Operation/Job Description: Project
Operation/Job Description: Project
Work interfering with other jobs- clash of Before starting operation Muster and all section Master/STSL/
work leader responsible for location and vicinity of Doctor
H L M
location to be informed to avoid any interference.
Work Permit to be issued.
Fatality or injury due to failure of critical The safety gear (lifting sling, shackles etc.) to be STSL/ Deck
components which are inadequate checked for integrity. They must be available on officer/ CROP
L L L
inspected, maintenance or exceed site in sufficient number.
equipment limitations. Fall from height. Visual check.
Recommended as below: Muster/CROP
Preparation Wind speed less than 15 Knots at 10 meters
above sea level;
Weather Condition Sea state must have maximum significant
waves less than 1.5 meters; H L M
Maximum rolling movement of the Stand by
Vessel of 3 degrees (single amplitude);
Visibility must be such that all persons involved
in the transfer are able to see each other.
Slips, falls, personnel injury, basket Proper PPE to be used,
slung improperly Personnel to be instructed/trained on proper way to STSL/Deck
Hook up basket hook up basket Officer
3. Inspect area for trip hazards
L L L
Competent person to inspect rigging;
Fill up checklist
4. Trips, slips, falling. Proper PPE to be used. STSL/Deck H L M
Inspect area for trip hazards Officer/ Doctor
Proper illumination to provide before starting
operation.
Doctor must check patient and secured straps on a
stretchers
Stretchers are properly secured according to
ESVAGT guidelines and good practice to the
Personnel and casualty ESVGT.
embarking basket Competent person must perform inspection of strap
tighteners
Musculoskeletal injury Crew to use manual handling techniques.
Crew instructed by doctor how to carry on with CREW/STSL/
M L M
stretchers. Deck Officer
Proper PPE to be used
Man basket overloading Personal transfer capacity is 4 persons If is
STSL/Deck
medivac two person and casualty on a stretchers L L L
Officer/CROP
max transfer capacity 500kg.
Lifejackets to be distributed and checked if worn
properly
Personnel not wearing proper PPE/ wear Personnel basket transfer briefing must carry on
before start operation STSL/Deck
incorrectly. Webbing are not in used or H L M
Embarkation area to be checked Officer/SV crew
used improperly
Rope webbings are fitted with fast click buckle
straps
5. Clear communication between CROP, Deck officer, STSL/Deck
Area is not ready on board of s/v to
Bridge, S/V. Officer/ CROP/
receive basket, deck crew on board of L M L
S/V crew to give “GOOD TO GO” signal no one SV crew /
s/v not ready to assist landing
else BRIDGE
STSL/Deck
Dropped objects Luggage compartment, check personnel for loose items Officer/ CROP/ M L L
SV crew
Bridge keep sharp lookout
Loss of lee during the transfer result in Clear communication
Master/DP H L M
Basket transfer from S12k to
excessive vessel motion Authorization for personnel transfers can only be
s/v and reverse given by the Master.
Loss of control due to lack of Only competent person with valid certifications can CROP/STSL/ H L M
experience, inadequate training or failure be carry on with task. DECK OFFICER
to follow safe techniques or the transfer CROP additionally must have experience at least 6
plan months operating that type of crane.
Two tug lines with proper length in use
The relevant responsible transfer Supervisor has
the control to instruct the personnel being
transferred
The operator must have a good view of the person
hoisted.
weather condition to be check before start
operation
MOB rescue team are established and FRC made
be ready for launching in case of emergency.
Check weather condition before start operation
Keep at all time lee side for S/V
Only competent person with valid certifications can
be carry on with task.
Proper PPE to be used
Life jacket to be used
Where necessary, SOLAS immersion and anti
exposure suits are required to be used above 45°
parallel and where water temperature is below
Injury or fatality due to crushing, 10°C
The Crane Operator shall have a full and STSL/DECK
6. pinching, impact, fall from height or
OFFICER/CROP
H L M
drowning unobstructed view of the take-off and landing area
as well as the full lifting trajectory
Lifting and lowering of the personnel shall be
conducted above open sea whenever possible, not
above the deck of the vessel.
The Crane Operator will pay out sufficient lifting line
slack to ensure that the transfer basket is not
affected by any motion of the vessel
The relevant responsible transfer Supervisor has
Basket transfer from S12k to the control to instruct the personnel being
s/v and reverse transferred
Personnel must not leave the transfer basket until
instructed to do so by the receiving transfer
Damage to materials and equipment Stored in the proper manner and visual inspection prior
7. Unhook & stow basket
to storage
CROP L L L
Consequen Accidental consequences Accidental consequences for property and Probability Descripti
Definition Risk Value Action / Time scale Risk Level Probability
ce Level for bodily injuries environment Level on
All personnel involved in this job must sign the JSA to confirm attendance to the pre-job meeting and to acknowledge their duties and
responsibilities:
Workgroup members: