PURPOSE: to standardize the preparation of Heat Stress Management Plans and to verify that ALL MINIMUM requirements are considered & implemented.
SCOPE: applicable to any SA facility. Each Contractor shall prepare a HSMP for its activities. SAPO may be required to prepare a general HSMP applicable to the
T&I/Project site.
MARK EACH BOX WITH A WHERE APPLICABLE, AND WITH AN X WHERE IS NOT APPLICABLE.
HEAT STRESS MANAGEMENT PLAN WILL NOT EXCEED 30 DAYS
DEPARTMENT/PROJECT (CRDD)-Central Region Distribution Department START DATE 04/24/24 END DATE 05/23/24
ENTITY EXECUTING THE
EQUIPMENT (X-56 NRTU) Mastoura Company
JOB
UNIT North Riyadh Tank Unit -(NRTU) NUMBER OF EMPLOYEES As per the work permit
DIVISION (NRTU/Operation Division NUMBER OF SUPERVISORS As per work Activity
SCOPE OF WORK Erection of Scaffolding at OME Building
WORK SCHEDULE From 07:00 AM □ PM 03:30 □ AM PM
24 hrs SCHEDULE □
Yes No Notes:08-HRS 30Mins
STOP
BREAK PERIODS As per the heat Index chart
PERIODS □
From 12:00 AM PM To: 13:00 AM PM □
For Confined Space: ____ MINIMUM 2-MEN TEAM “BUDDY SYSTEM” PROTOCOL
ROTATIONS OF IN PLACE (MANDATORY DURING CATEGORY 4 – RED)
PERSONNEL For Sun-exposed personnel:
30-mins minimum 2-Men Team “Buddy System Rotation” Yes □
No Activity
TYPES OF SHELTERS PROVIDED (describe structure type, dimensions, covering material, ventilation or A/C). INCLUDE
NUMBER OF SHELTERS
SHELTERS/SHADING FOR INDIVIDUALS (e.g.: Flagman, Manual Ground Breaking, others)
1. Umbrella For Rest shelter 1. (1)-Umbrella
2. 2.
3.
4.
OTHER CONTROLS: □Can Mechanical/powered assistance replace manual labor? Specify:___ □ Shaded Jobsites (Specify):
Others Umbrella single shade for standby man & Rest shelter for workers
Above 43°C (110°F), air chillers or A/C shall be provided on Confined Spaces or similar enclosed work areas