Managing Risk and Contractual Liability. Part 1 Design Defects

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Part 1

38 TheStructuralEngineer Professional guidance


January 2015 Contractual liability

Managing risk and contractual


liability. Part 1: Design defects
Case study 1 Expert evidence criticised the
consultant’s approval of using welded end
A consultant was instructed to undertake plates for joining a loadbearing beam, even
In the first of a new structural designs and calculations for only on an ‘in principle’ basis.
series from insurance an extension to a residential property. A While calculations would have revealed
scheme was delivered to the client who the problems with the design, it was
broker Griffiths & gave no indication that he was not satisfied shown that the detail was so inadequate
Armour examining with it. that it should have been obvious to any
contractual risks and A contractor was then appointed reasonably competent engineer, even
who sought advice from the engineer without calculations, that it would fail. The
liability claims, we look as to how the scheme could be ‘better’ use of ‘in principle’ language was therefore
at design defects and implemented. In particular he wanted to irrelevant.
explore whether it would be possible to In relation to the side beam, our expert
ways to avoid them.
splice the rear and side beams which were advised that a reasonably competent
to support the extension at first-floor level. engineer would have specified either that
Although the idea is anathema for most The consultant agreed that this would be high-strength bolts be used or that the
engineers, the most basic cause of claims possible in principle, but explained that he plates be welded. The fabricator’s design
against them is a perceived defect in was too busy to provide the splicing detail indicated neither of these measures. While
the services they have provided. Most which would be required – the contractor the consultant recalled having advised
engineers have procedures in place would have to approach either the steel against the proposed design for the side
which are sufficiently robust to catch manufacturer or another consultant for beam the contractor unsurprisingly had
the majority of errors. It is when these that detail. no recollection of his oral disclaimer of
procedures are not properly followed that Under some pressure from the responsibility.
problems arise. contractor he then mentioned over the In the circumstances, settlement was
Three situations stand out for special telephone that on previous schemes agreed in equal shares with the contractor.
attention: he had specified a certain type of plate
incorporating high-strength friction grip Lesson
• ‘free’ advice bolts – but he reiterated that the contractor Don’t rely on providing further advice
• the inferior alternative design should seek definitive advice on this. on an ‘in principle’ basis. Even with this
• design-and-build contracts Subsequently, the contractor obtained a disclaimer, liability can still attach in
detailed design from the steel fabricators, certain circumstances.
‘Free’ advice proposing that the rear beam be joined
For everyone who offers ‘free’ advice using welded end plates and that the side
there is another person prepared to beam be spliced with plates bolted across
rely on it. In our personal lives this will the side, top and underside. No mention
seldom give rise to litigation. But in the was made of the high-strength friction Case study 2
construction world, whenever engineers bolts. The consultant was faxed a copy
offer advice which turns out to be wrong of these drawings and was again pressed An engineer was engaged by a contractor
they can expect to be sued. for his approval. Again, he confirmed that to provide outline scheme drawings and an
Case studies 1 and 2 highlight how easy the rear beam design was acceptable estimate of materials likely to be required
it can be for construction professionals to ‘in principle’. He advised against splicing on a certain design-and-build project.
get into difficulties when they try to help the side beam on the basis that welded No fees were payable to the engineer up
their clients. plates should ideally be used instead, but to bid stage and there was no certainty
The perils of free advice are clear. If you he commented that the number of bolts that the contractor would be successful.
are offering a view as an engineer then do looked about right. Again, he stressed that For that reason the engineer decided to
remember what it is that you are giving – calculations should be obtained. exempt the work from his internal quality
an expert opinion. While it can be difficult The beams were installed with no management procedures.
to subject oral advice to the same rigours further amendment to the design. As soon The contractor’s bid was successful and
of quality assurance as your written as the temporary supports were removed the engineer was subsequently appointed
advice, the consequences of failing to do the beams sagged, causing damage to for detailed design duties. It then became
so can be significant. the first and second floors and also to the apparent that the quantities of materials
neighbouring property. previously estimated by the engineer did

TSE37_38-39 Health & Safety v2.indd 38 18/12/2014 12:45


www.thestructuralengineer.org

39

not adequately reflect the complexity he carried out a percolation test. To his Subsequently, at the construction stage,
of the scheme design. The contractor surprise, the test was successful and the decking sub-contractor complained
incurred unexpected costs which he he was persuaded to proceed with a that fitting the decking onto conventionally
sought to recover from the consultant. soakaway scheme. flanged beams was more difficult than
The contractor’s case was that the Once installed, the soakaway failed to it would have been had the proprietary
consultant had prepared the design and discharge drainage water. The test result decking manufacturer’s beams been
materials schedules for the purpose of the had been an anomaly and the mound specified. They claimed against the main
contractor’s bid and that the contractor system had to be re-adopted at a cost contractor for additional costs and later
had been entitled to rely upon them for to which the consultant was forced to declared that the design was unbuildable.
that specific purpose. The consultant contribute. Eventually use of the proprietary decking
had to accept that he had failed to It would have been advisable for the was abandoned altogether in favour of
exercise reasonable skill and care and consultant to trust his own experience and pre-cast concrete decks.
consequently was forced to settle the resist the proposed alternative until the The engineer had no defence to the
claim on the best available terms. anomalous percolation results had been significant delay claim which followed.
ratified by further study. He had failed to take into account the
Lesson implications of the contractor’s proposed
Liability attaches wherever an engineer Lesson design changes and to seek the advice of
fails to exercise the required standard Changing your advice under pressure the proprietary manufacturer. He should
of care. That standard is no lower where from others nearly always saddles you have stuck to the original design concept.
a lesser fee has been agreed or where with additional risks. Design changes The matter settled for a sum in excess of
work has been undertaken in good faith are often price driven – where a saving £900 000.
but effectively free of charge. is made the engineer rarely takes any
credit, but if the alternative design Lesson
fails then he will always be the easiest Even an apparently minor amendment to
The inferior alternative design defendant to pursue. a carefully considered design can give
By and large, highly trained staff and an rise to significant delay. This case clearly
appropriate checking regime identify illustrates one of the essential risks of
potential design defects long before Design-and-build contracts design-and-build schemes.
they are released into the client’s hands. Design-and-build procurement increases
Problems are likely to arise when these by its very nature the likelihood of an
systems are circumvented or not followed alternative design proposal arising. Under Conclusion
with due attention. But this is not usually a fixed-sum contract and with no wriggle Irrespective of the factual scenarios,
a case of carelessness or deliberate room on price, contractors will nearly avoidance of quality controls frequently
avoidance – it frequently occurs via the always look for cost-saving opportunities leads to problems. As the case studies
back door when an engineer is asked to with the engineer’s opinion being treated show, whether it is the last-minute change
consider an alternative design solution like a rubber stamp, at least until something to the established design or the pressures
which has originated from outside their own goes wrong. As Case study 4 illustrates, of working to tight programmes under a
practice. engineers who agree to alternatives often design-and-build contract, the risks are not
The alternative can come along in any lose control of the process from that difficult to spot.
shape or size and seemingly innocuous point onwards, despite being saddled with Just as crucial as implementing quality-
changes to a carefully engineered design ownership of the risk. checking systems is ensuring that those
can lead to disaster. systems cannot be circumvented. Where
Case study 3 highlights the problems properly used, those systems operate to
faced by the ever-helpful consultant Case study 4 protect balance sheets and reputations, and
agreeing to adopt an alternative design for this reason they need to be embedded
proposed by a third party. A structural engineer was retained in into the culture of the organisation.
relation to a new multi-storey steel frame
scheme. The tender design specified This series has been adapted from
Case study 3 a system consisting of lightweight Reinforcing the Simple Messages and
proprietary decking sitting on the flanges Contractual Liability Claims: Lessons to be
A consultant gave advice on the design of steel beams. The use of this product Learned, published by Griffiths & Armour.
of a drainage system for an extension anticipated the bottom flanges on the Griffiths & Armour is a leading
to a property. Mindful of the difficult beams being wider than usual, either by independent and privately owned UK
ground conditions prevalent in the area using specially designed beams or by insurance broker and risk management
he specified a mound drainage system. taking conventional beams and welding a adviser. For further information, visit
The architect regarded this as too costly wider flange to the underside. www.griffithsandarmour.com
a solution and suggested instead that However, in order to economise on or scan the QR code.
a soakaway scheme be explored. This steel quantities, the contractor proposed Griffiths & Armour
had previously been discounted by at tender stage to use unmodified is authorised and
the consultant because of the ground conventionally flanged beams. The regulated by the
conditions. However, under pressure, engineer agreed to this alternative. Financial Conduct
Authority.

TSE37_38-39 Health & Safety v2.indd 39 18/12/2014 12:45

You might also like