REV.

01
IR NO: 03-PO-
0319-72-2023
DATE OF ISSUE:
NOV.25, 2023

Sheet 1 of 11
INSPECTION REPORT

PROJECT NAME PETROJET Saudi Arabia

CLIENT / END USER PETROJET Saudi Arabia

CONTRACTOR PETROJET Saudi Arabia

MATERIAL DESCRIPTION Steel plate

ITP NO. /

CONTRACTOR PO NO. N/A

MR NO. N/A
VENDOR / MANUFACTURER Nanjing Iron & Steel INSP. PLACE 1. Liuhe District, Nanjing
Company Limited City, Jiangsu Province
2. Shanghai Luojing Wharf
warehouse

STAGE OF INSPECTION DESCRIPTION


BEFORE MF'G

DURING MF'G

FINAL Quantity check, Visual & dimension inspection


Marking inspection, Packing inspection, Document review

INSPECTION SUMMARY
On November 25, 2023, the inspector inspected the steel plate in the warehouse of Liuhe District, Nanjing City,
Jiangsu Province and Shanghai Luojing Wharf, and the results were as follows:

1- Product quantity confirmation: the steel plate is mixed with each other, the accurate quantity cannot be
confirmed. Only the top of the plate can be inspected not 100% due to the equipment limit. Result: Pending.

2- Product visual confirmation: Products are stacked, the inspection can not confirm the appearance of the steel
plate according to the proportion, only the appearance of the first steel plate on the top layer. No defect such as
Cracks, notches and sharp bottom imperfections was found. The result is acceptable.

3- On November 22, two 5*2400*9425mm steel plates were found in the port of Shanghai, which were damaged
by side lifting (Revised plate No.23308908050204/23308908020305). Two steel plates of this specification have
been reconfirmed in NISCO and sent to Shanghai Port for replacement later. No defect such as Cracks, notches
and sharp bottom imperfections was found. The result is acceptable.

4- Dimension inspection confirmation: Check the size of 6x2400x9425 & 12x2300x9425 & 20x2400x9425
&10*2400*9425 &5*2400*9425 steel plate, which meets the requirements.

5- Marking inspection confirmation: The inspection confirms the inkjet code and side code of the product, and the
criteria are correct and acceptable.

INSPECTOR NAME: INSPECTOR STAMP:

Li Yong
Nov 25,2023
REV.01
IR NO: 03-PO-
0319-72-2023
DATE OF ISSUE:
NOV.25, 2023

Sheet 2 of 11
INSPECTION REPORT

6- Packing inspection confirmation: Different number of steel plates are bound with steel belts (different
thickness steel plates, the number of bound steel plates is different), stacked together, and covered by rain cloth.

7- Document review confirmation: At present, Nangang replaces two pcs 5*2400*9425mm steel plates. The
quality certificate needs to be resubmitted and reviewed. As of after work on November 25th, 2023. The above
information has not yet been submitted. Nangang reply quality certificate after finishing as soon as possible to
submit for review.

Update: The MTC been revised and reviewed on NOV.27. -Acceptable.

Note: The two new plates number is the same as the old number.

INSPECTION HRS. REPORTING TRAVEL TRAVEL


DATE OF VISIT TOTAL HRS
Normal OT HRS. HRS. DISTANCE

Nov. 25,2023 7 4 1 3 300KM 15

CHECK-LIST
Quality Survey

Description Yes No Description Yes No


Material traceability Welders’ qualification
Document control Repair procedure
Non-conformance control Heat treatment control
Test and measuring equipment control Painting control
NDE qualification Sub-vendors control
Welding process control

Scope of Inspection

Description W M R Description W M R
Mill certificates String test
Material identification Leak test
Welding production test plates / PQR's Inspection after dismantling
Mechanical tests for test plates / PQR's Alignment check

N.D.E. (RT, UT, PT, MT) Electrical certificates


P.M.I. Calibration certificates
Hardness test Routine or type test
Cryogenic test Electrical test
Thickness test Loop test
Holiday test Sequence test
Insulation resistance test
Visual and dimensional Wiring
Weld preparation Earthing
Welding inspection Final acceptance test
INSPECTOR NAME: INSPECTOR STAMP:

Li Yong
Nov 25,2023
REV.01
IR NO: 03-PO-
0319-72-2023
DATE OF ISSUE:
NOV.25, 2023

Sheet 3 of 11
INSPECTION REPORT

Anchor bolts and jig plate


Formed head Tie-in points
Flange face finishing Painting and coating
Internals Preservation
Pneumatic test Name plate
Hydrostatic test Tagging and marking
Heat treatment Packing
Quantity
Impeller over speed test MRB
Rotor balance test
Running test Others:
Performance test
N.P.S.H. test
Vibration measurement
Noise measurement

W = Full witness M = Monitoring R = Document review

NARRATIVE:

1. ATTENDEES
Attendee Name Position Company Name
Xu Chunsen Salesperson NISCO
Li Yong inspector Brooke obo PETROJET

2. APPLICABLE CODES AND STANDARDS


Revision
Doc. No. Description
(Date)
ASTM A36-2019 / Standard Specification for Carbon Structural Steel
Specification for pressure vessel plates, carbon steel, for
ASME SA-516-2021 /
moderate-and lower -temperature service

3. APPLICABLE VENDOR DOCUMENTS


Approval
Doc. No. Revision Description
Status
Po No.0319/72-2023/may/2023 14/10/2023 approved Purchase Order

4. P.O. ITEMS PRESENTED FOR INSPECTION

P.O Item No. Tag Number Description Quantity

1 / Plate size: 2400*9425*6mm A36 158pcs


2 / Plate size: 2400*9425*5mm A36 6pcs
3 / Plate size: 2400*9425*5mm A36 221pcs
4 / Plate size: 2400*9425*10mm A36 174pcs

INSPECTOR NAME: INSPECTOR STAMP:

Li Yong
Nov 25,2023
REV.01
IR NO: 03-PO-
0319-72-2023
DATE OF ISSUE:
NOV.25, 2023

Sheet 4 of 11
INSPECTION REPORT

5 / Plate size: 2300*9425*12mm A36 29pcs


6 / Plate size: 2400*9425*12mm A36 89pcs
7 / Plate size: 2400*9425*14mm A36 57pcs
8 / Plate size: 2400*9425*16mm A36 66pcs
9 / Plate size: 2400*9425*20mm A36 2pcs
10 / Plate size: 2400*9425*26mm SA-516 Gr60N 2pcs

5. P.O. ITEMS NOTIFIED BUT NOT READY FOR INSPECTION

P.O Item No. Tag Number Description Quantity

/ / / /

6. INSPECTION PERFORMED & RESULTS


ITP Step Description Results
1 Quantity confirmation Pending
2 Visual inspection Pass
3 Dimensional inspection Pass
4 Marking inspection Pass
5 Packing inspection Pass
6 Document review Pass

7. INSPECTION DETAILS
1. Quantity inspection
The steel plate is mixed with each other, the accurate quantity cannot be confirmed. Only the top of the plate can be
inspected not 100% due to the equipment limit. Result: Pending.

2. Visual inspection
2.1、Products are stacked, the inspection can not confirm the appearance of the steel plate according to the
proportion, only the appearance of the first steel plate on the top layer(Five steel plates in total).No defect such as
Cracks, notches and sharp bottom imperfections was found. The result is acceptable.

2.2、On November 22, two 5*2400*9425mm steel plates were found in the port of Shanghai, which were damaged
by side lifting (Revised plate No.23308908050204/23308908020305). Two steel plates of this specification have
been reconfirmed in Nangang and sent to Shanghai Port for replacement later. No defect such as Cracks, notches
and sharp bottom imperfections was found. The result is acceptable.

3. Dimensional inspection
Inspection the dimensional of 6x2400x9425 & 12x2300x9425 & 20x2400x9425 &10*2400*9425 & 5*2400*9425
steel plate, which meets the requirements. The measured size data are as follows:
No Measured value Resul
specification Plate No. thickness width length
. t

INSPECTOR NAME: INSPECTOR STAMP:

Li Yong
Nov 25,2023
REV.01
IR NO: 03-PO-
0319-72-2023
DATE OF ISSUE:
NOV.25, 2023

Sheet 5 of 11
INSPECTION REPORT

2330890802030 2411/2409m
1 5x2400x9425 5.11/5.17/5.19mm 9441/9445mm ok
5 m
2330890805020 2413/2412m
2 5x2400x9425 5.37/5.28/5.30mm 9463/9462mm ok
4 m
2310970604020 2407/2406m
3 6x2400x9425 6.40/6.58/6.51mm 9479/9478mm ok
1 m
12x2300x942 2310989010020 2316/2315m
4 12.06/12.07/12.08mm 9462/9461mm ok
5 1 m
20x2400x942 2330912331010 2412/2412m
5 20.19/20.23/20.23mm 9462/9465mm ok
5 2 m
10x2400x942 2330912402030 2406/2405m
6 10.26/10.10/10.14mm 9452/9451mm ok
5 3 m
10x2400x942 2330903906030 2410/2411m
7 10.03/10.07/10.12mm 9460/9459mm ok
5 5 m
The surveyor confirmed that the validity date of the measuring tool is within the validity period and meets the
measurement requirements.

4. Marking inspection
Iinspector checked the plate number and side label of the steel plate, checked the plate number of 7 pieces and the
side label of part of the steel plate, the printing was clear, and the result met the requirements.

Marking sample was listed as follows:


NISCO
23308908050204 UT 435
A36 ASTM A36-2019
5X2400X9425 20231019A
Made in China

Side mark: 23308908050204 A36 5x2400x9425(BU)

5. Packing inspection
Five to ten sheets of steel are stacked with steel straps, stacked together, and covered with a rain cloth to keep rain
water in.

6、Document review
At present, Due to lifting damage. NISCO replaces two pcs 5*2400*9425mm steel plates. The quality certificate
needs to be resubmitted and reviewed. As of after work on November 25th, 2023. The above information has not
yet been submitted. Nangang reply quality certificate after finishing as soon as possible to submit for review. Result:
Pending.
Update: The MTC been revised and reviewed on NOV.27. -Acceptable.
Note: The two new plates number is the same as the old number.

8. MEASURING AND TEST EQUIPMENT


Description Identification No Calibration Due Date

Outside micrometer(0-25mm) 013211251628A 2024.02.07

INSPECTOR NAME: INSPECTOR STAMP:

Li Yong
Nov 25,2023
REV.01
IR NO: 03-PO-
0319-72-2023
DATE OF ISSUE:
NOV.25, 2023

Sheet 6 of 11
INSPECTION REPORT

Steel tape measure(0-15m) 012118252048A 2024.04.12

Steel tape measure(0-3.5m) 012118252029A 2024.04.12

Thickness gauge 019214280035B 2024.04.25

9. OUTSTANDING MATTERS / ACTION


Outstanding matters / Action Action by Due date

/ / /

10. NEXT EXPECTED INSPECTION VISIT: N/A

11. ATTACHMENTS
/ /

12. PHOTOS

Product stacking(At the Port of Shanghai) Product stacking(At the Port of Shanghai)

Product stacking(At the Port of Shanghai) Product stacking(At the Port of Shanghai)
INSPECTOR NAME: INSPECTOR STAMP:

Li Yong
Nov 25,2023
REV.01
IR NO: 03-PO-
0319-72-2023
DATE OF ISSUE:
NOV.25, 2023

Sheet 7 of 11
INSPECTION REPORT

Product stacking(At the Port of Shanghai) Product stacking(At the Port of Shanghai)

Product stacking(At the Port of Shanghai) Product stacking(At the Port of Shanghai)

Steel plate visual inspection(At NISCO) Steel plate visual inspection(At NISCO)

INSPECTOR NAME: INSPECTOR STAMP:

Li Yong
Nov 25,2023
REV.01
IR NO: 03-PO-
0319-72-2023
DATE OF ISSUE:
NOV.25, 2023

Sheet 8 of 11
INSPECTION REPORT

Plate surface marking inspection(At NISCO) Plate surface marking inspection(At NISCO)

Plate side marking inspection(At NISCO) Steel plate length inspection(At NISCO)

Steel plate width inspection(At NISCO) Steel plate wall thickness inspection(At NISCO)

INSPECTOR NAME: INSPECTOR STAMP:

Li Yong
Nov 25,2023
REV.01
IR NO: 03-PO-
0319-72-2023
DATE OF ISSUE:
NOV.25, 2023

Sheet 9 of 11
INSPECTION REPORT

Steel plate visual inspection(At the Port of Steel plate visual inspection(At the Port of
Shanghai) Shanghai)

Steel plate visual inspection(At the Port of Steel plate visual inspection(At the Port of
Shanghai) Shanghai)

INSPECTOR NAME: INSPECTOR STAMP:

Li Yong
Nov 25,2023
REV.01
IR NO: 03-PO-
0319-72-2023
DATE OF ISSUE:
NOV.25, 2023

Sheet 10 of 11
INSPECTION REPORT

Plate surface marking inspection(At the Port of Plate surface marking inspection(At the Port of
Shanghai) Shanghai)

Plate side marking inspection(At the Port of Steel plate length inspection(At the Port of
Shanghai) Shanghai)

Steel plate length inspection(At the Port of Steel plate width inspection(At the Port of
Shanghai) Shanghai)

INSPECTOR NAME: INSPECTOR STAMP:

Li Yong
Nov 25,2023
REV.01
IR NO: 03-PO-
0319-72-2023
DATE OF ISSUE:
NOV.25, 2023

Sheet 11 of 11
INSPECTION REPORT

Steel plate width inspection(At the Port of Steel plate wall thickness inspection(At the Port of
Shanghai) Shanghai)

INSPECTOR NAME: INSPECTOR STAMP:

Li Yong
Nov 25,2023