Professional Documents
Culture Documents
WebinarRev1 Time Cost
WebinarRev1 Time Cost
2
INTRODUCTION
What is a Project?
The PMBOK Definition
TEMPORARY
A Temporary Endeavour undertaken
to Create a
Unique Product, Service or Result.
UNIQUE
Definition of Project
UNIQUE OUTCOME
specific purpose, for different stakeholders, done at
TEMPORARY different location, use different design or configuration,
done under different circumstances/situations,
encounter different constraints, facing different risks.
DEFINITE
Beginning & End
UNIQUE
Project – in Brief
04 KNOWLEDGE
Project Management Process
I I Initiating
1
P Planning
P
E Executing
C 6 2
Monitoring & Controlling
5 M&C
7 3 E C Closing
M&C 4
E
I
Project Management Process Group
INITIATING
Beginning of each phase.
PLANNING
Process of formulating and revising project
goals and objectives and creating the project
management plan.
EXECUTING
Putting the project management plan into action
and utilize most project time and resources.
MONITORING & CONTROLLING
Performance measurement are taken.
CLOSING
Brings a formal, orderly end to the activities of a
project phase or project itself.
RAJAH JPSPK2020 : PROSES-PROSES UTAMA DALAM
PENGURUSAN PROJEK
TIME ESTIMATION
Tools and Techniques for Estimate
Expert Judgment
▪expert judgment guided by historical information, provides valuable insight from prior
similar project.
Analogous Estimating
▪uses values from previous similar project as the basis for estimating the same parameter or
measurement for a current project.
Parametric Estimating
▪uses a statistical relationship between relevant historical data and other variable (e.g.
square meter in construction)
Three Point Estimating
▪uses most likely (M), optimistic (O) and pessimistic (P). Estimate = (O+4M+P)/6
Bottom-up Estimating
▪is a method of estimating a component of work individually and then rolls them up to derive
a total project cost estimate.
Expert Judgment - Water Transfer Project
Sungai Perak
To Penang canal
Intake
Structures
Work Break Down Structure
Work package
or activity
Example: WBS FOR ROAD PROJECT
PROJEK PEMBINAAN JALAN
Performance CH 00 - 50 CH 50 - 100
Bond
Stripping of
Site office Stripping of Laying of Excavation Underground Topsoil
Preparation of Install Traffic
Topsoil Geotecxtile Ducts and
Formation and Barrier
Proof Rolling Cable
Survey & Supply and Excavation
Setting Out Install Pipe USM
Excavation Soil Road Line
USM Culvert
Replacement and Road
Subbase Lighting
Site Clearance Marking Common
250mm Column and
& Earthworks Works Excavation
Supply and Feeder Pillar
Common Install V
Excavation shape Drain Roadbase
Concrete Embankment
300mm
Environmental Kerb Fill
Management Embankment
Plan (EMP) Fill
Prime Coat
Fencing and Turfing and
Gating Hydroseeding
Traffic Turfing and
Hydroseeding Binder
Management Course
System (TMS)
Tack Coat
Wearing
Course
Estimate Activity Duration
Parametric Estimating
There is 68.26 % chance that the project will be completed in 46.66 to 55 days.
Three Point Estimating - Example
Most likely (M) =18 days, Optimistic estimate (O) = 14 days and pessimistic
estimate (P) = 26 days.
Expected Duration = 26 + 4 (18)+14 = 18.67 days + and – (Std dev) to get range of
duration
6
Standard Deviation = 26 - 14 = 2 days, Variance = 4
6
There is 68.26 percent chance that the activity will be completed in 16.67 days
to 20.67 days.
The Normal Distribution
The Normal Distribution
Using Bromilow Time Cost Model
2 4
Projek Pantai, T=292C 0.314 Projek Pengairan, T=315C 0.545
di mana :-
T = Tempoh pembinaan
C = Kos
S = Kapasiti
e = Sedia ada (existing)
p = Rancang (plan)
Di mana:
C= cost, T= duration, p =plan, e = existing
Sebuah Rumah Pam berkapasiti 200 cusec telah dibina dengan kos RM 2.3 juta dalam tempoh 18 bulan.
Apakah anggaran kos dan tempoh untuk pembinaan Rumah Pam berkapasiti 280 cusec.
Three quarter rule for cost Square root rule for duration
Anggaran Kos, Anggaran Tempoh,
𝟎.𝟕𝟓 𝟎.𝟓
𝑺𝒑 𝑪𝒑
𝑪𝒑 = 𝑪ⅇ 𝑻𝒑 = 𝑻ⅇ
𝑺ⅇ 𝑪ⅇ
Di mana:
C= cost, T= duration, p =plan, e = existing
COST ESTIMATION
Estimate Costs
Process of developing an approximation of the cost of resources needed to
complete project work;
This includes human, material and equipment and also other known factors that
can be figured in.
Weighing alternative options and examining risks and trade-offs ( make versus
buy, buy versus lease).
Expert Judgment
guided by historical information, provides
valuable insight from prior similar project Analogous Estimating
uses values from previous similar project as
the basis for estimating the same parameter
or measurement for a current project
Parametric Estimating
uses a statistical relationship between
relevant historical data and other variable
(e.g. square meter in construction)
Three Point Estimating
uses most likely (M), optimistic (O) and
Bottom-up Estimating pessimistic cost (P). Estimate = (O+4M+P)/6
Accuracy of
Stage Estimation Method
Estimate
Initiation -25 % to +75 % (Rough Expert Judgement
order of magnitude)
Analogous Estimating
Bottom-up Estimating
End of Planning -5 % to +10 %
A+B+C
A B C Parametric
Estimating
on BQ
• Schedule
of rate
• Expert
Judgement
Bottom up
estimate
WBS
Parametric
Cost= Quantity x Rate
Conclusion