Sheet 2

Name: SAIF GALA IBRAHIM


ID: 1211049

QUESTION # 1
A. -CM without risk; the construc4on acts as an agent or advisor
to the owner

-CM at risk; the construc2on manager acts as project coordinator and


general contractor.

Why owner might choose (CM at risk);


• A/E works directly for owner
• Time savings by fast-track delivery.
• Suitable for large complex projects and mul2-phase projects that are 2me
cri2cal.
• Guaranteed maximum price.

B.

ADVANTAGES DISADVANTAGES

- less conflicts between designer and - There is No direct connec2on


contractor. between owner and designer

- enable fast-track delivery. - Cost may be unknown un2l


the end of the design.
- most cost effec2ve.
- Ini2al cost may be higher due
- 2me can be reduced if the design build to increased contractor risk.
overlaps both of design and
construc2on. - Poten2al for compromises in
quality to meet budget.

- Owner responsible for


changes overlaps and gaps in
scope.

C. Construc2on Management (CM AT RISK)


D. Design and build is a fast-track strategy.
QUESTION # 2
A. Fast-Track

B. Tradi-onal

C. D.B.B approach

D. Tradi-onal

E. Fast-Track

QUESTION # 3
A. -Same as Q1
-
QUESTION # 4

A. – (D-B-B), To have the lowest possible cost.

B. – (D-B), fast-track, it will help to catch up with the


sale.