1 ሰኞ
ሳሚንታዊ ዕቅድ ማዘጋጀት እና ሲዲኤስ 9 ወደ ጤና ጣቢያ 100
የኤሌክትሪክ መስመር ለማገናኘት የሚያስፈልጉ መሳሪያዎች
መዘርዘር
የኤሌክትሪክ ኃይል መቆራረጥን ሪኮርድ መሰብሰብ
እና ለሪፖርት ማዘጋጀት::
2 ማክሰኞ
RMU ሳምንታዊ ምርመራ RMU 2.1፣ RMU 2.2፣ 100
( Correctness of nameplate information, Proper RMU 2.3፣ RMU 2.4፣
alignment, foundation fixing and grounding enclosure RMU 2.5
properness, all covers, panels section and doors for paint Rectifier of RMU 2.1
work and proper fit have checked in accordance. Exchanged with rectifier
of RMU 2.3 the RMU
2.1 starts supplying
power for relay.
የኤሌክትሪክ ኃይል መቆራረጥን ሪኮርድ መሰብሰብ እና ለሪፖርት
ማዘጋጀት::
3 ዕሮብ /ሓሙስ
Transformer ሳምንታዊ ምርመራ Temporary transformer 100
( Correctness of nameplate information, Proper have fully inspected and
alignment, foundation fixing and grounding enclosure cleaned from dusty
properness, all covers, panels section and doors for paint particles using blower.
work and proper fit have checked in accordance RMU 1.17፣ RMU 1.18፣
RMU 1.19፣ RMU 1.20፣
RMU ሳምንታዊ ምርመራ RMU 1.21 ፣ RMU 1.22
( Correctness of nameplate information, Proper
alignment, foundation fixing and grounding enclosure
properness, all covers, panels section and doors for paint
work and proper fit have checked in accordance.