System 实际 计划 总量 完成百分比 偏差 偏差百分比


Electrical System(Cable Tray) 20310 20132 21190 96% 178 1%
BAS / IT/ Fire System(Cable Tray 32059 31842 33789 95% 217 1%
Electrical(Cable) 256885 259124 274299 94% -2239 -1%
Fire System(Cable) 273165 270386 338000 81% 2779 1%
Ventilation System Air Duct 74101 73145 77105 96% 956 1%
DE-Smoking Air Duct 7784 7512 8901 87% 272 3%
Compressed Air Pipe 11842 11621 13597 87% 221 2%
Heating Water Pipe 24985 24721 25131 99% 264 1%
Sprinkler Pipe 161104 161078 169767 95% 26 0%
Fire Hydrant Pipe 21946 21321 24144 91% 625 3%
Chilled Water and Condensate
Water Pipe 0 0 790 0% 0 0%
Water Supply Pipe 4110 4031 5560 74% 79 1%
Cooling Water Pipe 0 0 440 0% 0 0%
Process Hot Water Pipe 0 ###
Gas Pipe 1858 1721 1858 100% 137 7%
System BS PS ASM CC CMR
Electrical System(Cable Tray) 20132
BAS / IT/ Fire System(Cable Tray) 31842
Electrical(Cable) 259124
Fire System(Cable) 270386
Ventilation System Air Duct 73145
DE-Smoking Air Duct 7512
Compressed Air Pipe 11621
Heating Water Pipe 24721
Sprinkler Pipe 161078
Fire Hydrant Pipe 21321
Chilled Water and Condensate Water Pipe 0
Water Supply Pipe 4031
Cooling Water Pipe 0
Process Hot Water Pipe
Gas Pipe 1721
System BS PS ASM
Electrical System(Cable Tray) 21190
BAS / IT/ Fire System(Cable Tray) 33789
Electrical(Cable) 274299
BAS / IT/ Fire System(Cable) 338000
Ventilation System Air Duct 77105
DE-Smoking Air Duct 8901
Compressed Air Pipe 13597
Heating Water Pipe 25131
Sprinkler Pipe 169767
Fire Hydrant Pipe 24144
Chilled Water and Condensate Water Pipe 790
Water Supply Pipe 5560
Cooling Water Pipe 440
Process Hot Water Pipe
Gas Pipe 1858
CC CMR
System BS PS ASM CC CMR
Electrical System(Cable Tray) 216
BAS / IT/ Fire System(Cable Tray) 63
Electrical(Cable) 0
BAS / IT/ Fire System(Cable) 0
Ventilation System Air Duct 144
DE-Smoking Air Duct 0
Compressed Air Pipe 46
Heating Water Pipe 114
Sprinkler Pipe 276
Fire Hydrant Pipe 22
Chilled Water and Condensate Water Pipe 0
Water Supply Pipe 0
Cooling Water Pipe 0
Process Hot Water Pipe
Gas Pipe 0
Auxiliary beam 7
Interior decoration 23
System BS PS ASM CC CMR
Electrical System(Cable Tray) 216
BAS / IT/ Fire System(Cable Tray) 82
Electrical(Cable) 0
Fire System(Cable) 0
Ventilation System Air Duct 144
DE-Smoking Air Duct 0
Compressed Air Pipe 46
Heating Water Pipe 114
Sprinkler Pipe 276
Fire Hydrant Pipe 22
Chilled Water and Condensate Water Pipe 0
Water Supply Pipe 0
Cooling Water Pipe 0
Process Hot Water Pipe
Gas Pipe 0
Auxiliary beam 7
Interior decoration 23
System BS PS
Electrical System(Cable Tray)
BAS / IT/ Fire System(Cable Tray)
Electrical(Cable)
Fire System(Cable)
Ventilation System Air Duct
DE-Smoking Air Duct
Compressed Air Pipe
Heating Water Pipe
Sprinkler Pipe
Fire Hydrant Pipe
Chilled Water and Condensate Water Pipe
Water Supply Pipe
Cooling Water Pipe
Process Hot Water Pipe
Gas Pipe
ASM CC CMR

On site construction human resources are insufficient


System Unit
Electrical System(Cable Tray) m
BAS / IT/ Fire System(Cable Tray) m
Electrical(Cable) m
BAS / IT/ Fire System(Cable) m
Ventilation System Air Duct ㎡
DE-Smoking Air Duct ㎡
Compressed Air Pipe m
Heating Water Pipe m
Sprinkler Pipe m
Fire Hydrant Pipe m
Chilled Water and Condensate Water Pipe m
Water Supply Pipe m
Cooling Water Pipe m
Process Hot Water Pipe m

You might also like