Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

JITS CONSTRUCTION CORPORATION

II Vic Valley, Tandang Sora Avenue 1116 , Old Balara, Quezon City, Metro Manila, Philippines

DATE : October 13, 2023

TO: JCCA

PROJECT : Visayas Avenue Medical Center Incorporated

LOCATION: Visayas Avenue, Project 8 Brgy Bahay toro, Quezon City. Metro Manila

FROM: Visayas Avenue Medical Center

Project Site

SUBJECT: Earthquake Incident

INCIDENT REPORT

On October 13, 2023, at around 0835 AM . a Magnitude 5.2 of Earthquake happened at our Mabini Batangas.
The effect of the aforesaid earthquake in our Jobsite is almost unrecognized . Even the minimal effect . After
being notified by the NDRRMC, we then still gathered our workers and immediately informed for a possible
AFER SHOCK for safety preparation.

At around 01:00 PM , together with the project in charge Engr. Jumar Andres. We have conducted an inspection
at the project site , We found out that the said tremor did not cause any damage at our project site.

Prepared by: Noted by :

Novo C. Deplomo Engr. Jumar V. Andres


Safety Officer Project Manager

Received by:

Engr. Vincent Vergara


JCCA