Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

T m)

Time for Cleaning the Welds : like getting tools, electrodes, cables, etc., the time
for pre-heating the joint at the beginning and also
This was another area which required improve- between successive layers and the breaks in the fore-
ment. The fear of failure of a joint was uppermost in noon and afternoon for tea, other unavoidable delays
the welders' minds. Hence, excessive cleaning to very and time for personal needs, rest, etc., not more than
minute detail was the order of the day. Here again, 330 minutes of clear welding time can be available.
it was a question of inducing confidence in the welders. This results in an arcing time of only 100-110 minutes
per shift for a ratio of 1: 3. Actually, the arcing time
In general, for an arcing time of 100 minutes, the was around 90 to 100 minutes only, in most of the
time taken for cleaning and other manipulations was cases in pressure parts welding. This works out to
about 200 minutes making a total welding time of 300 only 2 0 % of the shift time. This appears to be low
minutes. The ratio between arcing time to total time compared to the figures given in welding text books.
was as high as 1 : 3 This was a phenomenon observed
wherever welding of parts subjected to high pressure, J. A. OATES in his "Welding Engineer's H a n d
and radiographic tests, was involved. Book" says—

Available data for structurals and sheet metal "The cost of labour is assessed by the weight
welding of non-pressure parts show that the ratio of metal deposited in a given time, that is
between arcing time and total time should be about how many minutes per hour the arc is actually
1 : 1.6. 500 cases were taken from the standards for in operation. The time expressed as a per-
different joints for plates of different thickness and in centage is the operating or output factor
each case the arcing time as a percentage of the total In a well organised shop an output factor of
time has been worked out. The result is tabulated in 50% should cover the ordinary type of work.
a frequency distribution as shown in Table No. 4. For site welding in the field, except in cases
where there are large quantities of continuous
The table shows that 66% of the welding time welds, the output factor may be as low as
should be arcing time. This works out to a ratio of 20%".
1 : 1.5 between arcing time to total time. In the plant
also, for non-pressure parts welding, this ratio was Similar figures can also be found in the
achieved. But in the case of pressure parts, the ratio already mentioned "N.P.C. Report No. 34—
was 1 : 3 . The effect of this ratio can be explained as Welding Industry in U.S.A., West Germany
follows :— and Britain".

In a shift of 480 minutes, leaving the time taken Steps were taken in this direction also. Table
by the operator for initial preparation for the day No. 3 shows how the cleaning time has come down as

TABLE No. 4

% of arc time to total welding time Mid Value Frequency Frequency %

40.00 to 44.99 42.5 1 0.2


45.00 to 49.99 47.5 2 0.4
50.00 to 54.99 52.5 4 0.8
55.00 to 59.99 57.5 19 3.8
60.00 to 64.99 62.5 189 37.8
65.00 to 69.99 67.5 126 25.2
70.00 to 74.99 72.5 152 30.4
75.00 to 79.99 77.5 7 1.4

500 100.0

INDIAN WELDING JOURNAL, APRIL 1972

You might also like