1. Introduction : Guidance Notes
6. Hands-On Expanded
Implementation Support
7. E-Procurement
Guidance Notes
www.isbd.org 3
1. Introduction : Guidance Notes
8. Selection Of Consultants
1. Procurement Plan / Strategy
Document
9. New Procurement Approaches
10.2.Joint Ventures and
Procurement Other
Related Types Of Association
Complaints
Handling
11. Eligibility
12.3.Conflicts
Prior andof Post Review
Interests and Unfair Competitive Advantage
Guidance
13.4.Gender
Advanced ContractingSocial
Consideration, and and Sustainable Public Procurement Page-2 Notes
Retroactive Financing
14. Abnormally Low Tenders-ALT
15.5.Non-Compliance
Procurement in Fragile and Conflict
Affected States
16. Alternative Procurement Arrangements
6. Hands-On Expanded
17. PPP and Other Private Sector Methods
Implementation Support
18. Risk Based Procurement
7. E-Procurement
19. Expedited processes for LLF Projects
Guidance Notes
www.isbd.org 4
Key Guidance Notes
2. Procurement
1. Procurement Plan
Related 3. Prior and
/ Strategy
Complaints
Document Post Review
Handling
5. Procurement in
4. Advanced Fragile and 6. Hands-On
Contracting and
Retroactive Financing Conflict Affected Implementation
States Support
www.isbd.org 5
Key Guidance Notes: Procurement Strategy
Contents (of Guidance Note)
Section 4 -
Section 2 - Assessment of
Section 3 - Section 5 -
Section 1 - Procurement Operating and
Project Stakeholder
Introduction Planning & Beneficiary
Overview Analysis
Strategy Capacity
Section 9 -
Section 6 - Section 8 -
Section 7 - Procurement
Procurement Market
Procurement Options and
Risk Research and
Objectives Recommendati
Assessment Analysis
ons
Annex I - Example Procurement Plan
Annex II - Procurement Options and Recommendations Template
Annex III - Project Overview Template
Annex IV - Procurement Strategy Template
www.isbd.org 6
Key Guidance Notes: Procurement Related Complaints Handling
Contents (of Guidance Note)
Section 6 -
Contract-
Related
Complaints
www.isbd.org 7
Key Guidance Notes: Prior and Post Review
Contents (of Guidance Note)
www.isbd.org 8
Key Guidance Notes: : Advanced Contracting and Retroactive Financing
Contents (of Guidance Note)
Section 2 – Section 3 -
Section 1 -
Advanced Retroactive
Introduction
Contracting Financing
Background Background
Circumstances Purpose
of Use Uses of Retroactive Financing
Safeguards Limitations of Retroactive
Financing
Control Measures
Exceptions
www.isbd.org 9
Key Guidance Notes: : Procurement in Fragile and Conflict Affected States
Contents (of Guidance Note)
Section 2 - Section 3 –
Procurement in Procurement in
Section 1 -
Fragile, Conflict- Fragile,
Introduction
Affected States Conflict-
(Overview) Affected States
Project Design and Procurement Planning
Procurement Preparedness
Situational Response
Application of IsDB Regulations and Procedures
Annex I. IsDB Member Countries
during Emergencies
Annex II. Summary of Measures
for Fragile, Conflict-Affected and Operational Context and Market Conditions
Emergency Situations Organizational and Institutional Support
Use of Procurement Agents
Flexible Arrangements for Procurement
www.isbd.org 10
Key Guidance Notes: Hands-On Expanded Implementation Support
Contents (of Guidance Note)
Bid opening
Section 2. Bid Evaluation
Applicability for Debriefing Bidders and addressing complaints
Section 1 - HEIS at Different Debriefing
Introduction stages of Addressing complaints
Procurement
Contract Negotiations and Technical Discussions
Process
Contract Management/Implementation
Project Preparation: Design of an
Risk Management
effective implementation support plan
Determination of Application
Project Implementation
Termination of HEIS
Preparation of Procurement
Documents Determination of Application for HEIS,
Termination of HEIS and Roles of Different
Bidding Process
Parties in HEIS is given in the Attachment
Pre-Bid meeting
www.isbd.org 11
SPD Standard Procurement
Document
01 Introduction
Use of SBDs , Revision Process and Purpose
www.isbd.org
Introduction (1/4)
Sample Standard
NEW SUITE OF STANDARD PROCUREMENT DOCUMENTS ( SPDs)
www.isbd.org
Introduction (2/4)
www.isbd.org
Introduction (3/4)
www.isbd.org
Introduction (4/4)
Revision Process
SPDs developed from existing SBDs and modified
to reflect the New Guidelines
• Mandatory for
international Maintained existing category classifications:
Use of New SPDs
competitive Goods
procurements Works
where the Project Consulting services
is approved after Maintained structure of SBD documents:
31st March 2019;
Instruction to Bidders (ITB)
Bid Data Sheet (BDS)
• May be used for Employer’s Requirements
national Conditions of Contract
competitive
procurements;
1
Abnormally Low Bid/Proposal
2 New award criteria
3
Notification of Intention to Award,
Standstill Period + debrief
4 Unbalanced or Front Loaded Bids
5
6
Environmental, Social, Procurement-related complaints
Health & Safety
7 Business Day
www.isbd.org
Common Key Changes (2/8)
New Award Criteria Contract is awarded to the Bidder offering the Most Value for Money.
This is the Bidder that meets the Qualification Criteria and whose Bid has been determined to be:
Substantially responsive to the Bidding document Lowest evaluated cost
Time schedule may be taken into account in evaluation. Delay may be monetized and added to the
cost. No credit for earlier completion
Life cycle costs may be taken into account in contracts for “ Goods (equipment)” and “ Design,
Supply & Installation (Plant)”
Availability in the Purchaser’s Country of spare parts and after sales services for equipment
offered in the bid
www.isbd.org
Common Key Changes (2/8)
operating costs, which include consumption of energy, consumables and/or other resources
needed for the use of the product;
maintenance costs, which may include any service charges in this respect and spare parts
that have to be periodically replaced;
Cost of major replacements, and end-of-life costs, such as decommissioning and disposal
www.isbd.org
Common Key Changes (3/8)
Abnormally Low Bid/Proposal
ALB/P occurs
Where the price, in combination with other elements, appears unreasonably low, to the extent that it
raises material concerns as to the bidder’s/proposer’s capability to perform the contract for that
price.
The 5 stages in managing an ALB/P
www.isbd.org
Common Key Changes (4/8)
Unbalanced or Front Loaded Bids
Where the prices for items to be executed at the beginning of the project have been increased and prices for
items at the end of the project have been decreased without altering the total cost. The intention is to increase
the Contractor’s cash flow at the beginning of the project.
www.isbd.org
Common Key Changes (5/8)
Notification of Intention to Award (NIA) + Standstill period
Once Beneficiary decides who to award contract to it
1 must inform other bidders/proposers
www.isbd.org
NEW
Standstill Period Timeline PROVISION
The Standstill Period commences on the day following The Standstill Period expires at midnight
the transmission of the Notice of Intention to Award to on the tenth day (unless extended)
all Bidders/Proposers
EXAMPLE
EXTENDED Standstill
ORIGINAL Standstill Period (10 Business Days)
Period
1 1 1 1 1 1
BUSINES
1 2 3 4 5 6 7 8 9
S DAYS
0 1 2 3 4 5
BIDDER
REQUESTS
DEBRIEF
DATE OF LATE
DEADLINE FOR BORROWER TO PROVIDE DEBRIEF BY THE
DEBRIEF BORROWER
EXTENDED STANDSTILL PERIOD ENDS
24
SPD new
NEW
FEATURE Late Request for Debrief PROVISION
S
If Bidder/Proposer submits a late request for a debrief
Borrower to provide debrief as soon as possible
and normally no later than 15 Business Days after publication of the Contract Award
Notice
EXAMPLE
Standstill Period (10 Business Days) Standstill Period is NOT extended
BUSINESS 1 2 3 4 5 6 7 8 9 10 11 - - - - - - - - 26
DAYS
DEADLINE TO
REQUEST A DEBRIEF
25
Common Key Changes (6/8)
Procurement-related complaints
Procedure for Procurement-related Complaints is detailed in Annex C of the Procurement
Guidelines. New Provisions have been added in the ITB & BDS.
www.isbd.org
Common Key Changes (7/8)
Environmental, Social, Health & Safety
New Optional ESHS Requirements have been added in the SPDs
Contractor required to
submit
Code of Conduct (ESHS) that applies to his personnel, to ensure
compliance with ESHS Obligations
www.isbd.org
Common Key Changes (8/8)
Business Day
www.isbd.org
Some Key SPDs (1/6)
Standard Bidding Document for Procurement of Plant Design, Supply, and Installation
Shall be used by Beneficiaries for procuring of Plant Design, Supply, and Installation contracts
Under International Competitive Bidding among Member Countries (ICB/MC) or
Open International Competitive Bidding (ICB)
Either following a Prequalification process, or without Prequalification.
Use in contracts involving the design, supply, installation and commissioning of specially engineered
plant and equipment, such as:
www.isbd.org
Some Key SPDs (1/6)
Standard Bidding Document for Procurement of Plant Design, Supply, and Installation
The value of the plant and equipment portion Single Stage Bidding- technical & financial
represents the major part of the estimated co proposals submitted together
ntract value,
Two Stage Bidding- technical proposals sub
Or
mitted in 1st Stage & Modified Technical pro
The nature and complexity of the plant and
posals
equipment requires elaborate testing,
commissioning and acceptance procedures + financial proposals in 2nd Stage.
Main Features:
Beneficiary prepares Performance Specifications, not detailed technical specifications.
Bidders propose Concept Design at Bidding stage, and the eventual Contractor prepares the
detailed engineering design.
Contract Price is on Lump Sum Basis.
www.isbd.org
Some Key SPDs (2/6) Standard Bidding Document for Procurement of Major Works
To be used for the procurement of admeasurement (unit price or rate) type of works through
International Competitive Bidding among Member Countries (ICB/MC) or Open International
Competitive Bidding.
These Bidding Documents are not suitable for lump sum contracts without substantial changes
to the method of payment and price adjustment, and to the Bill of Quantities, Schedules of
Activities, and so forth
These SBDW are mandatory and required for use in major works contracts (those estimated
to cost more than USD 10 million, including contingency allowance) unless IsDB agrees to
the use of other IsDB Standard Bidding Documents on a case-by-case basis.
www.isbd.org
Some Key SPDs (2/6) Standard Bidding Document for Procurement of Major Works
Conditions of Contract Based on the 2010 FIDIC MDB Harmonized Edition ( currently being
upgraded to FIDIC 2017 version)
These SBD are required for use in major works contracts (those estimated to cost more than
USD 10 through International Competitive Bidding among Member Countries (ICB/MC) or Open
International Competitive Bidding, with Post-Qualification.
May be used in Unit price contracts but require substantial amendments for lump sum contracts
www.isbd.org 32
Some Key SPDs (3/6) Standard Bidding Document for Procurement of Small Works
PART 1 – Bidding Procedures PART 2 – Works Requirements PART 3 – Conditions of Contract
and Contract Forms
Section I. Instructions to Bidders Section VII. Employer Requirements Section VIII. General
Section II. Bid Data Sheet Conditions (GC)
Section III. Evaluation and Section IX. Particular
Qualification Criteria Conditions (PC)
Section IV. Bidding Forms Section X. Contract Forms
Section V. Eligible Countries
Section VI. IsDB Policy – Corrupt &
Fraudulent Practices
www.isbd.org
Some Key SPDs (4/6) Standard Request for Proposals (SRFP) for Selection of Consultants
The SRFP can be used with different selection methods described in “Guidelines for the Procurement of
Consultant Services”, including:
Least-Cost
Selection (“LCS”)
Selection under a
Fixed Budget
(“FBS”)
Quality-Based
Selection (“QBS”),
www.isbd.org
Some Key SPDs (4/6) Standard Request for Proposals (SRFP) for Selection of Consultants
For Selection Based on Consultant’s Qualifications (“CQS”) or assignments under any selection
method costing less than ID 100,000 equivalent (1 Islamic Dinar, ID = 1 Special Drawing Rights, SDR)
relevant elements of this SRFP may be used and further simplified for the purpose of a particular
assignment
Lump sum contracts are normally used for feasibility study and design assignments
www.isbd.org
Some Key SPDs (5/6)
Standard Shopping Document for Procurement of Works
Used for simple local civil works that are low in value
1
4
Quotations shall be obtained from at least 3
firms
www.isbd.org
Some Key SPDs (6/6)
Should be a sufficient number of local and/or foreign suppliers (a minimum of three) that
can meet the requirements of the procurement and ensure a satisfactory level of price
competition
www.isbd.org