1.0 INTRODUCTION
All AC Distribution Panels must be tested in the factory before delivery to the site and
must be tested by a pre-qualified testing and commissioning contractor at the site after
installation for processing to begin the on-site testing and commissioning phase.
Commissioning tests at the site are done to prove that:
2.0 RESPONSIBILITIES
- Anyone working in the testing location during the commissioning stage must follow
the safety instructions as per SEC rules and CSD employees are responsible for
applying safety rules in all places that they are working in.
- The PMD is responsible for committing the Main Contractor to prepare the testing
and commissioning places to be done in proper climate conditions as per Company
policies, procedures and accepted temperatures the relays, devices and test
equipment can be tested or operated within it.
- CSD Employee is responsible for:
o Witnessing the activities according to the approved specifications and design.
o Checking and witnessing all activities required for AC Distribution Panels
following all of this work instruction.
o Signing the commissioning schemes of AC Distribution Panels, checklists, and
the test formats once tests have been finished after checking all tests’ values
compared with AC Distribution Panels in the data schedule, and FAT results.
- The Testing & Commissioning Contractor Engineer is responsible for:
o Providing the following before starting the test:
o Test forms
o Approved schematic drawings (Pre-Check & Commissioning Copies)
o Test equipment valid calibration certificates and it is available in the
Prequalified Testing Equipment/Tools List DS-TS-6450-006-001
o Contractor engineer pre-qualification certificate
o Protection requirement
o Technical Data Schedule
o Approved final settings.
o Approved schematic drawings.
o Performing the testing and commissioning of the AC Distribution Panels using
an approved test equipment in the presence of the CSD witness.
o Signing the commissioning schemes of AC Distribution Panels checklists, and
the test formats once tests have been finished after checking all test values
compared with AC Distribution Panels in the data schedule, nameplate, and FAT
results.
4.0 REFERENCES
Index/Reference
Title
Number
CL-NG-6460-002-048 Checklist for AC Distribution Panels Commissioning
DS-TS-6450-006-001 Prequalified Testing Equipment/Tools List
31-TMSS-02 TMSS for Substation Panels (Document 2)
TES-P-119.30 TES for Substation Design Standards (Document 30)
This document shall comply in accordance with the existing Company’s Rules and Regulations.
Any modifications/discrepancies therein found not conformance shall be declared invalid.
For clarification and verification on this document, contact the following: