RENCANA ANGGARAN BIAYA ( RAB )

Pekerjaan : Upah Fabrikasi Struktur Baja & Atap


Proyek : Pembangunan Gudang ( 12 x 24 ) M2
Lokasi : Serang - Banten

HARSAT UPAH
NO URAIAN SATUAN VOLUME FABRIKASI & JUMLAH HARGA
ERECTION

1 Pek. Struktur Baja


Kolom WF 200X100X5,5X8 mm Kg 1,587.20 7,500.00 11,904,000.00
Rafter, WF 150x75x5x7 mm Kg 910.00 7,500.00 6,825,000.00
Balok Regel, WF 150x75x5x7 mm Kg 672.00 7,500.00 5,040,000.00
Overstek, WF 150x75x5x7 mm Kg 126.00 7,500.00 945,000.00
Gordeng CNP 120x50x20x2,3 mm Kg 1,641.64 7,500.00 12,312,300.00
Base Plate, Joint Plate & Stiffener Kg 167.37 7,500.00 1,255,238.19
Win Bacing Ø16 mm Kg 114.00 7,500.00 855,000.00
Trekstang Ø12 mm Kg 115.92 7,500.00 869,375.00
Upah Cat Zincromate Kg 5,334.12 500.00 2,667,060.88
Angkur Ø16 x 600 mm Kg 48.00 25,000.00 1,200,000.00
Baut HTB A325 Ø16 x 2,5" Pcs 200.00 1,500.00 300,000.00
Baut gordeng Ø12 x 1" Pcs 280.00 1,000.00 280,000.00
2 Pek. Atap :
Peredam panas, t = 4 mm M2 382.20 15,000.00 5,733,000.00
Atap Zincalume, AZ 100, t 0,35 mm M2 382.20 15,000.00 5,733,000.00
Nok Zincalume, AZ 100, t 0,4 mm M1 26.00 25,000.00 650,000.00
3 Pintu & Canopy
Pintu Gudang Uk. 2x(1800x3600) mm Unit 1.00 6,480,000.00 6,480,000.00
Canopy Uk. ( 4 x 12 ) m M2 48.00 150,000.00 7,200,000.00
4 Pekerjaan Penunjang
Mobilisasi & Demobilisasi Ls 1.00 - -
Alat Bantu Ls 1.00 - -

Jumlah 70,248,974.07
Jumlah ( Pembulatan ) 70,200,000.00

Jakarta, 05 Nopember 2022


PT. Bahagia Jaya Mandiri

( Ir. Aji Nur Alfajri )


Direktur Utama