CL-NG-6460-002-043 Checklist for Control Cable Commissioning Page Number: 1 of 1
1.0 Equipment General Data and Information
Substation Bay/Panel Equipment Serial No 2.0 Mechanical Checks and Visual Inspections Item Description Done Remarks 1. Inspect for physical damage/defects and verify the thickness / quality of the insulation, metallic sheath, metallic shield, and jacket. 2. Verify all cable connections as per approved drawing. 3. Verify that all cables and cores are labeled correctly. 4. Check for proper cable duct, support, clamping, trays and proper grounding. 5. Check tightness of terminals, ferrule numbering and confirm the cables are secured. 6. Check that all cable trays are secure and correctly grounded. 7. Check all cables are securely supported throughout. 8. Check the path/separation of control & power cables 9. Visual inspection, size and rating confirmation. 10. Size checking against rating required. 3.0 Electrical Tests Item Description Done Remarks 1. Insulation Resistance Test with 1 kV DC insulation tester. 2. Phasing and continuity check.