6ABHA09- INSPECTION & TEST PLAN (ITP) FOR INSTALLATION & TESTING OF GLAZED CURTAIN WALLS
Review Sheet
Ref: 6ABHA09-ABHA-08-MBL-AR-ITP-00010 Revision 00 Date & Time 14 January 24
Client: Saudi Entertainment Ventures
Project Management Consultant and Engineer Saudi Consolidated Engineering Company - Khatib & Alami
Assistant Engineer and Supervision Consultant DAR International for Engineering Consultancy
Contractor Modern Building Leaders
Area / Location
Discipline:
☐ Civil ☐ Structural ☒ Architectural ☐ Mechanical ☐ GM ☐ Electrical ☐ HV ☐ IR ☐ Plumbing ☐ Quality ☐ BIM
☐ Project Control ☐ Quality Management ☐ FLS/Safety ☐ General ☒ Other (specify if other): Inspection Test Plan
Page 1 of 1
Client PMC LDC Contractor
Saudi Entertainment Ventures Khatib & Alami Dar International Engineering Consultancy Modern Building Leaders
Project name: Program 6: Abha Entertainment Complex
Location: Abha Contract No.:
Attachments 1 2 3
Date: 13-Jan-24
Remarks:
Document Status
(A) Approved As Submitted (B) Approved with Comments (C) Revise and Resubmit (D) Rejected
Has the mock-up inspection tests with frequency of the mock-up inspection tests been
2
included with Respecting W and H points?
3 Has the samples inspection tests been included with Respecting W and H points?
Are items to be inspected and tested including test stages identified and presented in a
4
logical construction order?
Are verifying documents has been identified with clear reference to applicable checklists
9
and forms?
Does the ITP include notification requirements for “Work Inspection Request” (WIR)/
10 Material inspection request (MIR)?(Minimum (24) hours for site work and (1) week in
advance for inspections requested during holidays and Fridays.
Does the ITP include specific code/ standard to be used for each inspection/ test in
11
accordance with the requirements of SEVEN List of Codes & Standards?
Are the 3rd party, MBL, LDC, PMC ,and SEVEN hold, witness review points been
14
established among all parties with a clear definition in the legend?
15 Does the ITP specify the percentage of tests to be done/ sampling plan?
17 Are the reporting forms & checklist been included as an attachment to the ITP?
Has the inspection & test plan been signed off by designated competent preparer,
19
reviewer and approver?
Does the inspection & test plan format & language is as per project requirements and
20
easy to understand?
Does the inspection & test plan include the repair stage or contain a reference to a
21
separate Special Procedure for repairs?
Does the inspection and test plan require an activity for the protection of completed
22
work? If yes is the approved Method/procedure mentioned in the Reference?
Conclusion/ Remarks
Signature
Date
Utilized By
Document Number 6ABHA09-ABHA-08-MBL-AR-ITP-00010 Document Type INSPECTION AND TEST PLAN Contract Number
Document Title Inspection Test Plan Issued by MBL SEVEN Project ID
Revision Number 0 Issue Date 06.01.2024 Start Date End Date
Title 6ABHA09 - Inspection & Test Plan (ITP) for Installation & Testing of Glazed Curtain Walls
ITP Number 6ABHA09-ABHA-08-MBL-AR-ITP-00010 Discipline ARCHITECTURAL ITP Approval Date
Project Title ABHA-P6 Entertainment Complex
WIR No
INSPECTION
RESPONSIBILITY
ITEM Acceptance Reference Recording
TASK / ACTIVITY Frequency Check List REMARKS
FLS/AC
SEVEN
PARTY
NO. Criteria / Controlling Document Document
3RD.
PMC
MBL
LDC
1.0 DOCUMENT REVIEW
1.1 Material Submittl , Shop Drawing , Methoed Statement Review Prior to start Activity N/A Specs 08 11 13 Aconec Approval N/A H H R N/A SR
1.2 Mock-up Sample Board & Preinspection Dossiue , PRQ, 3rd party Review Prior to start Activity N/A Specs 08 11 13 Aconec Approval N/A H H H N/A N/A
Submittal approved
2.1 Submission of drawings, MIR & review and approval Document Review 6ABHA09-ABHA-08-MBL-AR-TRN-00102 Specs 08 44 13 MIR N/A H H R N/A N/A
Design
Document Review
3.1 EXAMINATION Once 6ABHA09-ABHA-08-MBL-AR-TRN-00102 Specs 08 44 13 - 7 checklist 2.1 N/A H W S N/A N/A
/ Visual Inspection
Specs 08 44 13 - 8,SD&
3.3 TOLERANCES Test Once 6ABHA09-ABHA-08-MBL-AR-TRN-00102 Checklist 2.2 N/A H W S N/A N/A
CL2.1Survey report
Document Review
3.5 PROTECTION Once 6ABHA09-ABHA-08-MBL-AR-TRN-00102 Specs 08 44 13 - 9 &SD Checklist 2.4 N/A H W S N/A N/A
/ Visual Inspection
Specs 08 44 13 - 9 ,SD &
3.6 Curtain Wall check & Pull out Test Test (Pull Out) Once 6ABHA09-ABHA-08-MBL-AR-TRN-00102 Survey report & MEP WIR H H H R N/A S/R
Clearance
Water Penetration
3.7 Final inspection & Water Test Resistance Once 6ABHA09-ABHA-08-MBL-AR-TRN-00102 Specs 08 44 13 - 5 &SD WIR H H H R N/A S/R
GENERAL NOTES
1 The first three incidents of each Inspection or testing activity listed require 100 % participation by the Consultant. After this period, the Consultant may adjust the levels of SEVEN participation based upon the Contractor’s performance.
2 Surveillance: Q A/QC organization to monitor work in progress without notice from Construction Organization
3 Witness: Q A/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative is not present.
4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Consultant
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test S Surveillance
2.1 EXAMINATION
. Verify that wall openings and adjoining air and vapor seal 08 44 13-7
b ☐ ☐ ☐
materials are ready to receive work of this section. 3.02-B
Page 1 of 5
2.3 TOLERANCES ☐ ☐ ☐
08 44 13-8
A Maximum Variation from Plumb: (3 mm/m) ☐ ☐
3.04-A ☐
Maximum Misalignment of Two Adjoining Members 08 44 13-8
B
Abutting in Plane (0.8 mm). 3.04-B
☐ ☐ ☐
Sealant Space Between Curtain Wall Mullions and
08 44 13-8
C Adjacent Construction: Maximum of (20 mm) and ☐ ☐ ☐
3.04-C
minimum of (6 mm)
2.4 ADJUSTING ☐ ☐ ☐
08 44 13-9 ☐
A Adjust operating sash for smooth operation. ☐ ☐
3.06-A
Page 3 of 5
2.5 CLEANING ☐ ☐ ☐
08 44 13 9
* Survey Report & MEP Clearance after framing
3.07 B
☐ ☐ ☐
Remarks
Page 4 of 5
☐ The work is ready for inspection ☐ Document Reviewed ☐ Work Inspected ☐ Test Records Verified