor's profit & overhead @ 15%
has been deducted from the CPWD
Extra for every km or part thereof rate. Rate has been multiplied by 1.1
5 for Lead beyond 5 km but upto Km 0 14.54 0 for transposrt of loose soil ( 1 cum soil
10 km in situ = 1.1 cum of loose earth).

Extra for every km or part thereof


6 for Lead beyond 10 km but upto Km 0 12.08 0 -do-
20 km
Extra for every km or part thereof
7 Km 0 9.99 0 -do-
for Lead beyond 20 km
Rates based on item no. 2.31 of
CPWD Delhi DAR 2018. Contractor's
Clearing jungle including profit & overhead @ 15% has been
uprooting of rank vegetation, deducted from the CPWD rate.
grass, brush wood,
trees and saplings of girth up to
30 cm measured at a height of 1
8 m sqm 0.5 10.91 5.46
above ground level and removal
of rubbish up to a distance of 50
m
outside the periphery of the area
cleared.

Total 231.98
B LABOUR:
Rate taken from Item no. 0113 of
1 Chowkidar day 0.001 558 0.56 Basic rates (Labour) of CPWD Delhi
DAR 2018
2 Sundries (No rates reqd) LS 1 0.1 0.10

C Total 232.64
Add for water charges @ 1% (no
D LS 0.01 2.33
rate reqd)

E Add for Contractor's Profit and LS 0.15 35.25


overheads @15% (no rate reqd)

F Cost of 1 Cum 270.22 For lead within 1 km


Assuming that additional width of
Correction factor (Ce) for 50cm extra width: 50 cm shall be cut, out of which
part of the earth shall get wasted
Ce=1+{0.5*1/(B+4H+2D)} for New Line, and remaining shall be transported
Ce=1+{0.5*0.5/B} for Doubling/multipling, and used at other location.
Where Considering all the above, cost of
B=Finished top width of formation (Blanket top), 50% of additional earth (50 cm
H=Average Depth of Blanket layer, width) is being considered for
D=Average Earth Bank height (excluding blanket layer) arriving at the rate.

shrinkage allownace of 5%:

Apply correction factors Ce & Cs to Rate

={Rate in
row (F) i.e.
G Final Cost of 1 Cum 238.80} x Ce
x Cs
Say Round off to nearest Rupee

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest
available DAR of CPWD / IRUSSOR of Indian Railways

BOQ Item No. 1001(A)


(based on item no. 013120 of USSOR - Analysis of Rates (IR) and suitably modified with use of carriage and labour rates of
CPWD)

S. No. Description Unit Quantity Rate Amount Remarks


Details of cost for 1 cum
MATERIALS &
A TRANSPORTATION:
This rate should include cost of earth
to be paid to the land owner and
royalty and any other levy/tax.
1 Good Earth cum 1 75.00 75.00 Prevailing rate of the project area to
be taken.

Hydraulic Excavator (3D) with This is based on item 2.6.1 of CPWD


2 day 0.004125 7000.00 28.88
driver and fuel Delhi DAR 2018
Rates based on item no. 1.1.2 of
Carriage of Materials rates (by
Transportation of earth by mechanical transport) of CPWD Delhi
mechanical means including DAR 2018. Contractor's profit &
3 loading and unloading for lead Cum 1.1 111.49 122.64 overhead @ 15% has been deducted
upto 1 km (10% extra qty taken from the CPWD rate.
for loose earth after excavation)

Total 226.52
B LABOUR:
Rate taken from Item no. 0113 of
1 Chowkidar day 0.001 558 0.56 Basic rates (Labour) of CPWD Delhi
DAR 2012
2 Sundries (No rates reqd) LS 1 0.1 0.10

C Total 227.18
Add for water charges @ 1% (no
D LS 0.01 2.27
rate reqd)

E Add for Contractor's Profit and LS 0.15 34.42


overheads @15% (no rate reqd)

F Cost of 1 Cum 263.87 For lead within 1 km

Assuming that additional width of


Correction factor (Ce) for 50cm extra width: 50 cm shall be cut, out of which
part of the earth shall get wasted
Ce=1+{0.5*1/(B+4H+2D)} for New Line, and remaining shall be transported
Ce=1+{0.5*0.5/B} for Doubling/multipling, and used at other location.
Where Considering all the above, cost of
B=Finished top width of formation (Blanket top), 50% of additional earth (50 cm
H=Average Depth of Blanket layer, width) is being considered for
D=Average Earth Bank height (excluding blanket layer) arriving at the rate.

shrinkage allownace of 5%:

Apply correction factors Ce & Cs to Rate

={Rate in
row (F) i.e.
G Final Cost of 1 Cum 263.87} x Ce
x Cs
Say Round off to nearest Rupee

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest
available DAR of CPWD / IRUSSOR of Indian Railways

BOQ Item No. 1005

(based on item no. 013120 of USSOR - Analysis of Rates (IR) suitably modified with use of carriage and labour rates of CPWD
and item no. 16.78.3 of CPWD DAR for blending )

S. No. Description Unit Quantity Rate Amount Remarks


Details of cost for 1 cum
A MATERIALS & TRANSPORTATION:
Rate worked out assuming 80% moorum
and 20% fine sand in the blanketing
material. The proportioning depending
upon materials available at site will
change so as to obtain blanket as per
specs. Rate for moorum & fine sand taken
from Item no. 0810 & 0983 of Basic rates
(Materials) of CPWD Delhi DAR 2012
respectively i.e. 0.8x450+0.2x640 = Rs.
488/-. Rate includes cost of blanketing
1 Blanket material cum 1 488.00 488.00 materials to be paid to the land/quarry
owner and royalty and any other levy/tax.
Rate for the required blanket material as
prevailing in the project area to be taken.

Rates based on item no. 1.1.2 of Carriage


Transportation of blanketing of Materials rates (by mechanical
2 material by mechanical means Cum 1 71.98 71.98 transport) of CPWD Delhi DAR 2012.
including loading and unloading
for lead upto 1 km Contractor's profit & overhead @ 15% has
been deducted from the CPWD rate.
Fill in lead qty as per actuals. Rate is
based on item no. 1.1.2 of Carriage of
Materials rates by mechanical transport
Extra for every km or part thereof of CPWD Delhi DAR 2012. Deduct rate for
3 for Lead beyond 1 km but upto 5 Km 4 9.38 37.51
1 km lead from the rate for 5 km lead and
km
divide by 4 for average rate per km.
Contractor's profit & overhead @ 15% has
been deducted from the CPWD rate.
Fill in lead qty as per actuals. Rates based
on item no. 1.1.2 of Carriage of Materials
Extra for every km or part thereof rates by mechanical transport of CPWD
4 for Lead beyond 5 km but upto Km 5 8.02 40.09
10 km Delhi DAR 2012. Contractor's profit &
overhead @ 15% has been deducted from
the CPWD rate.
Extra for every km or part thereof
5 for Lead beyond 10 km but upto Km 0 6.60 0 -do-
20 km
Extra for every km or part thereof
6 Km 0 5.39 0 -do-
for Lead beyond 20 km
Rates based on item no. 1.1.2 of Carriage
of Materials rates (by mechanical
Extra for additional handling of transport) of CPWD Delhi DAR 2012.
7 blanketing material in case Cum 1 71.98 71.98 Contractor's profit & overhead @ 15% has
blending with Pug Mills is done been deducted from the CPWD rate. To
be ignored if blending with pug mills is
not done
Based on AOR of CPWD DAR item no.
16.78.3 considering Wet Mix Plant 60 TPH
hour @75 tonne capacity (Code - 0059),
Generator 100 KVA/125 KVA (code -
0070), Water Tanker 5 to 6 KL capacity 5
km lead with one trip per hour (Code -
Extra for mechanical blending in
8 Cum 1 141.00 141 0057 ), Front end loader 1 cum bucket
pug mills
capacity (incl POL) (Code – 0052), Tipper
10 tonne capacity( taking lead= 10
=450x10 =4500 t.Km Tipper -5 Cum (Code
– 0053) and Add 10 per cent of cost of
carriage to cover cost of loading and
unloading
Total 850.56
B LABOUR:

1 Beldar day 0.147 247 36.31 Rate taken from Item no. 0114 of Basic
rates (Labour) of CPWD Delhi DAR 2012

2 Coolie day 0.147 247 36.31 Rate taken from Item no. 0115 of Basic
rates (Labour) of CPWD Delhi DAR 2012

3 Bhisti day 0.020 260 5.20 Rate taken from Item no. 0101 of Basic
rates (Labour) of CPWD Delhi DAR 2012

4 Chowkidar day 0.0004 247 0.10 Rate taken from Item no. 0113 of Basic
rates (Labour) of CPWD Delhi DAR 2012

5 Sundries (No rates reqd) LS 1 0.05 0.05

C Total 928.53
Add for water charges @ 1% (no
D LS 0.01 9.29
rate reqd)

E Add for Contractor's Profit and LS 0.15 140.67


overheads @15% (no rate reqd)

F Cost of 1 Cum 1,078.49 For lead of 10 km and blending with Pug


Mills

Considering the fact that while


Correction factor (Ce) for 50 cm extra width:
cutting the extra 50 cm from bank,
excess blanketing material will be
Ce=1+{0.8*1/(B+2H)} for New Line,
get mixed with earth but the same
Ce=1+{0.8*0.5/B} for Doubling/Multipling,
shall be used as earth and
Where
therefore 20% cost of blanketing
B=Finished top width of formation (Blanket top),
material is considered to be
H=Average depth of Blanket layer
recovered by the contractor.

Case 2 : Blended material


Apply correction factors Ce & Cv to Rate

={Rate in
row (F) i.e.
G Final Cost of 1 Cum 1078.49} x
Ce x Cv
Say Round off to nearest Rupee
Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest
available DAR of CPWD / IRUSSOR of Indian Railways

BOQ Item No. 1007 (a)

(based on item no. 014051 of USSOR - Analysis of Rates (IR) and suitably modified with use of labour rates of CPWD-Delhi DSR
2016)

S. No. Description Unit Quantity Rate Amount Remarks


Details of cost for 100 sqm
A MATERIAL:
1 Grass Sods Sqm 100 40 4000.00 The rate is as per rates of item no.
014051 of USSOR - 2010

B LABOUR:
1 Beldar Day 1 368 368.00 The rate is as per basic labour rate of
item no. 0114 of CPWD Delhi DSR
2016.

2 Coolie Day 2 368 736 The rate is as per basic labour rate of
item no. 0115 of CPWD Delhi DSR
2016.

3 Bhisti Day 0.5 407 203.5 The rate is as per basic labour rate of
item no. 0101 of CPWD Delhi DSR
2016.

4 Sundries (No rates reqd) LS 11.55 1 11.55


Total for B 1319.05

C Total 5319.05
D Add for water charges @ 1% LS 0.01 53.19
Add for Contractor's Profit and
E LS 0.15 805.84
overheads @15%
Cost for 100 Sqm 6,178.08
Cost for 1 Sqm 61.78
Say 61.8

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest
available DAR of CPWD / IRUSSOR of Indian Railways

BOQ Item No. 1007 (b)

(based on item no. 014052 of USSOR - Analysis of Rates (IR) and suitably modified with use of labour rates of CPWD-Delhi DSR
2016)

S. No. Description Unit Quantity Rate Amount Remarks


Details of cost for 100 sqm
A MATERIAL:
Doob grass Sqm 100 25 2500.00 The rate is as per rates of item no.
014052 of USSOR - 2010

B LABOUR:
1 Beldar Day 3 368 1104.00 The rate is as per basic labour rate of
item no. 0114 of CPWD Delhi DSR
2016.

2 Coolie Day 4.39 368 1615.52 The rate is as per basic labour rate of
item no. 0115 of CPWD Delhi DSR
2016.

3 Sundries (No rates reqd) LS 6.6 1 6.60


Total for B 2726.12

C Total 5226.12
D Add for water charges @ 1% LS 0.01 52.26
Add for Contractor's Profit and
E LS 0.15 791.76
overheads @15%
Cost for 100 Sqm 6,070.14
Cost for 1 Sqm 60.70
Say 60.7

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest
available DAR of CPWD / IRUSSOR of Indian Railways

BOQ Item No. 1007 (c)

(based on item no. 014053 of USSOR - Analysis of Rates (IR) and suitably modified with use of labour rates of CPWD-Delhi DSR
2016)

S. No. Description Unit Quantity Rate Amount Remarks


Details of cost for 100 sqm
A MATERIAL:
Sarkanda/Sarpat Sqm 100 25 2500.00 The rate is as per rates of item no.
014053 of USSOR - 2010

B LABOUR:
1 Beldar Day 2.5 368 920.00 The rate is as per basic labour rate of
item no. 0114 of CPWD Delhi DSR
2016.

2 Coolie Day 2.5 368 920 The rate is as per basic labour rate of
item no. 0115 of CPWD Delhi DSR
2016.

3 Sundries (No rates reqd) LS 13.2 1 13.20


Total for B 1853.20

C Total 4353.20
D Add for water charges @ 1% LS 0.01 43.53
Add for Contractor's Profit and
E LS 0.15 659.51
overheads @15%
Cost for 100 Sqm 5,056.24
Cost for 1 Sqm 50.56
Say 50.6
Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest
available DAR of CPWD / IRUSSOR of Indian Railways
BOQ Item No. 1011

(based on item no. 193080 of USSOR - Analysis of Rates (IR) and suitably modified with use of carriage and labour rates of
CPWD)

S. No. Description Unit Quantity Rate Amount Remarks


Details of cost for 1 cum
A MATERIALS & TRANSPORTATION:
Rate for sand taken from Item no.
1 Fine sand (Zone-IV) cum 1 640.00 640.00 0983 of Basic rates (Materials) of
CPWD Delhi DAR 2012.

Rates based on item no. 1.1.5 of


Carriage of Materials rates (by
Transportation of sand by
mechanical means including mechanical transport) of CPWD Delhi
2 Cum 1 66.23 66.23
loading and unloading for lead DAR 2012. Contractor's profit &
upto 1 km
overhead @ 15% has been deducted
from the CPWD rate.
Fill in lead qty as per actuals. Rate is
based on item no. 1.1.5 of Carriage of
Materials rates by mechanical

Extra for every km or part thereof transport of CPWD Delhi DAR 2012.
4 for Lead beyond 1 km but upto 5 Km 4 8.63 34.52 Deduct rate for 1 km lead from the
km rate for 5 km lead and divide by 4 for
average rate per km. Contractor's
profit & overhead @ 15% has been
deducted from the CPWD rate.
Fill in lead qty as per actuals. Rates
based on item no. 1.1.5 of Carriage of
Materials rates by mechanical
Extra for every km or part thereof
5 for Lead beyond 5 km but upto Km 5 7.38 36.9 transport of CPWD Delhi DAR 2012.
10 km Contractor's profit & overhead @ 15%
has been deducted from the CPWD
rate.
Extra for every km or part thereof
6 for Lead beyond 10 km but upto Km 0 6.08 0 -do-
20 km
Extra for every km or part thereof
7 Km 0 4.96 0 -do-
for Lead beyond 20 km
Total 777.65
B LABOUR:
Rate taken from Item no. 0128 of
1 Mate day 0.01 260 2.60 Basic rates (Labour) of CPWD Delhi
DAR 2012

Rate taken from Item no. 0114 of


2 Beldar day 0.3 247 74.10 Basic rates (Labour) of CPWD Delhi
DAR 2012

C Total 854.35
Add for water charges @ 1% (no
D LS 0.01 8.54
rate reqd)

E Add for Contractor's Profit and LS 0.15 129.43


overheads @15% (no rate reqd)

Extra for compaction with


F cum 1 14 14.00
vibratory roller

Cost of 1 Cum 1,006.32 For lead of 10 km


Say 1,006 For lead of 10 km

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest
available DAR of CPWD / IRUSSOR of Indian Railways

BOQ Item No. 1025

(based on item no. 013120 of USSOR - Analysis of Rates (IR) suitably modified with use of carriage and labour rates of CPWD
and item no. 16.78.3 of CPWD DAR for blending )

S. No. Description Unit Quantity Rate Amount Remarks

Details of cost for 1 cum


A MATERIALS & TRANSPORTATION:

1 Blanket material cum 1 488 488 Rate worked out assuming 80%
moorum and 20% fine sand in the
blanketing material. The
proportioning depending upon
materials available at site will
change so as to obtain blanket as
per specs. Rate for moorum & fine
sand taken from Item no. 0810 &
0983 of Basic rates (Materials) of
CPWD Delhi DAR 2012 respectively
i.e. 0.8x450+0.2x640 = Rs. 488/-.
Rate includes cost of blanketing
materials to be paid to the
land/quarry owner and royalty and
any other levy/tax. Rate for the
required blanket material as
prevailing in the project area to be
taken.
2 Transportation of blanketing Cum 1 71.98 71.98 Rates based on item no. 1.1.2 of
material by mechanical means Carriage of Materials rates (by
including loading and unloading mechanical transport) of CPWD
for lead upto 1 km Delhi DAR 2012. Contractor's profit
& overhead @ 15% has been
deducted from the CPWD rate.

3 Extra for every km or part thereof Km 4 9.38 37.51 Fill in lead qty as per actuals. Rate
for Lead beyond 1 km but upto 5 is based on item no. 1.1.2 of
km Carriage of Materials rates by
mechanical transport of CPWD
Delhi DAR 2012. Deduct rate for 1
km lead from the rate for 5 km
lead and divide by 4 for average
rate per km. Contractor's profit &
overhead @ 15% has been
deducted from the CPWD rate.

4 Extra for every km or part thereof Km 5 8.02 40.09 Fill in lead qty as per actuals. Rates
for Lead beyond 5 km but upto based on item no. 1.1.2 of Carriage
10 km of Materials rates by mechanical
transport of CPWD Delhi DAR
2012. Contractor's profit &
overhead @ 15% has been
deducted from the CPWD rate.

5 Extra for every km or part thereof Km 0 6.6 0 -do-


for Lead beyond 10 km but upto
20 km
6 Extra for every km or part thereof Km 0 5.39 0 -do-
for Lead beyond 20 km
7 Extra for additional handling of Cum 1 71.98 71.98 Rates based on item no. 1.1.2 of
blanketing material in case Carriage of Materials rates (by
blending with Pug Mills is done mechanical transport) of CPWD
Delhi DAR 2012. Contractor's profit
& overhead @ 15% has been
deducted from the CPWD rate. To
be ignored if blending with pug
mills is not done
8 Extra for mechanical blending in Cum 1 141 141 Based on AOR of CPWD DAR item
pug mills no. 16.78.3 considering Wet Mix
Plant 60 TPH hour @75 tonne
capacity (Code - 0059), Generator
100 KVA/125 KVA (code - 0070),
Water Tanker 5 to 6 KL capacity 5
km lead with one trip per hour
(Code - 0057 ), Front end loader 1
cum bucket capacity (incl POL)
(Code – 0052), Tipper 10 tonne
capacity( taking lead= 10 =450x10
=4500 t.Km Tipper -5 Cum (Code –
0053) and Add 10 per cent of cost
of carriage to cover cost of loading
and unloading

Total 850.56
B LABOUR: Quantities of each type of labour
taken from item of Delhi CPWD
and additional quantity of 0.153
for Beldar has been taken for
stacking of blanketing material

1 Beldar day 0.3 247 74.1 Rate taken from Item no. 0114 of
Basic rates (Labour) of CPWD Delhi
DAR 2012
2 Coolie day 0.147 247 36.31 Rate taken from Item no. 0115 of
Basic rates (Labour) of CPWD Delhi
DAR 2012
3 Bhisti day 0.02 260 5.2 Rate taken from Item no. 0101 of
Basic rates (Labour) of CPWD Delhi
DAR 2012
4 Chowkidar day 0.0004 247 0.1 Rate taken from Item no. 0113 of
Basic rates (Labour) of CPWD Delhi
DAR 2012
5 Sundries (No rates reqd) LS 1 0.05 0.05
C Total 966.32
D Add for water charges @ 1% (no LS 0.01 9.29
rate reqd)
E Add for Contractor's Profit and LS 0.15 140.67
overheads @15% (no rate reqd)

F Cost of 1 Cum 1122.38 For lead of 10 km and blending


with Pug Mills
Say 1122 Round off to nearest Rupee

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest
available DAR of CPWD / IRUSSOR of Indian Railways
Standard Rate Analysis for Site Specific Items of Schedule 2A of the BOQ

BOQ Item No. 2003


(based on item no. 4.1.6 of CPWD DAR 2021 )
S. No. Description Unit Quantity Rate Amount Remarks
Details of cost for 1.00 cum
MATERIALS:
The material rates are
exclusive of contractor's profit,
Stone Aggregate (Single size) : 40 mm
over heads and GST but
nominal size (0.7 cum -7.5% for voids i.e.
1 cum 0.65 1478.19 960.82 inclusive of royalty and
0.05=0.65 cum) at site of work including
Carriage charges etc. (add
carriage charges
rates of Code No. 0293 &
2206)
Stone Aggregate (Single size) : 20 mm
-do- (add rates of Code No.
2 nominal size at site of work including cum 0.24 1563.93 375.34
0295 & 2202)
carriage charges
Fine sand (zone IV) at site of work -do- (add rates of Code No.
3 cum 0.47 1063.93 500.05
including carriage charges 0983 & 2203)
The rates are exclusive of
GST, contractors profit & OH
LABOUR:
but inclusive of wages for
weekly day of rest

labour; of pouring, consolidating & curing

4 Mason day 0.1 749 74.90 Code No 0155


5 Beldar day 1.63 645 1,051.35 Code No 0114
6 Bhisti day 0.7 714 499.80 Code No 0101
Hire charges of Concrete Mixer 0.25 to
7 day 0.07 800 56.00 Code No 0002
0.40 cum with hopper
8 Vibrator (Needle type 40 mm) day 0.07 350 24.50 Code No 0012
9 Sundries L.S. 13.52 2.12 28.66 Code No 9999
Total 3,571.42
10 Add Water charges @ 1% 35.71
Total 3,607.13
11 GST @18% 649.28
12 Add CPOH @ 15% 541.07
Total 4,797.48
Cost of 1 Cum 4,797.48
Say 4,797.00
Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest available DAR of
Note: CPWD / IRUSSOR of Indian Railways

BOQ Item No. 2004


(based on item no. 5.33.1 & 5.33.2 of CPWD DAR 2021 )
S. No. Description Unit Quantity Rate Amount Remarks
Details of cost for 1.00 cum
MATERIALS:
The material rates are
exclusive of contractor's profit,
Stone Aggregate (Single size) : 20 mm over heads and GST but
1 nominal size at site of work including cum 0.57 1563.9 891.44 inclusive of royalty and
carriage charges Carriage charges etc. (add
rates of Code No. 0295 &
2202)
Stone Aggregate (Single size) : 10 mm
-do- (add rates of code no.
2 nominal size at site of work including cum 0.28 1513.9 423.90
0297+2202)
carriage charges
Coarse sand at site of work including -do- (add rates of code no.
3 cum 0.425 1663.9 707.17
carriage charges 0982+2203)
Production cost, pumping to respective
floors and laying in position
Production cost of concrete by batch mix
4 cum 1 400 400.00 Code No 0004
plant
Pumping charges of concrete including
5 Hire charges of pump, piping work & cum 1 210 210.00 Code No 0009
accessories etc.
The rates are exclusive of
GST, contractors profit & OH
LABOUR:
but inclusive of wages for
weekly day of rest

labour; of pouring, consolidating & curing

6 Mason day 0.17 749 127.33 Code No 0155


7 Beldar day 2 645 1,290.00 Code No 0114
8 Bhisti day 0.9 714 642.60 Code No 0101
9 Vibrator (Needle type 40 mm) day 0.07 350 24.50 Code No 0012
10 Sundries L.S. 13 2.12 27.56 Code No 9999

Qty arrived by taking average


of item no. 5.33.1 (upto plinth
Extra labour for lifting in sub/super
level) & half of 5.33.2 (from
structure works
plinth to floor five).
0.75x(0+2.5/2)/2=0.47 day.

11 Coolie day 0.47 645 303.15 Code No 0115


Total 5,047.65
12 Add Water charges @ 1% 50.48
Total 5,098.13
13 GST @18% 917.66
14 Add CPOH @ 15% 764.72
Total 6,780.51
Cost of 1 Cum 6,780.51
Say 6,781.00

Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest available DAR of
Note:
CPWD / IRUSSOR of Indian Railways

BOQ Item No. 2005


(based on item no. 5.33.1 & 5.33.2 of CPWD DAR 2021 )

S. No. Description Unit Quantity Rate Amount Remarks


Details of cost for 1.00 cum
MATERIALS:

The material rates are


exclusive of contractor's profit,
Stone Aggregate (Single size) : 20 mm
over heads and GST but
1 nominal size at site of work including cum 0.57 1563.9 891.44
inclusive of royalty and
carriage charges
Carriage charges etc.. (add
rates of code no. 0295+2202)

Stone Aggregate (Single size) : 10 mm


-do- (add rates of code no.
2 nominal size at site of work including cum 0.28 1513.9 423.90
0297+2202)
carriage charges
Coarse sand at site of work including -do- (add rates of code no.
3 cum 0.425 1663.9 707.17
carriage charges 0982+2203)

Qty of super-plasticizer (Code


No 7318)required for grades of
M-25, M-30, M-35 & M-40 -
4 Plasticizer/super plasticizer kilogram 1.8 29 52.20 average of qty of item no.
5.33.2.1, 5.33.2.2, 5.33.2.3 &
5.33.2.4=(1.65+1.75+1.85+1.9
5)/4=1.80 kg

Production cost, pumping to respective


floors and laying in position
Production cost of concrete by batch mix
5 cum 1 400 400.00 Code No 0004
plant
Pumping charges of concrete including
6 Hire charges of pump, piping work & cum 1 210 210.00 Code No 0009
accessories etc.
The rates are exclusive of
GST, contractors profit & OH
LABOUR:
but inclusive of wages for
weekly day of rest

labour; of pouring, consolidating & curing

7 Mason day 0.17 749 127.33 Code No 0155


8 Beldar day 2 645 1,290.00 Code No 0114
9 Bhisti day 0.9 714 642.60 Code No 0101
10 Vibrator (Needle type 40 mm) day 0.07 350 24.50 Code No 0012
11 Sundries L.S. 13 2.12 27.56 Code No 9999

Qty arrived by taking average


of item no. 5.33.1 (upto plinth
Extra labour for lifting in super structure
level) & half of 5.33.2 (from
works
plinth to floor five).
0.75x(0+2.5/2)/2=0.47 day.

14 Coolie day 0.47 645 303.15 Code No 0115


Total 5,099.85
15 Add Water charges @ 1% 51.00
Total 5,150.85
16 GST @18% 927.15
17 Add CPOH @ 15% 772.63
Total 6,850.63
Cost of 1 Cum 6,850.63
Say 6,851.00

Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest available DAR of
Note: CPWD / IRUSSOR of Indian Railways

BOQ Item No. 2006

S. No. Description Unit Quantity Rate Amount Remarks


Rates of this item may be
updated by PIUs based on rate
A Concreting Cum 1 6,851 6,851.00
analysis for item no. 2005 of
BOQ.
This rate is fixed and will not be
B Transportation, erection and launching Cum 1 5672 5,672.00
changed by PIUs.
Cost of 1 Cum 12,523.00
Say 12,523.00

Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest available DAR of
Note:
CPWD / IRUSSOR of Indian Railways

BOQ Item No. 2011

S. No. Description Unit Quantity Rate Amount Remarks


Rates of this item may be
updated by PIUs based on rate
A Concreting Cum 1 6,851 6,851.00
analysis for item no. 2005 of
BOQ.
This rate is fixed and will not be
B Transportation, erection and launching Cum 1 4492 4,492.00
changed by PIUs.
Cost of 1 Cum 11,343.00
Say 11,343.00

Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest available DAR of
Note:
CPWD / IRUSSOR of Indian Railways

Rate Analysis for Item no. 2012


(based on item no. 4.1.3, 4.7.1, 5.9.1, 6.1.1, 6.4.1 & 11.1.2 of CPWD Delhi DAR 2021 )
S. No. Description Unit Quantity Rate Amount Remarks

Analysis based on item no.


1 Details of cost for 1:2:4 concrete 20mm 4.1.3 of CPWD Delhi DAR
aggregates 1 cum without cement 2021.

MATERIALS:
The material rates as per basic
Stone Aggregate (Single size) : 20 mm rates for materials Code No.
1.1 cum 0.67 1400.0 938.00
nominal size 0295 of CPWD Delhi DAR
2021.
The material rates as per basic
Stone Aggregate (Single size) : 10 mm rates for materials Code No.
1.2 cum 0.22 1350.0 297.00
nominal size at site of work 0297 of CPWD Delhi DAR
2021.
The material rates as per basic
rates for materials Code No.
1.3 Carriage of stone aggregates cum 0.89 163.93 145.90
2202 of CPWD Delhi DAR
2021.
The material rates as per basic
rates for materials Code No.
1.4 Coarse sand at site of work cum 0.445 1500.0 667.50
0982 of CPWD Delhi DAR
2021.
The material rates as per basic
rates for materials Code No.
1.5 Carriage of sand cum 0.445 163.93 72.95
2203 of CPWD Delhi DAR
2021.
The rates are exclusive of
GST, contractors profit & OH
LABOUR:
but inclusive of wages for
weekly day of rest
Rates as per basic rates for
1.6 Mason (average) day 0.1 749 74.90 labour Code No. 0155 of
CPWD Delhi DAR 2021.
Rates as per basic rates for
1.7 Beldar day 1.63 645 1,051.35 labour Code No. 0114 of
CPWD Delhi DAR 2021.
Rates as per basic rates for
1.8 Bhisti day 0.7 714 499.80 labour Code No. 0101 of
CPWD Delhi DAR 2021.
Rates as per basic rates for
Hire charges of Concrete Mixer 0.25 to hire charges for plant and
1.9 day 0.07 800 56.00
0.40 cum with hopper machinery Code No. 0002 of
CPWD Delhi DAR 2021.
Rates as per basic rates for
hire charges for plant and
1.10 Vibrator (Needle type 40 mm) day 0.07 350 24.50
machinery Code No. 0012 of
CPWD Delhi DAR 2021.
1.11 Sundries L.S. 14.3 2.12 30.32 Code No 9999
A Cost of 1 cum 1:2:4 concrete 3,858.22

Details of cost for 25 nos. blocks, Analysis based on item no.


2 25x25x20 cm size 1:2:4 concrete 20mm 4.7.1 of CPWD Delhi DAR
aggregates 2021.

Volume =25 no x 0.25 m x 0.25 m x 0.2 m


= 0.3125 cum
2.1 Cement Concrete cum 0.3125 3,858.22 1,205.69 Rate as per (A) above
Centering and Shuttering
(1) Mould
(i) Plate 3 mm thick (4x0.25x0.20)=0.2
sqm @ 23.55 kg/sqm = 4.71 kg

(ii) Flat 10x5mm handle 2x0.25m = 0.5m


@ 0.4 kg/m = 0.2 kg. total steel = 4.91 kg

Assuming shuttering will become


unserviceable after use of 40 times and Rate as per item no. 10.1 of
2.2 kg 0.0921 93.05 8.57
taking 75% credit, qty taken for cost for CPWD Delhi DAR 2021.
using once =4.91x0.75/40=0.0921 kg

(2) Moulding Platform Assuming platform


will become unserviceable after use of 40 AOR as per item no. 11.1.2 of
times. (i) Brick on edge flooring cement CPWD Delhi DAR 2016
2.3
mortar 1:6 - 1x2.0x2.0m = 4 sqm (quantity taken only for 0.1
Qty taken for cost of using once = 4/40 = sqm)
0.1 sqm

Rates as per basic rates for


Common burnt clay FPS bricks
2.3.1 1000 nos. 0.00565 4590 25.93 materials Code No. 2602 of
designation 75
CPWD Delhi DAR 2021.
Rates as per basic rates for
2.3.2 Carriage of bricks 1000 nos. 0.00565 437.15 2.47 materials Code No. 2201 of
CPWD Delhi DAR 2021.

Rates as per rate analysis for


2.3.3 Cement Mortar 1:6 Cum 0.00434 2,399.85 10.42 cement mortar 1:6 (below AOR
for item no. 2039).

Rates as per basic rates for


2.3.4 Mason (brick layer) 2nd class day 0.01080 714 7.71 labour Code No. 0124 of
CPWD Delhi DAR 2021.
Rates as per basic rates for
2.3.5 Beldar day 0.00250 645 1.61 labour Code No. 0114 of
CPWD Delhi DAR 2021.
Rates as per basic rates for
2.3.6 Coolie day 0.01620 645 10.45 labour Code No. 0115 of
CPWD Delhi DAR 2021.
Rates as per basic rates for
2.3.7 Bhisti day 0.00270 714 1.93 labour Code No. 0101 of
CPWD Delhi DAR 2021.
(ii) 25mm thick cement concrete 1:2:4 in
pavement 2.00x2.00x0.025 = 0.100
Rate as per (A) above. Labour
Qty taken for cost of using once =
for fixing blocks in Item no. 2.6
0.100/40 = 0.0025 cum
to 2.8 above taken as average
of that for brickwork Item no.
2.4 cum 0.0025 3,858.22 9.65
6.1.1 & 6.4.1 of CPWD Delhi
DAR 2021 as labour element of
item no. 4.7.1 is for lifting,
hoisting and fixing manually.

Rates as per rate analysis for


cement mortar 1:6 (below AOR
Cement Mortar 1:2 for Fixing
2.5 cum 0.0410 2,399.85 98.39 for item no. 2039). Qty taken
0.1625/100x25 = 0.041
half of surface area with 10 mm
thick mortar for 25 blocks.

Rates as per basic rates for


labour Code No. 0115 of
CPWD Delhi DAR 2021. Qty
2.6 Coolie day 0.495 645 319.28 reduced in proportion of
0.325/1.0 from average of
quantities given for CPWD
item no. 6.1.1 & 6.4.1.

Rates as per basic rates for


labour Code No. 0123 of
CPWD Delhi DAR 2021. Qty
2.7 Mason (brick layer) 1st class day 0.13 784 101.92 reduced in proportion of
0.325/1.0 from average of
quantities given for CPWD
item no. 6.1.1 & 6.4.1.

Rates as per basic rates for


labour Code No. 0124 of
CPWD Delhi DAR 2021. Qty
2.8 Mason (brick layer) 2nd class day 0.07 714 52.12 reduced in proportion of
0.325/1.0 from average of
quantities given for CPWD
item no. 6.1.1 & 6.4.1.

Rates as per basic rates for


labour Code No. 0101 of
CPWD Delhi DAR 2021. Qty
2.9 Bhisti day 0.063 714 44.98 reduced in proportion of
0.325/1.0 from average of
quantities given for CPWD
item no. 6.1.1 & 6.4.1.
Rates of carriage of bricks as
per basic rates for materials
2.10 Carriage of blocks 1000 nos. 0.025 437.15 10.93
Code No. 2201 of CPWD
Delhi DAR 2021. ok
TOTAL 1,912.05
On SrNo 2.1, 2.3.1, 2.3.2,
Add 1% Water charges 14.66 2.3.4, 2.3.5, 2.3.6, 2.3.7, 2.7,
2.8, 2.9 & 2.10
TOTAL 1,926.71
GST @18% 266.47
Add CPOH @ 15% 222.06
Cost for 0.3125 cum 2,415.24
Cost per cum 7,728.76
Say 7,729.00
Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest available DAR of
Note:
CPWD / IRUSSOR of Indian Railways

BOQ Item No. 2014

S. No. Description Unit Quantity Rate Amount Remarks


Rates of this item may be
updated by PIUs based on rate
A Concreting Cum 1 6,781 6,781.00
analysis for item no. 2004 of
BOQ.
This rate is fixed and will not be
changed by PIUs. The
transportation charges will be
B Transportation, handling & fixing Cum 1 1603 1,603.00
payable only when the
segments are cast at a casting
yard.
Cost of 1 Cum 8,384.00
Say 8,384.00

Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest available DAR of
Note:
CPWD / IRUSSOR of Indian Railways

BOQ Item No. 2022 a


S. No. Description Unit Quantity Rate Amount Remarks
Pile diameter = 1200 mm,
Unit = meter
Taking output = 9 m
As worked out for item no.
2004 of BOQ. Rates of this
A Concreting Cost inclusive of COHP etc. m 10.1736 6,781.00 68,987.18 item may be updated by PIUs
based on rate analysis for item
no. 2004 of BOQ.

Rate analysis as per 192072 of


USSOR - Analysis of Rates
B Boring, bentonite and other costs (IR) and rates of materials,
machinery and labour as per
CPWD Delhi DSR 2021.

a) Machinery

Rate taken from Item no. 0024


Hire and running charges of hydraulic
of Basic rates (0.1 HIRE
piling rig with power unit etc. including Day 1 35000 35,000.00
CHARGES OF PLANTS) of
complete accessories and shifting at site.
CPWD Delhi DSR 2021

Rate taken from Item no. 0025


of Basic rates (0.1 HIRE
Hire and running charges of light crane Day 0.1 3500 350.00
CHARGES OF PLANTS) of
CPWD Delhi DSR 2021

Rate taken from Item no. 0026


Hire and running charges of bentonite of Basic rates (0.1 HIRE
Day 1 3000 3,000.00
pump CHARGES OF PLANTS) of
CPWD Delhi DSR 2021

Rate taken from Item no. 0018


of Basic rates (0.1 HIRE
Hire and running charges of loader Day 0.2 6000 1,200.00
CHARGES OF PLANTS) of
CPWD Delhi DSR 2021

Rate taken from Item no. 0017


of Basic rates (0.1 HIRE
Hire and running charges of tipper Day 0.2 3750 750.00
CHARGES OF PLANTS) of
CPWD Delhi DSR 2021

Rate taken from Item no. 7183


of Basic rates (0.3
Bentonite Tonne 0.39 2800 1,092.00
MATERIALS) of CPWD Delhi
DSR 2021
b) Labour

Rate taken from Item no. 0128


Mate Day 0.18 714 128.52 of Basic rates (0.2 LABOUR) of
CPWD Delhi DSR 2021

Rate taken from Item no. 0114


Beldar Day 4.5 645 2,902.50 of Basic rates (0.2 LABOUR) of
CPWD Delhi DSR 2021

Total 44,423.02
Sundries (no rates reqd.) 1 1492.9 1,492.90
Total 45,915.92
Add for Water Charges @ 1% (no rates
0.01 459.16
reqd.)
Total 46,375.08
Add GST @18% 8,347.51
Add for Contractor’s Profit and Overheads
0.15 6,956.26
@ 15% (no rates reqd.)
C Total cost for B 61,678.86

D Total cost for 9 m (A + C) 130,666.04


Cost of 1 m 14,518.45
Say 14,518.00

Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest available DAR of
Note:
CPWD / IRUSSOR of Indian Railways

BOQ Item No. 2022 b


S. No. Description Unit Quantity Rate Amount Remarks
Pile diameter = 1000 mm,
Unit = meter
Taking output = 10 m
As worked out for item no.
2004 of BOQ. Rates of this
A Concreting Cost inclusive of COHP etc. m 7.85 6,781.00 53,230.85 item may be updated by PIUs
based on rate analysis for item
no. 2004 of BOQ.

Rate analysis as per 192073 of


USSOR - Analysis of Rates
B Boring, bentonite and other costs (IR) and rates of materials,
machinery and labour as per
CPWD Delhi DSR 2021.

a) Machinery

Rate taken from Item no. 0024


Hire and running charges of hydraulic
of Basic rates (0.1 HIRE
piling rig with power unit etc. including Day 1 35000 35,000.00
CHARGES OF PLANTS) of
complete accessories and shifting at site.
CPWD Delhi DSR 2021

Rate taken from Item no. 0025


of Basic rates (0.1 HIRE
Hire and running charges of light crane Day 0.1 3500 350.00
CHARGES OF PLANTS) of
CPWD Delhi DSR 2021

Rate taken from Item no. 0026


Hire and running charges of bentonite of Basic rates (0.1 HIRE
Day 1 3000 3,000.00
pump CHARGES OF PLANTS) of
CPWD Delhi DSR 2021

Rate taken from Item no. 0018


of Basic rates (0.1 HIRE
Hire and running charges of loader Day 0.1 6000 600.00
CHARGES OF PLANTS) of
CPWD Delhi DSR 2021

Rate taken from Item no. 0017


of Basic rates (0.1 HIRE
Hire and running charges of tipper Day 0.1 3750 375.00
CHARGES OF PLANTS) of
CPWD Delhi DSR 2021

Rate taken from Item no. 7183


of Basic rates (0.3
Bentonite Day 0.35 2800 980.00
MATERIALS) of CPWD Delhi
DSR 2021
b) Labour

Rate taken from Item no. 0128


Mate Day 0.16 714 114.24 of Basic rates (0.2 LABOUR) of
CPWD Delhi DSR 2021

Rate taken from Item no. 0114


Beldar Day 4 645 2,580.00 of Basic rates (0.2 LABOUR) of
CPWD Delhi DSR 2021

Total 42,999.24
Sundries (no rates reqd.) 1 1376.22 1,376.22
Total 44,375.46
Add for Water Charges @ 1% (no rates
0.01 443.75
reqd.)
Total 44,819.21
Add GST @18% 8,067.46
Add for Contractor’s Profit and Overheads
0.15 6,722.88
@ 15% (no rates reqd.)
C Total cost for B 59,609.56

D Total cost for 10 m (A + C) 112,840.41


Cost of 1 m 11,284.04
Say 11,284.00

Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest available DAR of
Note: CPWD / IRUSSOR of Indian Railways

BOQ Item No. 2022 c


S. No. Description Unit Quantity Rate Amount Remarks
Pile diameter = 750 mm,
Unit = meter
Taking output = 15 m
As worked out for item no.
2004 of BOQ. Rates of this
A Concreting Cost inclusive of COHP etc. m 6.624 6,781.00 44,917.34 item may be updated by PIUs
based on rate analysis for item
no. 2004 of BOQ.

Rate analysis as per 192074 of


USSOR - Analysis of Rates
B Boring, bentonite and other costs (IR) and rates of materials,
machinery and labour as per
CPWD Delhi DSR 2021.

a) Machinery

Rate taken from Item no. 0024


Hire and running charges of hydraulic
of Basic rates (0.1 HIRE
piling rig with power unit etc. including Day 1 35000 35,000.00
CHARGES OF PLANTS) of
complete accessories and shifting at site.
CPWD Delhi DSR 2021

Rate taken from Item no. 0025


of Basic rates (0.1 HIRE
Hire and running charges of light crane Day 0.1 3500 350.00
CHARGES OF PLANTS) of
CPWD Delhi DSR 2021

Rate taken from Item no. 0026


Hire and running charges of bentonite of Basic rates (0.1 HIRE
Day 1 3000 3,000.00
pump CHARGES OF PLANTS) of
CPWD Delhi DSR 2021

Rate taken from Item no. 0018


of Basic rates (0.1 HIRE
Hire and running charges of loader Day 0.1 6000 600.00
CHARGES OF PLANTS) of
CPWD Delhi DSR 2021

Rate taken from Item no. 0017


of Basic rates (0.1 HIRE
Hire and running charges of tipper Day 0.1 3750 375.00
CHARGES OF PLANTS) of
CPWD Delhi DSR 2021

Rate taken from Item no. 7183


of Basic rates (0.3
Bentonite Day 0.35 2800 980.00
MATERIALS) of CPWD Delhi
DSR 2021
b) Labour

Rate taken from Item no. 0128


Mate Day 0.16 714 114.24 of Basic rates (0.2 LABOUR) of
CPWD Delhi DSR 2021

Rate taken from Item no. 0114


Beldar Day 4 645 2,580.00 of Basic rates (0.2 LABOUR) of
CPWD Delhi DSR 2021

Total 42,999.24
Sundries (no rates reqd.) 1 1319.89 1,319.89
Total 44,319.13
Add for Water Charges @ 1% (no rates
0.01 443.19
reqd.)
Total 44,762.32
Add GST @18% 8,057.22
Add for Contractor’s Profit and Overheads
0.15 6,714.35
@ 15% (no rates reqd.)
C Total cost for B 59,533.89

D Total cost for 15 m (A + C) 104,451.23


Cost of 1 m 6,963.42
Say 6,963.00

Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest available DAR of
Note:
CPWD / IRUSSOR of Indian Railways

BOQ Item No. 2022 d


S. No. Description Unit Quantity Rate Amount Remarks
Pile diameter = 600 mm,
Unit = meter
Taking output = 22 m
As worked out for item no.
2004 of BOQ. Rates of this
A Concreting Cost inclusive of COHP etc. m 6.2172 6,781.00 42,158.83 item may be updated by PIUs
based on rate analysis for item
no. 2004 of BOQ.

Rate analysis as per 192075 of


USSOR - Analysis of Rates
B Boring, bentonite and other costs (IR) and rates of materials,
machinery and labour as per
CPWD Delhi DSR 2021.

a) Machinery

Rate taken from Item no. 0024


Hire and running charges of hydraulic
of Basic rates (0.1 HIRE
piling rig with power unit etc. including Day 1 35000 35,000.00
CHARGES OF PLANTS) of
complete accessories and shifting at site.
CPWD Delhi DSR 2021

Rate taken from Item no. 0025


of Basic rates (0.1 HIRE
Hire and running charges of light crane Day 0.1 3500 350.00
CHARGES OF PLANTS) of
CPWD Delhi DSR 2021

Rate taken from Item no. 0026


Hire and running charges of bentonite of Basic rates (0.1 HIRE
Day 1 3000 3,000.00
pump CHARGES OF PLANTS) of
CPWD Delhi DSR 2021

Rate taken from Item no. 0018


of Basic rates (0.1 HIRE
Hire and running charges of loader Day 0.1 6000 600.00
CHARGES OF PLANTS) of
CPWD Delhi DSR 2021

Rate taken from Item no. 0017


of Basic rates (0.1 HIRE
Hire and running charges of tipper Day 0.1 3750 375.00
CHARGES OF PLANTS) of
CPWD Delhi DSR 2021

Rate taken from Item no. 7183


of Basic rates (0.3
Bentonite Day 0.3 2800 840.00
MATERIALS) of CPWD Delhi
DSR 2021
b) Labour

Rate taken from Item no. 0128


Mate Day 0.14 714 99.96 of Basic rates (0.2 LABOUR) of
CPWD Delhi DSR 2021

Rate taken from Item no. 0114


Beldar Day 3.5 645 2,257.50 of Basic rates (0.2 LABOUR) of
CPWD Delhi DSR 2021

Total 42,522.46
Sundries (no rates reqd.) 1 1295.41 1,295.41
Total 43,817.87
Add for Water Charges @ 1% (no rates
0.01 438.18
reqd.)
Total 44,256.05
Add GST @18% 7,966.09
Add for Contractor’s Profit and Overheads
0.15 6,638.41
@ 15% (no rates reqd.)
C Total cost for B 58,860.54

D Total cost for 22 m (A + C) 101,019.38


Cost of 1 m 4,591.79
Say 4,592.00

Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest available DAR of
Note:
CPWD / IRUSSOR of Indian Railways

BOQ Item No. 2029

(based on item no. 193080 of USSOR - Analysis of Rates (IR) and suitably modified with use of carriage and labour rates of CPWD)

S. No. Description Unit Quantity Rate Amount Remarks


Details of cost for 1 cum
A MATERIALS & TRANSPORTATION:
Rate for sand taken from Item
no. 0983 of Basic rates
1 Fine sand (Zone-IV) cum 1 900.00 900.00
(Materials) of CPWD Delhi
DAR 2021.

Rates based on CPWD Delhi


Transportation of sand by mechanical DAR 2012 with 8 Cum quantity
2 means including loading and unloading for Cum 1 108.94 108.94 per trip (item no. 1.1.5) for
lead upto 1 km Carriage of Materials rates (by
mechanical transport).

Fill in lead qty as per actuals.


Rates based on CPWD Delhi
DAR 2012 with 8 Cum quantity
per trip (item no. 1.1.5) for
Extra for every km or part thereof for Lead
4 Km 4 13.75 54.99 Carriage of Materials rates (by
beyond 1 km but upto 5 km
mechanical transport). Deduct
rate for 1 km lead from the rate
for 5 km lead and divide by 4
for average rate per km.

Extra for every km or part thereof for Lead


5 Km 5 11.68 58.43 -do-
beyond 5 km but upto 10 km
Extra for every km or part thereof for Lead
6 Km 0 9.53 - -do-
beyond 10 km but upto 20 km
Extra for every km or part thereof for Lead
7 Km 0 7.69 - -do-
beyond 20 km
Total 1,122.36
B LABOUR:

Rate taken from Item no. 0128


1 Mate day 0.01 714 7.14 of Basic rates (Labour) of
CPWD Delhi DAR 2021
Rate taken from Item no. 0114
2 Beldar day 0.3 645 193.50 of Basic rates (Labour) of
CPWD Delhi DAR 2021

C Total 1,323.00
Add GST @ 18% 238.14
Add for Contractor's Profit and overheads
E LS 0.15 198.45
@15% (no rate reqd)
Total 1,759.59
Cost of 1 Cum 1,759.59

Say 1,760.00 For lead of KM input as above.

Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest available DAR of
Note:
CPWD / IRUSSOR of Indian Railways

BOQ Item No. 2039


(based on item no. 7.1.1 of CPWD DAR 2021 )
S. No. Description Unit Quantity Rate Amount Remarks
Details of cost for 1.00 cum
MATERIALS:
Stone for masonry work The material rates as per basic
rates for materials Code No.
1 cum 1 1100.00 1,100.00
1157 of CPWD Delhi DAR
2021.
Through and bond stone size 24x24x39 The material rates as per basic
cm (@7 nos. per cum) rates for materials Code No.
2 100 Nos 0.07 5000.00 350.00
1154 of CPWD Delhi DAR
2021.
Carriage: Carriage of Soling stone &
masonry stone 7.00 x 24cm x 24cm x Rates as per basic rates for
3 39cm = 0.16 cum. cum 1.16 192.86 223.72 materials Code No. 2215 of
1.00 cum + 0.16 cum = 1.16 cum. CPWD Delhi DAR 2021.

Cement Mortar 1:6 (1 cement : 5 coarse Rates as per rate analysis for
4 sand) cum 0.33 2399.85 791.95 1:5 cement mortar (given
below)
Pointing with 1:3 cement mortar (@3.5
sqm for 1 cum of RR masonry considering Rates as per rate analysis for
5 wall thickness of 40 cm and inside and top sqm 3.5 234.13 819.46 flush pointing with 1:3 cement
face to be pointed) mortar (given below)

LABOUR:
Rates as per basic rates for
6 day 1.07 714.00 labour Code No. 0125 of
Mason (for plain stone work) 2nd class CPWD Delhi DAR 2021.
Rates as per basic rates for
7 day 1.07 645.00 690.15 labour Code No. 0114 of
Beldar CPWD Delhi DAR 2021.
Rates as per basic rates for
8 day 0.71 645.00 457.95 labour Code No. 0115 of
Coolie CPWD Delhi DAR 2021.
Rates as per basic rates for
9 day 0.09 714.00 64.26 labour Code No. 0101 of
Bhisti CPWD Delhi DAR 2021.
10 Cement concrete 1:6:12 L.S. 0 1.73 - Not applicable
11 Sundries L.S. 4.42 1.73 7.65
Total 4,505.14
12 Add Water charges @ 1% 45.05
Total 4,550.19
13 Add GST@18% 819.03
14 Add CPOH @ 15% 682.53
Total 6,051.75
Cost of 1 Cum 6,051.75
Say 6,052.00
Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest available DAR of
Note:
CPWD / IRUSSOR of Indian Railways
Rate Analysis for Cement Mortar (1:3 or 1:4 or 1:5 or 1:6)
(based on item no. 3.10 of CPWD DAR 2021, Note: Rate analysis for 1:5 and 1:3 is same as cement cost is not included)
S. No. Description Unit Quantity Rate Amount Remarks
Details of cost for 1 cum
Material

1 Portland Cement tonne 0 5700.00 -


2 Carriage of cement tonne 0 92.24 -
Rates as per basic rates for
3 cum 1.07 1500.00 1,605.00 materials Code No. 982 of
Coarse sand (zone III) CPWD Delhi DAR 2021.
Rates as per basic rates for
4 cum 1.07 163.93 175.41 materials Code No. 2203 of
Carriage of Coarse sand CPWD Delhi DAR 2021.
LABOUR
For measuring, carrying, depositing and
mixing-
Rates as per basic rates for
5 day 0.75 645.00 483.75 labour Code No. 0114 of
Beldar CPWD Delhi DAR 2021.
Rates as per basic rates for
6 day 0.07 714.00 49.98 labour Code No. 0101 of
Bhisti CPWD Delhi DAR 2021.

7 Hire and running charges of mechanical L.S. 26.91 2.12 57.05


mixer
8 Sundries L.S. 13.52 2.12 28.66
Cost of 1.00 cum 2,399.85
Say 2,399.85

Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest available DAR of
Note: CPWD / IRUSSOR of Indian Railways

Rate Analysis for Flush/Ruled Pointing on Stone work (1:3 cement mortar)
(based on item no. 13.33.1 of CPWD DAR 2021)
S. No. Description Unit Quantity Rate Amount Remarks
Details of cost for 10 sqm
Material
Cement mortar 1:3 (1 cement : 3 fine Rates as per rate analysis for
1 sand) cum 0.023 2399.85 55.20 1:3 cement mortar (given
above)
2 Sundries L.S. 7.15 2.12 15.16
LABOUR
Mason (average) Rates as per basic rates for
3 day 0.92 749.00 689.08 labour Code No. 0155 of
CPWD Delhi DAR 2021.
Coolie Rates as per basic rates for
4 day 1.37 645.00 883.65 labour Code No. 0115 of
CPWD Delhi DAR 2021.
Bhisti Rates as per basic rates for
5 day 0.93 714.00 664.02 labour Code No. 0101 of
CPWD Delhi DAR 2021.
Scaffolding and racking out joints including
6 L.S. 16.12 2.12 34.17
sundries
TOTAL 2,341.28
Add 1% water charges - Not to be considered here
TOTAL 2,341.28
Add 15% Contractor's Profit and
- Not to be considered here
overheads
Cost of 10.00 sqm 2,341.28
Cost of 1.00 sqm 234.13

Say 234.13

Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest available DAR of
CPWD / IRUSSOR of Indian Railways
Note:
Standard Rate Analysis for Site Specific Items of Schedule 3 of the BOQ

BOQ Item No. 3001 & 3002


(based on item no. 021360 of USSOR - Analysis of Rates (IR) (for stcking) and suitably modified with use of carriage and labour
rates of CPWD)

S. No. Description Unit Quantity Rate Amount Remarks


Details of cost for 1 cum
A MATERIALS & TRANSPORTATION:
Rate taken from Item no. 0292 of Basic
1 Cost of ballast at quarry cum 1 900.00 900.00 rates (Materials) of CPWD Delhi DAR
2012
Rates based on item no. 1.1.6 of Carriage
Transportation of ballast of Materials rates (by mechanical
by mechanical means
2 including loading and Cum 1 62.59 62.59 transport) of CPWD Delhi DAR 2012.
unloading for lead upto 1
km Contractor's profit & overhead @ 15%
has been deducted from the CPWD rate.
Fill in lead qty as per actuals. Rate is
based on item no. 1.1.6 of Carriage of
Materials rates by mechanical transport
Extra for every km or part of CPWD Delhi DAR 2012. Deduct rate for
3 thereof for Lead beyond 1 Km 4 8.16 32.63
km but upto 5 km 1 km lead from the rate for 5 km lead and
divide by 4 for average rate per km.
Contractor's profit & overhead @ 15%
has been deducted from the CPWD rate.
Fill in lead qty as per actuals. Rates based
on item no. 1.1.6 of Carriage of Materials
Extra for every km or part rates by mechanical transport of CPWD
4 thereof for Lead beyond 5 Km 5 6.97 34.87
km but upto 10 km Delhi DAR 2012. Contractor's profit &
overhead @ 15% has been deducted
from the CPWD rate.

Extra for every km or part


5 thereof for Lead beyond Km 10 5.74 57.39 -do-
10 km but upto 20 km

Extra for every km or part


6 thereof for Lead beyond Km 5 4.69 23.43 -do-
20 km
Total 1110.91
LABOUR for stacking as
B per AOR for item no. Suitably modifying quantities for 1 cum
021360 of USOR :

1 Mate day 0.005 260 1.3 Rate taken from Item no. 0128 of Basic
rates (Labour) of CPWD Delhi DAR 2012

2 Beldar day 0.05 247 12.35 Rate taken from Item no. 0114 of Basic
rates (Labour) of CPWD Delhi DAR 2012

3 Sundries LS 1 1.16 1.16


C Total 1125.72
Add for water charges @
D LS 0.01 11.26
1% (no rate reqd)
Add for Contractor's
E Profit and overheads LS 0.15 170.55
@15%
Cost of 1 Cum 1,307.53 For lead of 25 km
Say 1,308 For lead of 25 km

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from
latest available DAR of CPWD / IRUSSOR of Indian Railways
Standard Rate Analysis for Site Specific Items of Schedule 7A of the BOQ

BOQ Item No. 7001

S. No. Description Unit Quantity Rate Amount Remarks


Details per m of platform wall
Precast wall (M 30 RCC) as per
1 Cum 0.2878 8384 2412.92 As per rates of BOQ item no. 2014
RDSO drg with coping
Cost of m of wall 2,412.92
Say 2,413

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest
available DAR of CPWD / IRUSSOR of Indian Railways

BOQ Item No. 7002


(based on item no. 4.1.6 of CPWD DAR 2021 )
S. No. Description Unit Quantity Rate Amount Remarks
Details of cost for 1.00 cum
MATERIALS:

Stone Aggregate (Single size) : The material rates are exclusive of


40 mm nominal size (0.7 cum - contractor's profit, over heads
1 7.5% for voids i.e. 0.05=0.65 cum 0.65 1478.19 960.82 and GST but include royalty, and
cum) at site of work including Carriage charges etc. (add rates of
carriage charges Code No. 0293 & 2206)

Stone Aggregate (Single size) :


20 mm nominal size at site of -do- (add rates of Code No. 0295
2 cum 0.24 1563.93 375.34
work including carriage & 2202)
charges

Fine sand (zone IV) at site of


-do- (add rates of Code No. 0983
3 work including carriage cum 0.47 1063.93 500.05
& 2203)
charges

The rates are exclusive of GST,


contractors profit & OH but
LABOUR:
inclusive of wages for weekly day
of rest
labour; of pouring,
consolidating & curing
4 Mason day 0.1 749 74.9 Code No 0155
5 Beldar day 1.63 645 1051.35 Code No 0114
6 Bhisti day 0.7 714 499.8 Code No 0101

Hire charges of Concrete Mixer


7 day 0.07 800 56 Code No 0002
0.25 to 0.40 cum with hopper

8 Vibrator (Needle type 40 mm) day 0.07 350 24.5 Code No 0012
9 Sundries L.S. 13.52 2.12 28.66 Code No 9999
Total 3,571.42
10 Add Water charges @ 1% 35.71
Total 3,607.13
11 GST @18% 649.28
12 Add CPOH @ 15% 541.07
Total 4,797.48
Cost of 1 Cum 4,797.48
Say 4,797

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest
available DAR of CPWD / IRUSSOR of Indian Railways
BOQ Item no. 7003
(based on item no. 4.1.3 of CPWD Delhi DAR 2021 )
S. No. Description Unit Quantity Rate Amount Remarks
1 CONCRETE
Details of cost for 1:2:4 Analysis based on item no. 4.1.3
concrete 20mm aggregates 1 of CPWD Delhi DAR 2021.
cum without cement
MATERIALS:

The material rates as per basic


Stone Aggregate (Single size) :
1.1 cum 0.67 1400.0 938 rates for materials Code No. 0295
20 mm nominal size
of CPWD Delhi DAR 2021.

Stone Aggregate (Single size) : The material rates as per basic


1.2 10 mm nominal size at site of cum 0.22 1350.0 297 rates for materials Code No. 0297
work of CPWD Delhi DAR 2021.

The material rates as per basic


1.3 Carriage of stone aggregates cum 0.89 163.93 145.9 rates for materials Code No. 2202
of CPWD Delhi DAR 2021.

The material rates as per basic


1.4 Coarse sand at site of work cum 0.445 1500.0 667.5 rates for materials Code No. 0982
of CPWD Delhi DAR 2021.

The material rates as per basic


1.5 Carriage of sand cum 0.445 163.93 72.95 rates for materials Code No. 2203
of CPWD Delhi DAR 2021.

LABOUR:
Rates as per basic rates for labour
1.6 Mason (average) day 0.1 749 74.9 Code No. 0155 of CPWD Delhi
DAR 2021.
Rates as per basic rates for labour
1.7 Beldar day 1.63 645 1051.35 Code No. 0114 of CPWD Delhi
DAR 2021.
Rates as per basic rates for labour
1.8 Bhisti day 0.7 714 499.8 Code No. 0101 of CPWD Delhi
DAR 2021.
Rates as per basic rates for hire
charges for plant and machinery
Hire charges of Concrete Mixer
1.9 day 0.07 800 56 Code No. 0002 of CPWD Delhi
0.25 to 0.40 cum with hopper DAR 2021.

Rates as per basic rates for hire


charges for plant and machinery
1.10 Vibrator (Needle type 40 mm) day 0.07 350 24.5 Code No. 0012 of CPWD Delhi
DAR 2021.

1.11 Sundries L.S. 14.3 2.12 30.32


Cost of 1 cum 1:2:4 concrete 3,858.22

Add for Water Charges @ 1% 38.58


Total 3896.80
GST @18% 701.42
Add for Contractor’s Profit and
584.52
Overheads @ 15%
Total 5182.75
cost per cum cum 5182.75
Say 5183

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest
available DAR of CPWD / IRUSSOR of Indian Railways
BOQ Item No. 7004

(based on item no. 013120 of USSOR - Analysis of Rates (IR) and suitably modified with use of carriage and labour rates of CPWD)

S. No. Description Unit Quantity Rate Amount Remarks


Details of cost for 1 cum
A MATERIALS & TRANSPORTATION:
This is based on item no. 013120 of
USOR of SCR and includes cost of
earth to be paid to the land owner
1 Good Earth cum 1 75.00 75.00 and royalty and any other levy/tax.
Prevailing rate of the project area to
be taken.

Hydraulic Excavator (3D) with This is based on item 2.6.1 of CPWD


2 day 0.004125 7500.00 30.94
driver and fuel Delhi DAR 2012
Rates based on item no. 1.1.2 of
Carriage of Materials rates (by
Transportation of earth by
mechanical means including mechanical transport) of CPWD Delhi
3 Cum 1 71.98 71.98
loading and unloading for lead DAR 2012. Contractor's profit &
upto 1 km
overhead @ 15% has been deducted
from the CPWD rate.
Fill in lead qty as per actuals. Rate is
based on item no. 1.1.2 of Carriage
of Materials rates by mechanical

Extra for every km or part transport of CPWD Delhi DAR 2012.


4 thereof for Lead beyond 1 km Km 0 9.38 0 Deduct rate for 1 km lead from the
but upto 5 km rate for 5 km lead and divide by 4 for
average rate per km. Contractor's
profit & overhead @ 15% has been
deducted from the CPWD rate.
Fill in lead qty as per actuals. Rates
based on item no. 1.1.2 of Carriage
of Materials rates by mechanical
Extra for every km or part
5 thereof for Lead beyond 5 km Km 0 8.02 0 transport of CPWD Delhi DAR 2012.
but upto 10 km Contractor's profit & overhead @
15% has been deducted from the
CPWD rate.
Extra for every km or part
6 thereof for Lead beyond 10 km Km 0 6.60 0 -do-
but upto 20 km

Extra for every km or part


7 Km 0 5.39 0 -do-
thereof for Lead beyond 20 km

Total 177.92
B LABOUR:
Rate taken from Item no. 0113 of
1 Chowkidar day 0.001 247 0.25 Basic rates (Labour) of CPWD Delhi
DAR 2012
2 Sundries (No rates reqd) LS 1 0.1 0.10

C Total 178.27
Add for water charges @ 1%
D LS 0.01 1.78
(no rate reqd)
Add for Contractor's Profit and
E overheads @15% (no rate LS 0.15 27.01
reqd)

F Mechanical compaction cum 1 10.15 10.15 Rate taken from SBOQ item no. 1006
G Grand Total (C+D+E+F) Cum 1 217.21
Cost of 1 Cum 217.21 For lead within 1 km
Say 217 For lead within 1 km

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest
available DAR of CPWD / IRUSSOR of Indian Railways
BOQ Item No. 7007C
(based on item no. 16.75 of CPWD DAR 2016 )
S. No. Description Unit Quantity Rate Amount Remarks
Details of cost for 1.00 cum
MATERIALS:
1 cum 1.00 4786.00 4786 Rates as per rate analysis for item
Concrete M 25 = 1.00 cum i/c no. 2004 of BOQ
placing of concrete, vibrating,
levelling etc
2 Operational charges for L.S. 57.2 1.73 98.96
vacuum dewatering system i/c
screed vibration, placing of
filter mat, top mat, vacuum
process, floating, trowelling,
Brooming etc.

3 T&P charges i/c consumable L.S. 41.6 1.73 71.97


power charges, loading,
unloading and hire charges of
equipments

Total 4,956.93
4 Add 1% water charges on all 1.71
except (1)
Total 4,958.64

5 Add 15% Contractor's Profit 25.9


and overheads on all except (1)
Total 4,984.54
Cost of 1 Cum 4,984.54
Say 4,985

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest
available DAR of CPWD / IRUSSOR of Indian Railways

BOQ Item No. 7021a and 7021b


(based on item no. 6.26.2 of CPWD DAR 2016 )
S. No. Description Unit Quantity Rate Amount Remarks
Details of cost for 1.00 cum
MATERIALS:
1 Common burnt clay F.P.S. (non 1000 Nos 0.494 4,500.00 2223.00 Rates as per basic rates for
modular) bricks class materials Code No. 2602 of CPWD
designation 7.5 or 75 Delhi DAR 2016.
2 Carriage of bricks 1000 Nos 0.494 276.72 136.70 Rates as per basic rates for
materials Code No. 2201 of CPWD
Delhi DAR 2016.
3 Cement mortar 1:4/1:6 cum 0.25 1769.50 442.38 Rates as per rate analysis for
cement mortar (given below AOR
for item no. 2039)
4 Sundries including L.S. 16.38 1.73 28.34
steel/wooden strips for making
grooves.
LABOUR:
For selection of bricks
5 Beldar day 0.50 368 184.00 Rates as per basic rates for labour
Code No. 0114 of CPWD Delhi
DAR 2016.
6 Mason (brick layer) 1 st class day 0.46 487 224.02 Rates as per basic rates for labour
Code No. 0123 of CPWD Delhi
DAR 2016.
7 Mason (brick layer) 2nd class day 0.46 448 206.08 Rates as per basic rates for labour
Code No. 0124 of CPWD Delhi
DAR 2016.
8 Coolie day 1.60 368 588.80 Rates as per basic rates for labour
Code No. 0115 of CPWD Delhi
DAR 2016.
9 Bhisti day 0.20 407 81.40 Rates as per basic rates for labour
Code No. 0101 of CPWD Delhi
DAR 2016.
Extra labour for lifting of
material (above floor two level
up to floor five level)
10 Coolie day 0 368 0.00 not applicable
11 Sundries L.S. 0 1.73 0.00 not applicable
Total 4,114.72
12 Add 1% water charges 41.15
Total 4,155.87
13 Add 15% Contractor's Profit 623.38
and overheads
Total 4,779.25
Cost of 1 Cum 4,779.25
Say 4,779

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest
available DAR of CPWD / IRUSSOR of Indian Railways

BOQ Item No. 7021c


(based on item no. 6.13.1 of CPWD DAR 2016 )
S. No. Description Unit Quantity Rate Amount Remarks
Details of cost for 10 sqm
MATERIALS:
1 Common burnt clay F.P.S. (non 1000 Nos 0.565 4,500.00 2542.50 Rates as per basic rates for
modular) bricks class materials Code No. 2602 of CPWD
designation 7.5 or 75 Delhi DAR 2016.
2 Carriage of bricks 1000 Nos 0.565 276.72 156.35 Rates as per basic rates for
materials Code No. 2201 of CPWD
Delhi DAR 2016.
3 Cement mortar 1:3 cum 0.28 1769.50 495.46 Rates as per rate analysis for
cement mortar (given below AOR
for item no. 2039)
4 Sundries & Scaffolding L.S. 13.52 1.73 23.39
LABOUR:
5 Mason (brick layer) 1 st class day 0.60 487 292.20 Rates as per basic rates for labour
Code No. 0123 of CPWD Delhi
DAR 2016.
6 Mason (brick layer) 2nd class day 0.60 448 268.80 Rates as per basic rates for labour
Code No. 0124 of CPWD Delhi
DAR 2016.
7 Coolie day 2.00 368 736.00 Rates as per basic rates for labour
Code No. 0115 of CPWD Delhi
DAR 2016.
8 Bhisti day 0.70 407 284.90 Rates as per basic rates for labour
Code No. 0101 of CPWD Delhi
DAR 2016.
Extra labour for lifting of
material (above floor two level
up to floor five level)
9 Coolie day 0 368 0.00 not applicable
Total 4,799.60
10 Add 1% water charges 48
Total 4,847.60
11 Add 15% Contractor's Profit 727.14
and overheads
Cost of 10 sqm 5,574.74
Cost of 1 sqm 557.47
Say 557

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest
available DAR of CPWD / IRUSSOR of Indian Railways
BOQ Item No. 7033

(based on item no. 193080 of USSOR - Analysis of Rates (IR) and suitably modified with use of carriage and labour rates of CPWD)

S. No. Description Unit Quantity Rate Amount Remarks


Details of cost for 1 cum
A MATERIALS & TRANSPORTATION:
Rate for moorum taken from Item
no. 0810 of Basic rates (Materials) of
1 Moorum cum 1 450.00 450.00 CPWD Delhi DAR 2012.

Rates based on item no. 1.1.1 of


Carriage of Materials rates (by
Transportation of Morrum by
mechanical means including mechanical transport) of CPWD Delhi
2 Cum 1 66.23 66.23
loading and unloading for lead DAR 2012. Contractor's profit &
upto 1 km
overhead @ 15% has been deducted
from the CPWD rate.
Fill in lead qty as per actuals. Rate is
based on item no. 1.1.1 of Carriage
of Materials rates by mechanical

Extra for every km or part transport of CPWD Delhi DAR 2012.


4 thereof for Lead beyond 1 km Km 4 8.63 34.52 Deduct rate for 1 km lead from the
but upto 5 km rate for 5 km lead and divide by 4 for
average rate per km. Contractor's
profit & overhead @ 15% has been
deducted from the CPWD rate.
Fill in lead qty as per actuals. Rates
based on item no. 1.1.1 of Carriage
of Materials rates by mechanical
Extra for every km or part
5 thereof for Lead beyond 5 km Km 0 7.38 0 transport of CPWD Delhi DAR 2012.
but upto 10 km Contractor's profit & overhead @
15% has been deducted from the
CPWD rate.
Extra for every km or part
6 thereof for Lead beyond 10 km Km 0 6.08 0 -do-
but upto 20 km

Extra for every km or part


7 Km 0 4.96 0 -do-
thereof for Lead beyond 20 km

Total 550.75
B LABOUR:
Rate taken from Item no. 0128 of
1 Mate day 0.01 260 2.60 Basic rates (Labour) of CPWD Delhi
DAR 2012

Rate taken from Item no. 0114 of


2 Beldar day 0.3 247 74.10 Basic rates (Labour) of CPWD Delhi
DAR 2012

C Total 627.45
Add for water charges @ 1%
D LS 0.01 6.27
(no rate reqd)
Add for Contractor's Profit and
E overheads @15% (no rate LS 0.15 95.06
reqd)
Cost of 1 Cum 728.78 For lead of 5 km
Say 729 For lead of 5 km

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest
available DAR of CPWD / IRUSSOR of Indian Railways

BOQ Item No. 7039

(based on item no. 6.79 of CPWD DAR 2016 )

Code Description Unit Quantity Rate Amount Remarks


Details of cost for 225 cum (450
tonnes)
MATERIAL
Conforming to table…….
45mm to 22.4mm @ 30% = 89.10
cum Qty for 0292, 0294, 0295
codes = 89.10/4 = 22.275 cum
Qty for 2206, 2202 codes =
89.10/2 = 44.55 cum 22.4 mm to
2.36 mm @ 40% = 118.80 cum
Qty for 1179 code = 118.80/2 =
59.40 cum 2.36 mm to 75
microon @ 30% = 89.10 cum
Qty for 2903, 2904 codes =
89.10/2 = 44.55 cum

0292 Stone Aggregate (Single size) : 50 cum 22.275 1000 22275


mm nominal size
293 Stone Aggregate (Single size) : 40 cum 22.275 1300 28957.5
mm nominal size
294 Stone Aggregate (Single size) : 25 cum 22.275 1350 30071.25
mm nominal size
295 Stone Aggregate (Single size) : 20 cum 22.275 1350 30071.25
mm nominal size
2206 Carriage of Stone aggregate 40 cum 44.55 112.79 5024.7945
mm nominal size and above
2202 Carriage of Stone aggregate cum 44.55 103.77 4622.9535
below 40 mm nominal size
294 Stone Aggregate (Single size) : 25 cum 29.7 1350 40095
mm nominal size
295 Stone Aggregate (Single size) : 20 cum 29.7 1350 40095
mm nominal size
1179 Crushed stone 2.36 mm to 12.5 cum 59.4 900 53460
mm size
2202 Carriage of stone aggregate below cum 118.8 103.77 12327.876
40 mm nominal size
2903 stone chippings/screenings 4.75 cum 44.55 1400 62370
mm nominal size
2904 Stone chippings/screenings 150 cum 44.55 1400 62370
micron nominal size
2203 Carriage of Coarse sand cum 89.1 103.77 9245.907
Machinery/ Hire charges:
59 Wet Mix Plant 60 TPH @ 75 t Hour 6.6 800 5280
capacity
70 Generator 100 KVA/125 KVA Hour 6 250 1500
57 Water Tanker 5 to 6 KL capacity Hour 3 150 450
5 km lead with one trip per hour

52 Front end loader 1 cum bucket Hour 6 900 5400


capacity (incl POL)
Tipper 10 tonne capacity (taking
lead = 10 km) = 450x10 = 4500
t.Km
53 Tipper - 5 Cum Ton Km 4950 3 14850
Add 10 percent of cost of carriage 1485
to cover cost of loading and
unloading
65 Paver finisher Machine 100 TPH Hour 6 800 4800

54 Vibratory roller 8 to 10 tonne Hour 3.9 600 2340


LABOUR 0
128 Mate Day 0.48 617 296.16
139 Skilled Beldar (for floor rubbing 2 617 1234
etc.)
114 Beldar 10 558 5580
Total 444201.69 W
Add 1% Water charges on W 4442.02
Total 448643.71 X
Add 15% Contractor's profit and 67296.56
overheads on X
Total 515940.26 Y
Add Cess at 1% on Y 5159.40
Total 521099.67 Z
Add GST @ 12% on Z 62531.96
Total 583631.63
Cost for 225 cum (450 Tonne) 583631.63
Total Cost Per Cum 2593.92
Say 2594.00

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest
available DAR of CPWD / IRUSSOR of Indian Railways

BOQ Item No. 7040

(based on APMIP 2017 - 18 Commissioner of Horticulture A.P., Guntur )

Item No. Description Size Unit Rate (Rs.) Quantity Amount (Rs.)
Supply and laying of Drip
Irrigation system
(A) HEAD UNIT
1 Hydro - cyclone filter 50m 3/hr 2" No 2701.60 1.00 2701.60

2 Disc Filter 50 3/hr 2" No 4103.00 1.00 4103.00


3 Inlet manifold (pp) for HA 63 mm No 373.70 10.00 3737.00
4 Outlet manifold (pp) for HA 90 mm No 560.60 10.00 5606.00
5 Pressure Gauage 2" No 351.00 2.00 702.00
6 PP Ball valve/ control valve 63 mm No 519.60 3.00 1558.80
7 Air Release Valve 1" No 110.10 2.00 220.20
8 By Pass tee (flange end) PP 90 mm No 256.50 5.00 1282.50
Sub Total Head Unit (A) 19,911.10
(B) FIELD UNIT INCLUDING
SECONDARY TRANSPORTATION

Item No. Description Size Unit Rate (Rs.) Quantity Amount (Rs.)
1 PVC Pipe (4 kg/cm2) 90 mm mtr 78.02 300.00 23406.00
2 PVC Pipe (4 kg/cm2) 63 mm mtr 38.81 400.00 15524.00
3 PVC Pipe (6 kg/cm2) 40 mm mtr 24.59 100.00 2459.00
4 PVC BALL VALVE / Control Valve 63 mm mm 356.00 6.00 2136.00

5 PVC Flush Valve 63 mm mtr 65.80 8.00 526.40


6 LLDPE Plain Lateral, 16 mm CL I 16 mm mtr 6.53 100.00 653.00

7 Emitting Pipe 16-4 50 CL I (JTL) 16 mm mtr 9.58 8550.00 81909.00

8 Grommate 16 mm No 1.47 1500.00 2205.00


9 Take off 16 mm No 1.41 700.00 987.00
10 Joiner 16 mm No 1.47 556.00 817.32
11 End Cap 16 mm No 1.29 500.00 645.00
Sub Total Head Unit (B) 131,267.72
Total Head Unit (A) and (B) 151,178.82
12 Labour Charges skilled labour - LS 4100
Rs.600X4 days = 2400
Helper - Rs.425X4 days = Rs.1700
Total = Rs.4100

Total Head Unit (A) and (B) and Labour Charges 155,278.82
Over Head Charges 15% 23,291.82
Grand Total Head Unit (A) and (B) 178,570.64

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken from latest
available DAR of CPWD / IRUSSOR of Indian Railways
Standard Rate Analysis for Site Specific Items of Schedule 8 of the BOQ

BOQ Item No. 8001

(based on item no. 033060 of USSOR - Analysis of Rates (IR))

S. No. Description Unit Quantity Rate Amount Remarks


Rate for JK Super cement in Delhi as published
Supply of cement in The Economic Times, Delhi edition on
bag of 50
1 (OPC 43 Grade) at kg 1 258.00 258.00 23/07/13.
site Prevailing market rate of reputed brand plus
cost of transportation to site.

Add for Contractor's


2 Profit and overheads LS 0.15 38.70
@15%

Cost of 1 bag 296.70


Say 297

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken
from latest available DAR of CPWD / IRUSSOR of Indian Railways

BOQ Item No. 8002

(based on item no. 033060 of USSOR - Analysis of Rates (IR))

S. No. Description Unit Quantity Rate Amount Remarks


Rate for ACC cement in Delhi as published in
Supply of cement The Economic Times, Delhi edition on
bag of 50
1 (OPC 53 Grade) at kg 1 268.00 268.00 23/07/13.
site Prevailing market rate of reputed brand plus
cost of transportation to site.

Add for Contractor's


2 Profit and overheads LS 0.15 40.20
@15%

Cost of 1 bag 308.20


Say 308

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken
from latest available DAR of CPWD / IRUSSOR of Indian Railways

BOQ Item No. 8003

(based on item no. 033060 of USSOR - Analysis of Rates (IR))

S. No. Description Unit Quantity Rate Amount Remarks


Rate for JK Super cement in Delhi as published
Supply of cement in The Economic Times, Delhi edition on
bag of 50
1 1 245.00 245.00 23/07/13.
(PPC) at site kg
Prevailing market rate of reputed brand plus
cost of transportation to site.

Add for Contractor's


2 Profit and overheads LS 0.15 36.75
@15%

Cost of 1 bag 281.75


Say 282

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken
from latest available DAR of CPWD / IRUSSOR of Indian Railways
BOQ Item No. 8004

(based on item no. 033060 of USSOR - Analysis of Rates (IR))

S. No. Description Unit Quantity Rate Amount Remarks


Rate for JK Super cement (PPC) in Delhi as
published in The Economic Times, Delhi edition
Supply of cement bag of 50
1 1 245.00 245.00 on 23/07/13 is considered as PSC rate is not
(PSC) at site kg published in ET.
Prevailing market rate of reputed brand plus
cost of transportation to site.

Add for Contractor's


2 Profit and overheads LS 0.15 36.75
@15%

Cost of 1 bag 281.75


Say 282

Note: Wherever rates have been taken from CPWD DAR or IRUSSOR, the same should be taken
from latest available DAR of CPWD / IRUSSOR of Indian Railways