PLAN SEQUENCES OF OUTSTANDING PIPIN

Estimation Actual
m Work Description
Date Duration Date Duration

Installing Temporary Spool Pump 3 to


1 12-Aug-20 1 day 12-Aug-20 1 day
Pump 2
F OUTSTANDING PIPING AND TIE-IN WORKS

Impact To
Detail work Progress
Sales
- Connecting new pipe spool for
pump no 3 to pump no 2. to supply Done 100% filling station
B-30 from tank to gantry
Remark
Schedule of Outstanding Tie-in Works

12-Aug
13-Aug
14-Aug
15-Aug
16-Aug
17-Aug
18-Aug
19-Aug
20-Aug
21-Aug
Plan/
No TIE-IN LIST WORKS
Actual
Plan x
1 TP1 (S1A)
Actual
Plan x
2 TP2 (S1B)
Actual
Plan x
3 TP3 (S1C)
Actual
Plan
4 TP4 (S1D)
Actual
Plan
5 TP5 (S1E)
Actual
Plan x
6 TP6
Actual
Plan x
7 TP7 (S3A)
Actual
Plan x
8 TP8 (S3B)
Actual
Plan x
9 TP9 (S4A)
Actual
Plan x
10 TP10 (S4B)
Actual
Plan x
11 TP11 (S4C)
Actual
Plan x
12 TP12 (S7A)
Actual
Plan x
13 TP13 (S7B)
Actual
Plan x
14 TP14 (S7C)
Actual
Plan x
15 TP15 (S7D)
Actual
Plan x
16 TP16 (S7E)
Actual
Plan x
17 TP17 (S8A)
Actual
Plan x
18 TP18 (S8B)
Actual
Plan x
19 TP19 (S8C)
Actual
Plan x
20 TP20 (S5A)
Actual
Plan x
21 TP21 (S10A)
Actual
Plan x
22 TP22 (S10B)
Actual
Plan x
23 TP23 (S10C)
Actual
Plan x
24 TP24 (S10D)
24 TP24 (S10D)
Actual
x
x
22-Aug
23-Aug
24-Aug
25-Aug
26-Aug
27-Aug
28-Aug
29-Aug
30-Aug
31-Aug
1-Sep
2-Sep
3-Sep
4-Sep
5-Sep
6-Sep
7-Sep
8-Sep
9-Sep
10-Sep
11-Sep
12-Sep
13-Sep
No List Tie-in Tanggal Impact Operation Estimasi DWG No Remark
1 TP1 (S1A) 21-Aug-20 Jetty 1 1. Blowing Header Existing Jetty 12".
2 TP2 (S1B) 21-Aug-20 Jetty 1 2. Blowing MLA
A190015-STG-MEP-DWG-001-1
3 TP3 (S1C) 21-Aug-20 Jetty 1 2 hari
(JETTY AREA)
4 TP4 (S1D) 22-Aug-20 Jetty 1
5 TP5 (S1E) 22-Aug-20 Jetty 1
A190015-STG-MEP-DWG-001-2
6 TP6 19-Aug-20 Header in / Out 1 1. Blowing Header In and Out
(HEADER IN AND OUT)
7 TP7 (S3A) 13-Aug-20 HSD
8 TP8 (S3B) 13-Aug-20 HSD
9 TP9 (S4A) 13-Aug-20 HSD 1. Blowing header out HSD line 2,4,6
10 TP10 (S4B) 13-Aug-20 HSD
A190015-STG-MEP-DWG-001-3 (AREA
11 TP11 (S4C) 13-Aug-20 HSD 3 hari
HEADER OUT)
12 TP12 (S7A) 19-Aug-20 FAME
13 TP13 (S7B) 19-Aug-20 FAME
1. Blowing Line fame 6" to tank 1 and tank 2
14 TP14 (S7C) 20-Aug-20 FAME
15 TP15 (S7D) 20-Aug-20 FAME
16 TP16 (S7E) 14-Aug-20 FAME JALUR JETTY A190015-STG-MEP-DWG-001-4 (AREA
2 1. Blowing out line fame
17 TP17 (S8A) 14-Aug-20 FAME JALUR JETTY hari FOR MIXING UNIT)
18 TP18 (S8B) 15-Aug-20 Fame pump 1. Blowing line fame
19 TP19 (S8C) 15-Aug-20 Fame pump
20 TP20 (S5A) 15-Aug-20 B30 To gantri 1. need blow and modification
A190015-STG-MEP-DWG-001-4 (AREA
21 TP21 (S10A) 18-Aug-20 Fame Line 2 hari
PUMP)
22 TP22 (S10B) 18-Aug-20 Fame Line
23 TP23 (S10C) 18-Aug-20 Fame Line
24 TP24 (S10D) 18-Aug-20 Fame Line