WORK SCHEDULE/ PLAN

WORK PLAN FOR PRIORITY BUILDINGS


DURATION
S/NO ACTIVITIES (DAYS)
Baseline Start Baseline Finish Actual Start Actual Finish

A AREA 5 CONTROL BUILDING WORKS- BEFORE PANEL INSTALLATION


Completion of roof 8 26-Jul-23 3-Aug-23

Painting of Walls( phase1 - screeding and first coat) 7 27-Jul-23 3-Aug-23

Supports for False Ceiling 5 2-Aug-23 7-Aug-23

False Ceiling Installation 5 8-Aug-23 13-Aug-23

Floor Tiles Installation

Electrical & Lighting system Installation (partial installation- electrical conduits) 15 27-Jul-23 11-Aug-23

F&G Panels & Detectors Installation 5 9-Aug-23 14-Aug-23

Electrical Control Panel Installation( liginth panels) 3 17-Aug-23 20-Aug-23

INSTALLATION OF PROCESS CONTROL PANELS (by others) 25-Aug-23


AREA 5 SUBSTATION BATTERY ROOM WORKS- BEFORE EQUIPMENT
B INSTALLATION
Substaion A (Tiling, Painting) 9 7-Aug-23 16-Aug-23

Substation B (Construction, Painting) 15 30-Jul-23 14-Aug-23

Substation C (Tiling, Painting) 9 4-Aug-23 13-Aug-23

Substation D (Construction, Tiling, Painting) 15 31-Jul-23 15-Aug-23

Substation E (Construction, Tiling, Painting) 15 2-Aug-23 17-Aug-23

Substation F (Tiling, Painting) 9 5-Aug-23 14-Aug-23

C SUBSTATION WORKS- BEFORE PANEL INSTALLATION


Substation 10 (Dismantling works through to internal dust-free condition 15 26-Jul-23 15-Aug-23

Substation 10E (Dismantling works through to internal dust-free condition 15 29-Jul-23 15-Aug-23

Substation 5 (Dismantling works through to internal dust-free condition) 40 15-Aug-23 24-Sep-23

Substation 15 (Dismantling works through to internal dust-free condition) 30 30-Jul-23 29-Aug-23

Substation 5.1 (Dismantling works through to internal dust-free condition) 30 15-Aug-23 14-Sep-23

Substation 5.3 (Dismantling works through to internal dust-free condition) 30 20-Aug-23 19-Sep-23

Substation 11 (Dismantling works through to internal dust-free condition) 45 15-Aug-23 29-Sep-23

Substation 11.1 (Dismantling works through to internal dust-free condition) 30 20-Aug-23 19-Sep-23

D BATTERY ROOM OF SUBSTATION WORKS- BEFORE EQUIPMENT INSTALLATION

Substation 1 Battery Room (Polishing and Painting) 3 27-Jul-23 30-Jul-23

Substation 10 Battery Room (Construction, Tiling, and Painting) 7 31-Jul-23 7-Aug-23

Substation 5 Battery Room 6 19-Aug-23 25-Aug-23

Substation 5.1 Battery Room 5 21-Aug-23 26-Aug-23

Substation 15 Battery Room 10 2-Aug-23 12-Aug-23

Substation 5.3 Battery Room 9 25-Aug-23 3-Sep-23

Substation 11 Battery Room 9 20-Aug-23 29-Aug-23

Substation 11.1 Battery Room 9 25-Aug-23 3-Sep-23

SUBSTATION TRANSFORMER BAY WORKS - BEFORE EQUIPMENT


E
INSTALLATION
Substation 1 (Demolition and Refurbishment) 7 28-Jul-23 4-Aug-23

Substation 10 (Demolition and Refurbishment) 7 3-Aug-23 10-Aug-23

Substation 5 (Demolition and Refurbishment) 7 9-Aug-23 16-Aug-23

Substation 5.1 (Demolition and Refurbishment) 7 15-Aug-23 22-Aug-23

Substation 15 (Demolition and Refurbishment) 7 2-Aug-23 9-Aug-23

Substation 5.3 (Demolition and Refurbishment) 7 21-Aug-23 28-Aug-23

Substation 11 (Demolition and Refurbishment) 7 27-Aug-23 3-Sep-23

Substation 11.1 (Demolition and Refurbishment) 7 2-Sep-23 9-Sep-23