GATE 1 GATE 2
2 GLASS BEAD M/C OPEN AREA
NADCAP - Area denoted in
dotted lines
10
ZINC - BARREL SECTION
5
7 8 OFFICE
ZINC - TANK SECTION
LAB
1
6
ANODIZING SECTION 9
ZINC - CLEANING SECTION
2
OPEN AREA
3
11 PAINT
TOILET BOOTH
12 4
SAI LINKS ( INDIA ) PVT.LTD. - F-55 ( Housekeeping Schedule )
ZONE DEPARTMENT / AREA WORK TO BE DONE RESPONSIBILITY
1 ANODIZING All m/c cleaning Mr. Santosh Takalkar
All display chart cleaning
Maint chart to update
Ensure Mat on pallets
All material at proper place
C.E.O.
PRODUCTION PRODUCTION
STORES + PLANNING QUALITY STORES (ZINC + PLANNING QUALITY
(ANODIZING) (ANODIZING) (ANODIZING) PLATING) (ZINC PLATING) (ZINC PLATING)
PREPARED BY APPROVED BY