Gantt Chart 1
Gantt Chart 1
NO DESCRIPTION JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22 M23 M24
EFFECTIVE DATE
ENGINEERING
1 Calculation
2 Drawing
PROCUREMENT
1 Shell Plate
2 Platform, Stairway etc
3 Nozzle, Flanges & Elbow
4 Material Delivery To Shop
PRE-FABRICATION
PHASE 1
1 Shell Plate
2 Platform, Stairway etc
3 Nozzle, Flanges & Elbow
4 Blasting & Primer
5 Material Delivery to Site
PHASE 2
1 Shell Plate
2 Platform, Stairway etc
3 Nozzle, Flanges & Elbow
4 Blasting & Primer
5 Material Delivery to Site
PETUNJUK PEMBAHAGIAN
FASA
PERLAKSANAAN