Professional Documents
Culture Documents
Topic 3
Topic 3
Topic 3
Topic 3
Project Schedule
Paulo Faroleiro
Project Management
Part 3
Project Information Project Schedule
6 7
31 31
26 18 18 26
7 7
Project
Work Management Tools
(Tasks)
Methodology
Organization
ACTIVITY DURATION
Lost Time.
The duration of a work element is dependent on one of Somebody nominally working full-time on a project is
three things: not available 5 days/week, 52 weeks/year.
1. The amount of time it physically takes to do the work They lose time through holidays, sickness, training,
involved, which in turn is dependent on the number of group meetings, and the like.
people available to do it.
It is suggested that for the average project worker
2. The lead time, or waiting time, for the delivery of these consume 80 days/year; somebody assigned full-
some item is independent of the number of people time to a project does on average 180 days of project
doing the work. work a year, equivalent to 70 percent availability.
3. Some mixture of the two. To allow for this 40 percent is added to the nominal
duration (1.4 = 1.0/0.7).
(3) The schedule can be communicated as: (5) Given the initial schedule and resource
requirements for each activity, a resource schedule can
• An activity listing be calculated showing the requirements for each type
• Bar charts of resource with time. This can be smoothed by
(4) The duration is calculated by comparing the work delaying bulk work to fill peaks and troughs, or by
content to the number of people available, allowing for: extending the duration of the project. The resulting
schedule is frozen as the baseline.
• Lost time
• Part-time working (6) Progress against the schedule can be monitored by:
• Interference • Recording progress on the critical or near
• Communication critical paths
• Lead times • Using tracked bar charts and milestone
• Sequencing of tasks within activities!! tracker diagrams
Part 3
Project Information